jagomart
digital resources
picture1_Excel Sheet Download 7307 | Us Standard One Stop Shop - Standar Format


 183x       Filetype XLSX       File size 0.16 MB       Source: www.nerc.com


File: Excel Sheet Download 7307 | Us Standard One Stop Shop - Standar Format
sheet 1 us standard onestopshop status standard version title with link to project page purpose board adopted date effective date of standard inactive date standards is in the process of ...

icon picture XLSX Filetype Excel XLSX | Posted on 27 Jun 2022 | 3 years ago
Partial file snippet.
Sheet 1: US Standard One-Stop-Shop
Status Standard Version Title
(with Link to Project Page)
Purpose Board Adopted Date Effective Date of Standard Inactive
Date
Standards is in the process of adding the remaining Implemenation Plans. Implementation Plan Related Documents Public Notes
Standards is in the process of adding the remaining FERC Orders. FERC Orders
(Date Issued)
RSAWs
(Enforceable
Standards
Only)
Lessons Learned Compliance Guidance
Inactive BAL-001-1 Real Power Balancing Control Performance To maintain Interconnection steady-state frequency within defined limits by balancing real power demand and supply in real-time. 12/19/2012 4/1/2014 6/30/2016


10/16/2013 RSAW

Mandatory Subject to Enforcement BAL-001-2 Real Power Balancing Control Performance To control Interconnection frequency within defined limits. 08/15/2013 7/1/2016
Implementation Plan
Replaced BAL-001-1 4/16/2015 RSAW

Inactive BAL-001-TRE-1 Primary Frequency Response in the ERCOT Region To maintain Interconnection steady-state frequency within defined limits. 08/15/2013 4/1/2014 6/30/2020 Implementation Plan
Please see the implementation plan for specific compliance dates and timeframes. 1/16/2014


Mandatory Subject to Enforcement BAL-001-TRE-2 Primary Frequency Response in the ERCOT Region To maintain Interconnection steady-state frequency within defined limits. 2/6/2020 7/1/2020
Implementation Plan





Inactive BAL-002-1 Disturbance Control Performance The purpose of the Disturbance Control Standard (DCS) is to ensure the Balancing Authority is able to utilize its Contingency Reserve to balance resources and demand and return Interconnection frequency within defined limits following a Reportable Disturbance. Because generator failures are far more common than significant losses of load and because Contingency Reserve activation does not typically apply to the loss of load, the application of DCS is limited to the loss of supply and does not apply to the loss of load. 08/05/2010 4/1/2012 12/31/2017 Implementation Plan

01/10/2011 RSAW

Inactive BAL-002-1a Disturbance Control Performance The purpose of the Disturbance Control Standard (DCS) is to ensure the Balancing Authority is able to utilize its Contingency Reserve to balance resources and demand and return Interconnection frequency within defined limits following a Reportable Disturbance. Because generator failures are far more common than significant losses of load and because Contingency Reserve activation does not typically apply to the loss of load, the application of DCS is limited to the loss of supply and does not apply to the loss of load. 11/07/2012
2/17/2017 Implementation Plan
BAL-002-1a was never approved or amended by FERC; notice of withdrawal filed 2/2/2017 following FERC approval of BAL-002-2.
RSAW

Inactive BAL-002-2 Disturbance Control Standard – Contingency Reserve for Recovery from a Balancing Contingency Event To ensure the Balancing Authority or Reserve Sharing Group balances resources and demand and returns the Balancing Authority's or Reserve Sharing Group's Area Control Error to defined values (subject to applicable limits) following a Reportable Balancing Contingency Event. 11/5/2015
12/31/2017 Implementation Plan

1/19/2017 RSAW

Inactive BAL-002-2(i) Disturbance Control Standard – Contingency Reserve for Recovery from a Balancing Contingency Event To ensure the Balancing Authority or Reserve Sharing Group balances resources and demand and returns the Balancing Authority's or Reserve Sharing Group's Area Control Error to defined values (subject to applicable limits) following a Reportable Balancing Contingency Event. 8/10/2017 1/1/2018 3/31/2019 Implementation Plan
Replaces BAL-002-2. Changes to the VRFs for Requirements 1 and 2. 10/2/2017 RSAW

Mandatory Subject to Enforcement BAL-002-3 Disturbance Control Standard – Contingency Reserve for Recovery from a Balancing Contingency Event To ensure the Balancing Authority or Reserve Sharing Group balances resources and demand and returns the Balancing Authority's or Reserve Sharing Group's Area Control Error to defined values (subject to applicable limits) following a Reportable Balancing Contingency Event. 8/16/2018 4/1/2019
Implementation Plan CR Form 1 Replaces BAL-002-2(i) 9/25/2018 RSAW

Inactive BAL-002-WECC-2 Contingency Reserve To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions. 11/07/2012 10/1/2014 1/23/2017 Implementation Plan

11/21/2013 N/A

Inactive BAL-002-WECC-2a Contingency Reserve To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions. 11/2/2016 1/24/2017 6/27/2021 Implementation Plan





Mandatory Subject to Enforcement BAL-002-WECC-3 Contingency Reserve To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions. 8/15/2019 6/28/2021
Implementation Plan

4/15/2021


Inactive BAL-003-1.1 Frequency Response and Frequency Bias Setting To require sufficient Frequency Response from the Balancing Authority (BA) to maintain Interconnection Frequency within predefined bounds by arresting frequency deviations and supporting frequency until the frequency is restored to its scheduled value. To provide consistent methods for measuring Frequency Response and determining the Frequency Bias Setting. 2/7/2013 11/13/2015 11/30/2020 Implementation Plan Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard
11/13/2015 RSAW

Mandatory Subject to Enforcement BAL-003-2 Frequency Response and Frequency Bias Setting To require sufficient Frequency Response from the Balancing Authority
(BA) to maintain Interconnection Frequency within predefined bounds by arresting
frequency deviations and supporting frequency until the frequency is restored to its
scheduled value. To provide consistent methods for measuring Frequency Response
and determining the Frequency Bias Setting.
11/5/2019 12/1/2020
Implementation Plan

7/15/2020 RSAWs

Inactive BAL-004-0 Time Error Correction The purpose of this standard is to ensure that Time Error Corrections are conducted in a manner that does not adversely affect the reliability of the Interconnection. 2/8/2005 6/18/2007 4/1/2017 Implementation Plan
The retirement of BAL-004-0 is contingent upon the retirement of NAESB WEQ-006 Manual Time Error Correction Business Practice Standard. 3/16/2007 RSAW

Inactive BAL-004-WECC-02 Automatic Time Error Correction To maintain Interconnection frequency and to ensure that Time Error Corrections and Primary Inadvertent Interchange (PII) payback are effectively conducted in a manner that does not adversely affect the reliability of the Interconnection. 12/19/2012 4/1/2014 9/30/2018

Replaced by BAL-004-WECC-3 10/16/2013 N/A

Mandatory Subject to Enforcement BAL-004-WECC-3 Automatic Time Error Correction To maintain Interconnection frequency and to ensure that Time Error Corrections and Primary Inadvertent Interchange (PII) payback are effectively conducted in a manner that does not adversely affect the reliability of the Interconnection. 2/8/2018 10/1/2018
Implementation Plan

5/30/2018


Inactive BAL-005-0.2b Automatic Generation Control This standard establishes requirements for Balancing Authority Automatic Generation Control (AGC) necessary to calculate Area Control Error (ACE) and to routinely deploy the Regulating Reserve. The standard also ensures that all facilities and load electrically synchronized to the Interconnection are included within the metered boundary of a Balancing Area so that balancing of resources and demand can be achieved. 3/8/2012 9/13/2012 12/31/2018 Implementation Plan

9/13/2012 RSAW

Mandatory Subject to Enforcement BAL-005-1 Balancing Authority Control This standard establishes requirements for acquiring data necessary to calculate Reporting Area Control Error (Reporting ACE). The standard also specifies a minimum periodicity, accuracy, and availability requirement for acquisition of the data and for providing the information to the System Operator. 2/11/2016 1/1/2019
Implementation Plan

9/20/2017 RSAW

Inactive BAL-006-2 Inadvertent Interchange This standard defines a process for monitoring Balancing Authorities to ensure that, over the long term, Balancing Authority Areas do not excessively depend on other Balancing Authority Areas in the Interconnection for meeting their demand or Interchange obligations. 11/5/2009 4/1/2011 12/31/2018 Implementation Plan
Requirement 3 becomes inactive 12/31/2018. Other requirements become inactive 1/1/2019. 1/06/2011 RSAW

Mandatory Subject to Enforcement BAL-502-RF-03 Planning Resource Adequacy Analysis, Assessment and Documentation To establish common criteria, based on “one day in ten year” loss of Load
expectation principles, for the analysis, assessment and documentation of Resource Adequacy for Load in the ReliabilityFirst Corporation (RF) region
8/10/2017 1/1/2018







Inactive BAL-502-RFC-02 Planning Resource Adequacy Analysis, Assessment and Documentation To establish common criteria, based on “one day in ten year” loss of Load expectation principles, for the analysis, assessment and documentation of Resource Adequacy for Load in the ReliabilityFirst Corporation (RFC) region. 8/5/2009 5/23/2011 12/31/2017 Implementation Plan

3/17/2011 N/A

Inactive CIP-002-3 Cyber Security — Critical Cyber Asset Identification NERC Standards CIP-002-3 through CIP-009-3 provide a cyber security framework for the identification and protection of Critical Cyber Assets to support reliable operation of the Bulk Electric System.
These standards recognize the differing roles of each entity in the operation of the Bulk Electric System, the criticality and vulnerability of the assets needed to manage Bulk Electric System reliability, and the risks to which they are exposed.
Business and operational demands for managing and maintaining a reliable Bulk Electric System increasingly rely on Cyber Assets supporting critical reliability functions and processes to communicate with each other, across functions and organizations, for services and data. This results in increased risks to these Cyber Assets.
Standard CIP-002-3 requires the identification and documentation of the Critical Cyber Assets associated with the Critical Assets that support the reliable operation of the Bulk Electric System. These Critical Assets are to be identified through the application of a risk-based assessment.
12/16/2009 10/1/2010 6/30/2016 Implementation Plan

3/31/2010 RSAW

Inactive CIP-002-3b Cyber Security — Critical Cyber Asset Identification NERC Standards CIP-002-3 through CIP-009-3 provide a cyber security framework for the identification and protection of Critical Cyber Assets to support reliable operation of the Bulk Electric System.
These standards recognize the differing roles of each entity in the operation of the Bulk Electric System, the criticality and vulnerability of the assets needed to manage Bulk Electric System reliability, and the risks to which they are exposed.
Business and operational demands for managing and maintaining a reliable Bulk Electric System increasingly rely on Cyber Assets supporting critical reliability functions and processes to communicate with each other, across functions and organizations, for services and data. This results in increased risks to these Cyber Assets.
Standard CIP-002-3 requires the identification and documentation of the Critical Cyber Assets associated with the Critical Assets that support the reliable operation of the Bulk Electric System. These Critical Assets are to be identified through the application of a risk-based assessment.
2/7/2013
6/30/2016 Implementation Plan


RSAW

Inactive CIP-002-5.1 Cyber Security — BES Cyber System Categorization To identify and categorize BES Cyber Systems and their associated BES Cyber Assets for the application of cyber security requirements commensurate with the adverse impact that loss, compromise, or misuse of those BES Cyber Systems could have on the reliable operation of the BES. Identification and categorization of BES Cyber Systems support appropriate protection against compromises that could lead to misoperation or instability in the BES. 9/27/2013 7/1/2016 12/26/2016 Implementation Plan
Errata approved by the SC on 9/27/2013.
See also CIP V5 Effective Dates here under Key Resources: http://www.nerc.com/pa/CI/Pages/Transition-Program.aspx
11/22/2013 RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Mandatory Subject to Enforcement CIP-002-5.1a Cyber Security - BES Cyber System Categorization To identify and categorize BES Cyber Systems and their associated BES Cyber Assets for the application of cyber security requirements commensurate with the adverse impact that loss, compromise, or misuse of those BES Cyber Systems could have on the reliable operation of the BES. Identification and categorization of BES Cyber Systems support appropriate protection against compromises that could lead to misoperation or instability in the BES. 11/2/2016 12/27/2016
Implementation Plan Interpretation Interpretation of CIP-002-5.1 for Energy Sector Security Consortium (EnergySec)
RSAW
2/9/2018
Inactive CIP-002-6 Cyber Security - BES Cyber System Categorization To identify and categorize BES Cyber Systems and their associated BES
Cyber Assets for the application of cyber security requirements commensurate with the adverse impact that loss, compromise, or misuse of those BES Cyber Systems could have on the reliable operation of the BES. Identification and categorization of BES Cyber Systems support appropriate protection against compromises that could lead to misoperation or instability in the BES.
5/14/2020
2/4/2021 Implementation Plan
Withdrawn as of 2/4/2021



Inactive CIP-003-3 Cyber Security — Security Management Controls Standard CIP-003-3 requires that Responsible Entities have minimum security management controls in place to protect Critical Cyber Assets. Standard CIP-003-3 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 12/16/2009 10/1/2010 6/30/2016 Implementation Plan

3/31/2010 RSAW

Inactive CIP-003-3a Cyber Security — Security Management Controls Standard CIP-003-3 requires that Responsible Entities have minimum security management controls in place to protect Critical Cyber Assets. Standard CIP-003-3 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 11/7/2013
6/30/2016 Implementation Plan


RSAW

Inactive CIP-003-5 Cyber Security — Security Management Controls To specify consistent and sustainable security management controls that establish responsibility and accountability to protect BES Cyber Systems against compromise that could lead to misoperation or instability in the BES. 11/26/2012
6/30/2016 Implementation Plan

11/22/2013
CIP Version 5 Transition Program
Inactive CIP-003-6 Cyber Security — Security Management Controls To specify consistent and sustainable security management controls that establish responsibility and accountability to protect BES Cyber Systems against compromise that could lead to misoperation or instability in the Bulk Electric System (BES). 2/12/2015 7/1/2016 12/31/2019 Implementation Plan
With the approval of CIP-003-7 and its associated Implementation Plan, entities will not be required to implement CIP-003-6, Requirement R2, Attachment 1, Sections 2 and 3. Instead, entities will implement CIP-003-7, Requirement R2, Attachment 1 Sections 2 and 3 on January 1, 2020. See Implementation Plan for CIP-003-7.

CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Inactive CIP-003-7 Cyber Security — Security Management Controls To specify consistent and sustainable security management controls that establish responsibility and accountability to protect BES Cyber Systems against compromise that could lead to misoperation or instability in the Bulk Electric System (BES). 2/9/2017 1/1/2020 3/31/2020 Implementation Plan

4/19/2018


Mandatory Subject to Enforcement CIP-003-8 Cyber Security — Security Management Controls To specify consistent and sustainable security management controls that establish responsibility and accountability to protect BES Cyber Systems against compromise that could lead to misoperation or instability in the Bulk Electric System (BES). 5/9/2019 4/1/2020
Implementation Plan

7/31/2019


Inactive CIP-004-3a Cyber Security — Personnel & Training Standard CIP-004-3 requires that personnel having authorized cyber or authorized unescorted physical access to Critical Cyber Assets, including contractors and service vendors, have an appropriate level of personnel risk assessment, training, and security awareness. Standard CIP-004-3 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 5/24/2012 12/12/2012 6/30/2016 Implementation Plan

12/12/2012 RSAW

Inactive CIP-004-5.1 Cyber Security — Personnel & Training To minimize the risk against compromise that could lead to misoperation or instability in the BES from individuals accessing BES Cyber Systems by requiring an appropriate level of personnel risk assessment, training, and security awareness in support of protecting BES Cyber Systems. 9/27/2013
6/30/2016 Implementation Plan
Errata approved by the SC on 9/27/2013 11/22/2013
CIP Version 5 Transition Program
Mandatory Subject to Enforcement CIP-004-6 Cyber Security — Personnel & Training To minimize the risk against compromise that could lead to misoperation or instability in the Bulk Electric System (BES) from individuals accessing BES Cyber Systems by requiring an appropriate level of personnel risk assessment, training, and security awareness in support of protecting BES Cyber Systems. 2/12/2015 7/1/2016
Implementation Plan
Located under Key Resources: CIP V5 Effective Dates
RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Filed and Pending Regulatory Approval CIP-004-7 Cyber Security — Personnel & Training To minimize the risk against compromise that could lead to misoperation or
instability in the Bulk Electric System (BES) from individuals accessing BES Cyber Systems by requiring an appropriate level of personnel risk assessment, training, security awareness, and access management in support of protecting BES Cyber Systems.
8/12/2021

Implementation Plan





Inactive CIP-005-3a Cyber Security — Electronic Security Perimeter(s) Standard CIP-005-3 requires the identification and protection of the Electronic Security Perimeter(s) inside which all Critical Cyber Assets reside, as well as all access points on the perimeter. Standard CIP-005-3 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 2/16/2010 2/2/2011 6/30/2016 Implementation Plan

2/02/2011 RSAW

Inactive CIP-005-5 Cyber Security — Electronic Security Perimeter(s) To manage electronic access to BES Cyber Systems by specifying a controlled Electronic Security Perimeter in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the BES. 11/26/2012 7/1/2016 9/30/2020 Implementation Plan
Located under Key Resources: CIP V5 Effective Dates 11/22/2013 RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Mandatory Subject to Enforcement CIP-005-6 Cyber Security - Electronic Perimeter(s) To manage electronic access to BES Cyber Systems by specifying a
controlled Electronic Security Perimeter in support of protecting BES Cyber Systems
against compromise that could lead to misoperation or instability in the BES.
8/10/2017 10/1/2020 9/30/2022 Implementation Plan
Effective dates delayed due to COVID-19 per FERC Order (https://www.nerc.com/FilingsOrders/us/FERCOrdersRules/order granting motion to defer the implementation dates.pdf). 10/28/2018 RSAW
3/25/2021: Compliance Guidance Updates
Subject to Future Enforcement CIP-005-7 Cyber Security — Electronic Security Perimeter(s) To manage electronic access to BES Cyber Systems by specifying a controlled Electronic Security Perimeter in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the BES. 11/5/2020 10/1/2022
Implementation Plan

3/18/2021

3/25/2021: Compliance Guidance Updates
Inactive CIP-006-3c Cyber Security — Physical Security of Critical Cyber Assets Standard CIP-006-3 is intended to ensure the implementation of a physical security program for the protection of Critical Cyber Assets. Standard CIP-006-3 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 2/16/2010 5/19/2011 6/30/2016 Implementation Plan

5/19/2011 RSAW

Inactive CIP-006-5 Cyber Security — Physical Security of BES Cyber Systems To manage physical access to BES Cyber Systems by specifying a physical security plan in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the BES. 11/26/2012
6/30/2016 Implementation Plan

11/22/2013
CIP Version 5 Transition Program
Mandatory Subject to Enforcement CIP-006-6 Cyber Security — Physical Security of BES Cyber Systems To manage physical access to Bulk Electric System (BES) Cyber Systems by specifying a physical security plan in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the BES. 11/13/2014 7/1/2016
Implementation Plan
Located under Key Resources: CIP V5 Effective Dates
RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Inactive CIP-007-3a Cyber Security — Systems Security Management Standard CIP-007-3 requires Responsible Entities to define methods, processes, and procedures for securing those systems determined to be Critical Cyber Assets, as well as the other (non-critical) Cyber Assets within the Electronic Security Perimeter(s). Standard CIP-007-3 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 12/16/2009 10/1/2010 6/30/2016 Implementation Plan
The version number was updated from CIP-007-3 to CIP-007-3a to incorporate the approved interpretation that should have previously been appended. 3/31/2010 RSAW

Inactive CIP-007-3b Cyber Security — Systems Security Management Standard CIP-007-3 requires Responsible Entities to define methods, processes, and procedures for securing those systems determined to be Critical Cyber Assets, as well as the other (non-critical) Cyber Assets within the Electronic Security Perimeter(s). Standard CIP-007-3 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 11/7/2013
6/30/2016 Implementation Plan


RSAW

Inactive CIP-007-5 Cyber Security — System Security Management To manage system security by specifying select technical, operational, and procedural requirements in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the BES. 11/26/2012
6/30/2016 Implementation Plan

11/22/2013
CIP Version 5 Transition Program
Mandatory Subject to Enforcement CIP-007-6 Cyber Security — System Security Management To manage system security by specifying select technical, operational, and procedural requirements in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the Bulk Electric System (BES). 2/12/2015 7/1/2016
Implementation Plan
Located under Key Resources: CIP V5 Effective Dates
RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Inactive CIP-008-3 Cyber Security — Incident Reporting and Response Planning Standard CIP-008-3 ensures the identification, classification, response, and reporting of Cyber Security Incidents related to Critical Cyber Assets. Standard CIP-008-23 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 12/16/2009 10/1/2010 6/30/2016 Implementation Plan

3/31/2010 RSAW

Inactive CIP-008-5 Cyber Security — Incident Reporting and Response Planning To mitigate the risk to the reliable operation of the BES as the result of a Cyber Security Incident by specifying incident response requirements. 11/26/2012 7/1/2016 12/31/2020 Implementation Plan
Located under Key Resources: CIP V5 Effective Dates 11/22/2013 RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Mandatory Subject to Enforcement CIP-008-6 Cyber Security — Incident Reporting and Response Planning To mitigate the risk to the reliable operation of the BES as the result of a Cyber Security Incident by specifying incident response requirements. 2/7/2019 1/1/2021
Implementation Plan

6/20/2019 RSAW
11/12/2020: Compliance Guidance Updates
Inactive CIP-009-3 Cyber Security — Recovery Plans for Critical Cyber Assets Standard CIP-009-3 ensures that recovery plan(s) are put in place for Critical Cyber Assets and that these plans follow established business continuity and disaster recovery techniques and practices. Standard CIP-009-3 should be read as part of a group of standards numbered Standards CIP-002-3 through CIP-009-3. 12/16/2009 10/1/2010 6/30/2016 Implementation Plan

3/31/2010 RSAW

Inactive CIP-009-5 Cyber Security — Recovery Plans for BES Cyber Systems To recover reliability functions performed by BES Cyber Systems by specifying recovery plan requirements in support of the continued stability, operability, and reliability of the BES. 11/26/2012
6/30/2016 Implementation Plan

11/22/2013
CIP Version 5 Transition Program
Mandatory Subject to Enforcement CIP-009-6 Cyber Security — Recovery Plans for BES Cyber Systems To recover reliability functions performed by BES Cyber Systems by specifying recovery plan requirements in support of the continued stability, operability, and reliability of the BES. 11/13/2014 7/1/2016
Implementation Plan
Located under Key Resources: CIP V5 Effective Dates
RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Inactive CIP-010-1 Cyber Security — Configuration Change Management and Vulnerability Assessments To prevent and detect unauthorized changes to BES Cyber Systems by specifying configuration change management and vulnerability assessment requirements in support of protecting BES Cyber Systems from compromise that could lead to misoperation or instability in the BES. 11/26/2012
6/30/2016 Implementation Plan

11/22/2013
CIP Version 5 Transition Program
Inactive CIP-010-2 Cyber Security — Configuration Change Management and Vulnerability Assessments To prevent and detect unauthorized changes to BES Cyber Systems by specifying configuration change management and vulnerability assessment requirements in support of protecting BES Cyber Systems from compromise that could lead to misoperation or instability in the Bulk Electric System (BES). 2/12/2015 7/1/2016 9/30/2020 Implementation Plan
Located under Key Resources: CIP V5 Effective Dates
RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Mandatory Subject to Enforcement CIP-010-3 Cyber Security - Configuration Change Management and Vulnerability To prevent and detect unauthorized changes to BES Cyber Systems by
specifying configuration change management and vulnerability assessment
requirements in support of protecting BES Cyber Systems from compromise that
could lead to misoperation or instability in the Bulk Electric System (BES).
8/10/2017 10/1/2020 9/30/2022 Implementation Plan
Effective dates delayed due to COVID-19 per FERC Order (https://www.nerc.com/FilingsOrders/us/FERCOrdersRules/order granting motion to defer the implementation dates.pdf). 10/28/2018 RSAW
2/8/2018
Subject to Future Enforcement CIP-010-4 Cyber Security — Configuration Change Management and Vulnerability Assessments To prevent and detect unauthorized changes to BES Cyber Systems by specifying configuration change management and vulnerability assessment requirements in support of protecting BES Cyber Systems from compromise that could lead to misoperation or instability in the Bulk Electric System (BES). 11/5/2020 10/1/2022
Implementation Plan

3/18/2021

3/25/2021: Compliance Guidance Updates
Inactive CIP-011-1 Cyber Security — Information Protection To prevent unauthorized access to BES Cyber System Information by specifying information protection requirements in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the BES. 11/26/2012
6/30/2016 Implementation Plan

11/22/2013
CIP Version 5 Transition Program
Mandatory Subject to Enforcement CIP-011-2 Cyber Security — Information Protection To prevent unauthorized access to BES Cyber System Information by specifying information protection requirements in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the Bulk Electric System (BES). 2/12/2015 7/1/2016
Implementation Plan
Located under Key Resources: CIP V5 Effective Dates
RSAW CIP Version 5 Transition Program 5/20/2016: Compliance Guidance Updates
Filed and Pending Regulatory Approval CIP-011-3 Cyber Security — Information Protection To prevent unauthorized access to BES Cyber System Information (BCSI) by specifying information protection requirements in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the Bulk Electric System (BES). 8/12/2021

Implementation Plan





Subject to Future Enforcement CIP-012-1 Cyber Security – Communications between Control Centers To protect the confidentiality and integrity of Real-time Assessment and Real-time monitoring data transmitted between Control Centers. 8/16/2018 7/1/2022
Implementation Plan




11/12/2020
Mandatory Subject to Enforcement CIP-013-1 Cyber Security - Supply chain Risk Management To mitigate cyber security risks to the reliable operation of the Bulk
Electric System (BES) by implementing security controls for supply chain risk
management of BES Cyber Systems.
8/10/2017 10/1/2020 9/30/2022 Implementation Plan
Effective dates delayed due to COVID-19 per FERC Order (https://www.nerc.com/FilingsOrders/us/FERCOrdersRules/order granting motion to defer the implementation dates.pdf). 10/28/2018 RSAW
6/7/2017
Subject to Future Enforcement CIP-013-2 Cyber Security - Supply Chain Risks To mitigate cyber security risks to the reliable operation of the Bulk Electric System (BES) by implementing security controls for supply chain risk management of BES Cyber Systems. 11/5/2020 10/1/2022
Implementation Plan

3/18/2021

3/25/2021: Compliance Guidance Updates
Inactive CIP-014-1 Physical Security To identify and protect Transmission stations and Transmission substations, and their associated primary control centers, that if rendered inoperable or damaged as a result of a physical attack could result in widespread instability, uncontrolled separation, or Cascading within an Interconnection. 5/13/2014 10/1/2015 10/1/2015 Implementation Plan

11/20/2014

10/28/16: Compliance Guidance Updates
Mandatory Subject to Enforcement CIP-014-2 Physical Security To identify and protect Transmission stations and Transmission substations, and their associated primary control centers, that if rendered inoperable or damaged as a result of a physical attack could result in instability, uncontrolled separation, or Cascading within an Interconnection. 5/7/2015 10/2/2015
Implementation Plan

7/14/2015 RSAW

Inactive COM-001-1.1 Telecommunications Each Reliability Coordinator, Transmission Operator and Balancing Authority needs adequate and reliable telecommunications facilities internally and with others for the exchange of Interconnection and operating information necessary to maintain reliability. 10/29/2008 5/13/2009 9/30/2015 Implementation Plan
Requirement R4 becomes inactive 6/30/2016 5/13/2009


Inactive COM-001-2.1 Communications To establish Interpersonal Communication capabilities necessary to maintain reliability. 11/7/2012 11/13/2015 9/30/2017 Implementation Plan

11/13/2015 RSAW

Mandatory Subject to Enforcement COM-001-3 Communications To establish Interpersonal Communication capabilities necessary to
maintain reliability.
8/11/2016 10/1/2017
Implementation Plan


RSAW

Inactive COM-002-2 Communication and Coordination To ensure Balancing Authorities, Transmission Operators, and Generator Operators have adequate communications and that these communications capabilities are staffed and available for addressing a real-time emergency condition. To ensure communications by operating personnel are effective. 11/1/2006 6/18/2007 6/30/2016 Implementation Plan

3/16/2007 RSAW

Inactive COM-002-2a Communication and Coordination To ensure Balancing Authorities, Transmission Operators, and Generator Operators have adequate communications and that these communications capabilities are staffed and available for addressing a real-time emergency condition. To ensure communications by operating personnel are effective. 2/9/2012
6/30/2016 Implementation Plan


RSAW

Inactive COM-002-3 Communication and Coordination To ensure Emergency communications between operating personnel are effective. 11/7/2012
6/30/2016 Implementation Plan





Mandatory Subject to Enforcement COM-002-4 Operating Personnel Communications Protocols To improve communications for the issuance of Operating Instructions with predefined communications protocols to reduce the possibility of miscommunication that could lead to action or inaction harmful to the reliability of the Bulk Electric System (BES). 5/7/2014 7/1/2016
Implementation Plan

4/16/2015 RSAW

Inactive EOP-001-2.1b Emergency Operations Planning Each Transmission Operator and Balancing Authority needs to develop, maintain, and implement a set of plans to mitigate operating emergencies. These plans need to be coordinated with other Transmission Operators and Balancing Authorities, and the Reliability Coordinator. 3/8/2012 7/1/2013 3/31/2017 Implementation Plan
EOP-011-1 consolidates the requirements in three existing Reliability Standards: EOP-001-2.1b, EOP-002-3.1 and EOP-003-2 into a single Reliability Standard. 9/13/2012 RSAW

Inactive EOP-002-3.1 Capacity and Energy Emergencies To ensure Reliability Coordinators and Balancing Authorities are prepared for capacity and energy emergencies. 3/8/2012 9/13/2012 3/31/2017 Implementation Plan
EOP-011-1 consolidates the requirements in three existing Reliability Standards: EOP-001-2.1b, EOP-002-3.1 and EOP-003-2 into a single Reliability Standard. 9/13/2012 RSAW

Inactive EOP-003-2 Load Shedding Plans A Balancing Authority and Transmission Operator operating with insufficient generation or transmission capacity must have the capability and authority to shed load rather than risk an uncontrolled failure of the Interconnection. 11/4/2010 10/1/2013 3/31/2017 Implementation Plan
EOP-011-1 consolidates the requirements in three existing Reliability Standards: EOP-001-2.1b, EOP-002-3.1 and EOP-003-2 into a single Reliability Standard. 5/07/2012 RSAW

Inactive EOP-004-2 Event Reporting To improve the reliability of the Bulk Electric System by requiring the reporting of events by Responsible Entities. 11/7/2012 1/1/2014 3/31/2017 Implementation Plan

6/20/2013 RSAW

Inactive EOP-004-3 Event Reporting To improve the reliability of the Bulk Electric System by requiring the reporting of events by Responsible Entities. 11/13/2014 4/1/2017 3/31/2019 Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW

Mandatory Subject to Enforcement EOP-004-4 Event Reporting To improve the reliability of the Bulk Electric System by requiring the reporting of events by Responsible Entities. 2/9/2017 4/1/2019
Implementation Plan

1/18/2018 RSAW

Inactive EOP-005-2 System Restoration from Blackstart Resources Ensure plans, Facilities, and personnel are prepared to enable System restoration from Blackstart Resources to assure reliability is maintained during restoration and priority is placed on restoring the Interconnection. 8/5/2009 7/1/2013 3/31/2019 Implementation Plan

3/17/2011 RSAW

Mandatory Subject to Enforcement EOP-005-3 System Restoration from Blackstart Resources Ensure plans, Facilities, and personnel are prepared to enable System restoration from Blackstart Resources to ensure reliability is maintained during restoration and priority is placed on restoring the Interconnection. 2/9/2017 4/1/2019
Implementation Plan

1/18/2018 RSAW

Inactive EOP-006-2 System Restoration Coordination Ensure plans are established and personnel are prepared to enable effective coordination of the System restoration process to ensure reliability is maintained during restoration and priority is placed on restoring the Interconnection. 8/5/2009 7/1/2013 3/31/2019 Implementation Plan

3/17/2011 RSAW

Mandatory Subject to Enforcement EOP-006-3 System Restoration Coordination Ensure plans are established and personnel are prepared to enable effective coordination of the System restoration process to ensure reliability is maintained during restoration and priority is placed on restoring the Interconnection. 2/9/2017 4/1/2019
Implementation Plan

1/18/2018 RSAW

Inactive EOP-008-1 Loss of Control Center Functionality Ensure continued reliable operations of the Bulk Electric System (BES) in the event that a control center becomes inoperable. 8/5/2010 7/1/2013 3/31/2019 Implementation Plan

4/21/2011 RSAW

Mandatory Subject to Enforcement EOP-008-2 Loss of Control Center Functionality Ensure continued reliable operations of the Bulk Electric System (BES) in the event that a control center becomes inoperable. 2/9/2017 4/1/2019
Implementation Plan

1/18/2018 RSAW

Mandatory Subject to Enforcement EOP-010-1 Geomagnetic Disturbance Operations To mitigate the effects of geomagnetic disturbance (GMD) events by implementing Operating Plans, Processes, and Procedures. 11/7/2013 4/1/2015
Implementation Plan
A FERC order was issued on June 19, 2014, approving EOP-010-1. Requirement 2 of Reliability Standard EOP-010-1 will not become effective until the first day following retirement of Reliability Standard IRO-005-3.1a. 6/19/2014 RSAW

Mandatory Subject to Enforcement EOP-011-1 Emergency Operations To address the effects of operating Emergencies by ensuring each Transmission Operator and Balancing Authority has developed Operating Plan(s) to mitigate operating Emergencies, and that those plans are coordinated within a Reliability Coordinator Area. 11/13/2014 4/1/2017 3/31/2023 Implementation Plan
EOP-011-1 consolidates the requirements in three existing Reliability Standards: EOP-001-2.1b, EOP-002-3.1 and EOP-003-2 into a single Reliability Standard. 11/19/2015 RSAW

Manadatory Subject to Future Enforcement EOP-011-2 Emergency Preparedness and Operations To address the effects of operating emergencies by ensuring each Transmission Operator, Balancing Authority, and Generator Owner has developed plan(s) to mitigate operating Emergencies and that those plans are implemented and coordinated within the Reliability Coordinator Area as specified within the requirements. 6/11/2021 4/1/2023
Implementation Plan

8/24/2021


Inactive FAC-001-2 Facility Interconnection Requirements To avoid adverse impacts on the reliability of the Bulk Electric System, Transmission Owners and applicable Generator Owners must document and make Facility interconnection requirements available so that entities seeking to interconnect will have the necessary information. 8/14/2014 1/1/2016 12/31/2018 Implementation Plan

11/6/2014 RSAW

Mandatory Subject to Enforcement FAC-001-3 Facility Interconnection Requirements To avoid adverse impacts on the reliability of the Bulk Electric System, Transmission Owners and applicable Generator Owners must document and make Facility interconnection requirements available so that entities seeking to interconnect will have the necessary information. 2/11/2016 1/1/2019
Implementation Plan
FERC approved an errata to NERC’s petition on 2/19/2021 2/19/2021 RSAW

Inactive FAC-002-2 Facility Interconnection Studies To study the impact of interconnecting new or materially modified Facilities on the Bulk Electric System. 8/14/2014 1/1/2016 3/31/2021 Implementation Plan

11/6/2014 RSAW

Mandatory Subject to Enforcement FAC-002-3 Facility Interconnection Studies To study the impact of interconnecting new or materially modified Facilities on the Bulk Electric System. 2/6/2020 4/1/2021
Implementation Plan

10/30/2020 RSAW

Inactive FAC-003-3 Transmission Vegetation Management To maintain a reliable electric transmission system by using a defense-in-depth strategy to manage vegetation located on transmission rights of way (ROW) and minimize encroachments from vegetation located adjacent to the ROW, thus preventing the risk of those vegetation-related outages that could lead to Cascading. 5/9/2012 7/1/2014 9/30/2016 Implementation Plan
A FERC order was issued on September 19, 2013, approving FAC-003-3. This standard becomes enforceable on July 1, 2014 for Transmission Owners. For Generator Owners, R3 becomes enforceable on January 1, 2015 and all other requirements (R1, R2, R4, R5, R6, and R7) will become enforceable on January 1, 2016. 9/19/2013 RSAW
10/28/16: Compliance Guidance Updates
Mandatory Subject to Enforcement FAC-003-4 Transmission Vegetation Management To maintain a reliable electric transmission system by using a defense-in-depth strategy to manage vegetation located on transmission rights of way (ROW) and minimize encroachments from vegetation located adjacent to the ROW, thus preventing the risk of those vegetation-related outages that could lead to Cascading. 2/11/2016 10/1/2016
Implementation Plan


RSAW

Filed and Pending Regulatory Approval FAC-003-5 Transmission Vegetation Management To maintain a reliable electric transmission system by using a defense‐ in‐depth strategy to manage vegetation located on transmission rights of way (ROW) and minimize encroachments from vegetation located adjacent to the ROW, thus preventing the risk of those vegetation‐ related outages that could lead to Cascading.  5/13/2021

Implementation Plan

6/28/2021


Inactive FAC-008-3 Facility Ratings To ensure that Facility Ratings used in the reliable planning and operation of the Bulk Electric System (BES) are determined based on technically sound principles. A Facility Rating is essential for the determination of System Operating Limits. 5/24/2011 1/1/2013 9/30/2021 Implementation Plan

11/17/2011 RSAW
10/10/2017
Inactive FAC-008-4 Facility Ratings To ensure that Facility Ratings used in the reliable planning and operation of the Bulk Electric System (BES) are determined based on technically sound principles. A Facility Rating is essential for the determination of System Operating Limits. 5/9/2019
2/4/2021 Implementation Plan
FERC remanded proposed Reliability Standard FAC-008-4 to NERC for further consideration. Withdrawn February 4, 2021



Mandatory Subject to Enforcement FAC-008-5 Facility Ratings To ensure that Facility Ratings used in the reliable planning and operation of the Bulk Electric System (BES) are determined based on technically sound principles. A Facility Rating is essential for the determination of System Operating Limits. 2/4/2021 10/1/2021
Implementation Plan

4/7/2021 RSAW

Inactive FAC-010-2.1 System Operating Limits Methodology for the Planning Horizon To ensure that System Operating Limits (SOLs) used in the reliable planning of the Bulk Electric System (BES) are determined based on an established methodology or methodologies. 11/5/2009 4/19/2010 3/31/2017


4/19/2010 RSAW

Mandatory Subject to Enforcement FAC-010-3 System Operating Limits Methodology for the Planning Horizon To ensure that System Operating Limits (SOLs) used in the reliable planning of the Bulk Electric System (BES) are determined based on an established methodology or methodologies. 11/13/2014 4/1/2017
Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW

Inactive FAC-011-2 System Operating Limits Methodology for the Operations Horizon To ensure that System Operating Limits (SOLs) used in the reliable operation of the Bulk Electric System (BES) are determined based on an established methodology or methodologies. 6/24/2008 4/29/2009 3/31/2017 Implementation Plan

3/20/2009 RSAW

Mandatory Subject to Enforcement FAC-011-3 System Operating Limits Methodology for the Operations Horizon To ensure that System Operating Limits (SOLs) used in the reliable operation of the Bulk Electric System (BES) are determined based on an established methodology or methodologies. 11/13/2014 4/1/2017
Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW

Filed and Pending Regulatory Approval FAC-011-4 System Operating Limits Methodology for the Operations Horizon To ensure that System Operating Limits (SOLs) used in the reliable operation of the Bulk Electric System (BES) are determined based on an established methodology or methodologies. 5/13/2021

Implementation Plan

6/28/2021


Inactive FAC-013-2 Assessment of Transfer Capability for the Near-Term Transmission Planning Horizon To ensure that Planning Coordinators have a methodology for, and perform an annual assessment to identify potential future Transmission System weaknesses and limiting Facilities that could impact the Bulk Electric System’s (BES) ability to reliably transfer energy in the Near-Term Transmission Planning Horizon. 1/24/2011 4/1/2013 12/14/2020 Implementation Plan

11/17/2011 RSAW

Mandatory Subject to Enforcement FAC-014-2 Establish and Communicate System Operating Limits To ensure that System Operating Limits (SOLs) used in the reliable planning and operation of the Bulk Electric System (BES) are determined based on an established methodology or methodologies. 6/24/2008 4/29/2009
Implementation Plan

3/20/2009 RSAW

Filed and Pending Regulatory Approval FAC-014-3 Establish and Communicate System Operating Limits To ensure that System Operating Limits (SOLs) used in the reliable operation of the Bulk Electric System (BES) are determined based on an established methodology or methodologies and that Planning Assessment performance criteria is coordinated with these methodologies. 5/13/2021

Implementation Plan

6/28/2021


Inactive FAC-501-WECC-1 Transmission Maintenance To ensure the Transmission Owner of a transmission path identified in the table titled “Major WECC Transfer Paths in the Bulk Electric System” including associated facilities has a Transmission Maintenance and Inspection Plan (TMIP); and performs and documents maintenance and inspection activities in accordance with the TMIP. 10/29/2008 7/1/2011 6/30/2018


4/21/2011


Mandatory Subject to Enforcement FAC-501-WECC-2 Transmission Maintenance To ensure the Transmission Owner of a transmission path identified in Attachment B, Major WECC Transfer Paths in the Bulk Electric System, including associated facilities has a Transmission Maintenance and Inspection Plan (TMIP); and performs and documents maintenance and inspection activities in accordance with the TMIP. 2/8/2018 7/1/2018
Implementation Plan

5/30/2018


Inactive INT-004-3.1 Dynamic Transfers To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately in congestion management procedures. 8/20/2014 11/26/2014 12/14/2020 Implementation Plan
Replaced INT-004-3. Requirement R3 will become effective on the first calendar day two calendar quarters after the NAESB Electric Industry Registry is able to accept Pseudo-Tie registrations. All existing and future Pseudo-Ties are to be registered in the NAESB Electric Industry Registry. The retirement date for INT-004-3 and the enforcement date for INT-004-3.1 have been coordinated to ensure seamless transition from the original to the errata Reliability Standard on the date of Commission approval for the errata Reliability Standard. 11/26/2014 RSAW

Inactive INT-006-4 Evaluation of Interchange Transactions To ensure that responsible entities conduct a reliability assessment of each Arranged Interchange before it is implemented. 2/6/2014 10/1/2014 3/31/2021 Implementation Plan
Replaced INT-006-3 6/30/2014 RSAW

Mandatory Subject to Enforcement INT-006-5 Evaluation of Interchange Transactions To ensure that responsible entities conduct a reliability assessment of each Arranged Interchange before it is implemented. 5/9/2019 4/1/2021
Implementation Plan

9/17/2020 RSAW

Inactive INT-009-2.1 Implementation of Interchange To ensure that Balancing Authorities implement the Interchange as agreed upon in the Interchange confirmation process. 8/20/2014 11/26/2014 3/31/2021 Implementation Plan
Replaced INT-009-2. The retirement date for INT-009-2 and the enforcement date for INT-009-2.1 have been coordinated to ensure seamless transition from the original to the errata Reliability Standard on the date of Commission approval for the errata Reliability Standard. 11/26/2014 RSAW

Mandatory Subject to Enforcement INT-009-3 Implementation of Interchange To ensure that Balancing Authorities implement the Interchange as agreed upon in the Interchange confirmation process. 5/9/2019 4/1/2021
Implementation Plan

9/17/2020 RSAW

Inactive INT-010-2.1 Interchange Initiation and Modification for Reliability To provide guidance for required actions on Confirmed Interchange or Implemented Interchange to address reliability. 8/20/2014 11/26/2014 12/14/2020 Implementation Plan
Replaced INT-010-2. The retirement date for INT-010-2 and the enforcement date for INT-010-2.1 have been coordinated to ensure seamless transition from the original to the errata Reliability Standard on the date of Commission approval for the errata Reliability Standard. 11/26/2014 RSAW

Inactive INT-011-1.1 Intra-Balancing Authority Transaction Identification To ensure that transfers within a Balancing Authority Area using Point to Point Transmission Service are communicated and accounted for in congestion management procedures. 8/20/2014 11/26/2014 10/15/2015 Implementation Plan
Replaced INT-011-1. The retirement date for INT-011-1 and the enforcement date for INT-011-1.1 have been coordinated to ensure seamless transition from the original to the errata Reliability Standard on the date of Commission approval for the errata Reliability Standard. 11/26/2014 RSAW

Inactive IRO-001-1.1 Reliability Coordination — Responsibilities and Authorities Reliability Coordinators must have the authority, plans, and agreements in place to immediately direct reliability entities within their Reliability Coordinator Areas to re-dispatch generation, reconfigure transmission, or reduce load to mitigate critical conditions to return the system to a reliable state. If a Reliability Coordinator delegates tasks to others, the Reliability Coordinator retains its responsibilities for complying with NERC and regional standards. Standards of conduct are necessary to ensure the Reliability Coordinator does not act in a manner that favors one market participant over another. 10/29/2008 5/13/2009 3/31/2017 Implementation Plan

5/13/2009 RSAW

Inactive IRO-001-3 Reliability Coordination – Responsibilities and Authorities To establish the authority of Reliability Coordinators to direct other entities to prevent an Emergency or Adverse Reliability Impacts to the Bulk Electric System. 8/16/2012
1/26/2016 Implementation Plan
FERC approved withdrawal of standard



Mandatory Subject to Enforcement IRO-001-4 Reliability Coordination – Responsibilities To establish the responsibility of Reliability Coordinators to act or direct other entities to act. 11/13/2014 4/1/2017
Implementation Plan

11/19/2015 RSAW

Inactive IRO-002-2 Reliability Coordination — Facilities Reliability Coordinators need information, tools and other capabilities to perform their responsibilities. 10/17/2008 10/1/2011 3/31/2017


3/17/2011 RSAW

Inactive IRO-002-3 Reliability Coordination – Analysis Tools To ensure that Reliability Coordinators provide their System Operators with authority with respect to analysis tool outages and to have procedures to mitigate effects of analysis tool outages. 8/4/2011
1/26/2016 Implementation Plan
FERC approved withdrawal of standard



Inactive IRO-002-4 Reliability Coordination – Monitoring and Analysis Provide System Operators with the capabilities necessary to monitor and analyze data needed to perform their reliability functions. 11/13/2014 4/1/2017 9/30/2017 Implementation Plan

11/19/2015 RSAW

Inactive IRO-002-5 Reliability Coordination – Monitoring and Analysis To provide System Operators with the capabilities necessary to monitor and analyze data needed to perform their reliability functions. 2/9/2017 10/1/2017 12/31/2019 Implementation Plan


RSAW
1/8/2021: Compliance Guidance Update
Inactive IRO-002-6 Reliability Coordination - Monitoring and Analysis To provide System Operators with the capabilities necessary to monitor and analyze data needed to perform their reliability functions.

Regional Variance Purpose: To develop a methodology that creates models for performing Operational Planning Analyses and Real-time Assessments.
5/9/2019 1/1/2020 3/31/2021 Implementation Plan


RSAW

Mandatory Subject to Enforcement IRO-002-7 Reliability Coordination - Monitoring and Analysis To provide System Operators with the capabilities necessary to monitor and analyze data needed to perform their reliability functions. 5/9/2019 4/1/2021
Implementation Plan

9/17/2020 RSAW

Inactive IRO-003-2 Reliability Coordination — Wide-Area View The Reliability Coordinator must have a wide-area view of its own Reliability Coordinator Area and that of neighboring Reliability Coordinators. 11/1/2006 6/18/2007 3/31/2017 Implementation Plan

3/16/2007 RSAW

Inactive IRO-004-2 Reliability Coordination — Operations Planning Each Reliability Coordinator must conduct next-day reliability analyses for its Reliability Coordinator Area to ensure the Bulk Electric System can be operated reliably in anticipated normal and Contingency conditions. System studies must be conducted to highlight potential interface and other operating limits, including overloaded transmission lines and transformers, voltage and stability limits, etc. Plans must be developed to alleviate System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL) violations. 10/17/2008 10/1/2011 3/31/2017


3/17/2011 RSAW

Inactive IRO-005-3.1a Reliability Coordination — Current Day Operations The Reliability Coordinator must be continuously aware of conditions within its Reliability Coordinator Area and include this information in its reliability assessments. The Reliability Coordinator must monitor Bulk Electric System parameters that may have significant impacts upon the Reliability Coordinator Area and neighboring Reliability Coordinator Areas. 11/13/2014 9/13/2012 3/31/2017 Implementation Plan

9/13/2012 RSAW

Inactive IRO-005-4 Reliability Coordination — Current Day Operations To ensure that entities are notified when an expected or actual event with Adverse Reliability Impacts is identified. 8/4/2011
1/26/2016 Implementation Plan
FERC approved withdrawal of standard



Mandatory Subject to Enforcement IRO-006-5 Reliability Coordination — Transmission Loading Relief (TLR) To ensure coordinated action between Interconnections when implementing Interconnection-wide transmission loading relief procedures to prevent or manage potential or actual SOL and IROL exceedances to maintain reliability of the bulk electric system. 11/4/2010 7/1/2011
Implementation Plan

4/21/2011 RSAW

Inactive IRO-006-EAST-1 Transmission Loading Relief Procedure for the Eastern Interconnection To provide an Interconnection-wide transmission loading relief procedure (TLR) for the Eastern Interconnection that can be used to prevent and/or mitigate potential or actual System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL) exceedances to maintain reliability of the Bulk Electric System (BES). 11/4/2010 7/1/2011 3/31/2016 Implementation Plan

4/21/2011


Mandatory Subject to Enforcement IRO-006-EAST-2 Transmission Loading Relief Procedure for the Eastern Interconnection To coordinate action between Reliability Coordinators within the Eastern Interconnection when implementing transmission loading relief procedures (TLR) for the Eastern Interconnection to prevent or manage potential or actual System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL) exceedances to maintain reliability of the Bulk Electric System (BES). 8/13/2015 4/1/2016
Implementation Plan

12/4/2015 RSAW

Inactive IRO-006-TRE-1 IROL and SOL Mitigation in the ERCOT Region To provide and execute transmission loading relief procedures that can be used to mitigate SOL or IROL exceedances for the purpose of maintaining reliable operation of the bulk electric system in the ERCOT Region. 11/3/2011 7/1/2012 1/29/2019 Implementation Plan

5/31/2012 N/A

Inactive IRO-006-WECC-2 Qualified Transfer Path Unscheduled Flow (USF) Relief Mitigation of transmission overloads due to unscheduled flow on Qualified Transfer Paths. 2/7/2013 7/1/2014 9/30/2019


5/13/2014 N/A

Mandatory Subject to Enforcement IRO-006-WECC-3 Qualified Path Unscheduled Flow (USF) Relief To mitigate flows on Qualified Paths to reliable levels during Real-time operations. 2/7/2019 10/1/2019
Implementation Plan





Inactive IRO-008-1 Reliability Coordinator Operational Analyses and Real-time Assessments To prevent instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the interconnection by ensuring that the Bulk Electric System is assessed during the operations horizon. 10/17/2008 10/1/2011 3/31/2017 Implementation Plan

3/17/2011 RSAW

Mandatory Subject to Enforcement IRO-008-2 Reliability Coordinator Operational Analyses and Real-time Assessments Perform analyses and assessments to prevent instability, uncontrolled separation, or Cascading. 11/13/2014 4/1/2017
Implementation Plan

11/19/2015 RSAW

Filed and Pending Regulatory Approval IRO-008-3 Reliability Coordinator Operational Analyses and Real-time Assessments Perform analyses and assessments to prevent instability, uncontrolled separation, or Cascading. 5/13/2021

Implementation Plan

6/28/2021


Mandatory Subject to Enforcement IRO-009-2 Reliability Coordinator Actions to Operate Within IROLs To prevent instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the interconnection by ensuring prompt action to prevent or mitigate instances of exceeding Interconnection Reliability Operating Limits (IROLs). 8/13/2015 1/1/2016
Implementation Plan

12/4/2015 RSAW

Inactive IRO-010-1a Reliability Coordinator Data Specification and Collection To prevent instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the interconnection by ensuring the Reliability Coordinator has the data it needs to monitor and assess the operation of its Reliability Coordinator Area. 8/5/2009 10/1/2011 3/31/2017


3/17/2011 RSAW

Inactive IRO-010-2 Reliability Coordinator Data Specification and Collection To prevent instability, uncontrolled separation, or Cascading outages that adversely impact reliability, by ensuring the Reliability Coordinator has the data it needs to monitor and assess the operation of its Reliability Coordinator Area. 11/13/2014 1/1/2017 3/31/2021 Implementation Plan

11/19/2015 RSAW

Mandatory Subject to Enforcement IRO-010-3 Reliability Coordinator Data Specification and Collection To prevent instability, uncontrolled separation, or Cascading outages that adversely impact reliability, by ensuring the Reliability Coordinator has the data it needs to monitor and assess the operation of its Reliability Coordinator Area. 2/6/2020 4/1/2021 3/31/2023 Implementation Plan

10/30/2020 RSAW

Manadatory Subject to Future Enforcement IRO-010-4 Reliability Coordinator Data Specification and Collection To prevent instability, uncontrolled separation, or Cascading outages that adversely impact reliability, by ensuring the Reliability Coordinator has the data it needs to monitor and assess the operation of its Reliability Coordinator Area. 6/11/2021 4/1/2023
Implementation Plan

8/24/2021


Inactive IRO-014-1 Procedures, Processes, or Plans to Support Coordination Between Reliability Coordinators To ensure that each Reliability Coordinator’s operations are coordinated such that they will not have an Adverse Reliability Impact on other Reliability Coordinator Areas and to preserve the reliability benefits of interconnected operations. 2/7/2006 6/18/2007 3/31/2017 Implementation Plan

3/16/2007 RSAW

Inactive IRO-014-2 Coordination Among Reliability Coordinators To ensure that each Reliability Coordinator’s operations are coordinated such that they will not have an Adverse Reliability Impact on other Reliability Coordinator Areas and to preserve the reliability benefits of interconnected operations. 8/4/2011
1/26/2016

FERC approved withdrawal of standard



Mandatory Subject to Enforcement IRO-014-3 Coordination Among Reliability Coordinators To ensure that each Reliability Coordinator’s operations are coordinated such that they will not adversely impact other Reliability Coordinator Areas and to preserve the reliability benefits of interconnected operations. 11/13/2014 4/1/2017
Implementation Plan

11/19/2015 RSAW

Inactive IRO-015-1 Notifications and Information Exchange Between Reliability Coordinators To ensure that each Reliability Coordinator’s operations are coordinated such that they will not have an Adverse Reliability Impact on other Reliability Coordinator Areas and to preserve the reliability benefits of interconnected operations. 2/7/2006 6/18/2007 3/31/2017 Implementation Plan

3/16/2007 RSAW

Inactive IRO-016-1 Coordination of Real-time Activities Between Reliability Coordinators To ensure that each Reliability Coordinator’s operations are coordinated such that they will not have an Adverse Reliability Impact on other Reliability Coordinator Areas and to preserve the reliability benefits of interconnected operations. 2/7/2006 6/18/2007 3/31/2017 Implementation Plan

3/16/2007 RSAW

Mandatory Subject to Enforcement IRO-017-1 Outage Coordination To ensure that outages are properly coordinated in the Operations Planning time horizon and Near-Term Transmission Planning Horizon. 11/13/2014 4/1/2017
Implementation Plan

11/19/2015 RSAW

Inactive IRO-018-1 Reliability Coordinator Real-time Reliability Monitoring and Analysis Capabilities Establish requirements for Real-time monitoring and analysis capabilities to support reliable System operations. 5/5/2016
3/31/2018 Implementation Plan
IRO-018-1(i) became enforceable 4/1/2018, therefore IRO-018-1 will never be enforceable. 9/22/2016


Mandatory Subject to Enforcement IRO-018-1(i) Reliability Coordinator Real-time Reliability Monitoring and Analysis Capabilities Establish requirements for Real-time monitoring and analysis capabilities to support reliable System operations. 11/2/2016 4/1/2018
Implementation Plan
VRF designations for Requirement R1 of IRO-018-1 and Requirements R1 and R2 of TOP-010-1 changed to high.
RSAW

Mandatory Subject to Enforcement MOD-001-1a Available Transmission System Capability To ensure that calculations are performed by Transmission Service Providers to maintain awareness of available transmission system capability and future flows on their own systems as well as those of their neighbors 11/5/2009 4/1/2011
Implementation Plan
On September 16, 2010, FERC issued an order (in Docket No. RD10-5-000) approving an interpretation of MOD-001-1, creating MOD-001-1a. The effective date of April 1, 2011 did not change. 9/16/2010 RSAW

Inactive MOD-001-2 Available Transmission System Capability To ensure that determinations of available transmission system capability are determined in a manner that supports the reliable operation of the Bulk-Power System (BPS) and that the methodology and data underlying those determinations are disclosed to those registered entities that need such information for reliability purposes. 2/6/2014
5/9/2019 Implementation Plan
Petition for approval was withdrawn as part of Project 2018-03 SER Retirements.



Mandatory Subject to Enforcement MOD-004-1 Capacity Benefit Margin To promote the consistent and reliable calculation, verification, preservation, and use of Capacity Benefit Margin (CBM) to support analysis and system operations. 11/13/2008 4/1/2011
Implementation Plan

11/24/2009 RSAW

Mandatory Subject to Enforcement MOD-008-1 Transmission Reliability Margin Calculation Methodology To promote the consistent and reliable calculation, verification, preservation, and use of Transmission Reliability Margin (TRM) to support analysis and system operations. 8/26/2008 4/1/2011
Implementation Plan

11/24/2009 RSAW

Inactive MOD-010-0 Steady-State Data for Modeling and Simulation of the Interconnected Transmission System To establish consistent data requirements, reporting procedures, and system models to be used in the analysis of the reliability of the Interconnected Transmission Systems. 2/8/2005 6/18/2007 6/30/2016 Implementation Plan
MOD-010-0 retires midnight of the day immediately prior to the Effective Date of MOD-032-1, Requirement R2, in the particular Jurisdiction in which the new standard is becoming effective. 3/16/2007 RSAW

Inactive MOD-011-0 Maintenance and Distribution of Steady-State Data Requirements and Reporting Procedures To establish consistent data requirements, reporting procedures, and system models to be used in the analysis of the reliability of the interconnected transmission systems. 2/8/2005
6/30/2016 Implementation Plan
MOD-011-0 retires midnight of the day immediately prior to the Effective Date of MOD-032-1, Requirement R2, in the particular Jurisdiction in which the new standard is becoming effective.



Inactive MOD-012-0 Dynamics Data for Modeling and Simulation of the Interconnected Transmission System. To establish consistent data requirements, reporting procedures, and system models to be used in the analysis of the reliability of the interconnected transmission systems. 2/8/2005 6/18/2007 6/30/2016 Implementation Plan
MOD-012-0 retires midnight of the day immediately prior to the Effective Date of MOD-032-1, Requirement R2, in the particular Jurisdiction in which the new standard is becoming effective. 3/16/2007 RSAW

Inactive MOD-013-1 Maintenance and Distribution of Dynamics Data Requirements and Reporting Procedures To establish consistent data requirements, reporting procedures, and system models to be used in the analysis of the reliability of the interconnected transmission systems. 5/2/2006
6/30/2016 Implementation Plan
MOD-013-1 retires midnight of the day immediately prior to the Effective Date of MOD-032-1, Requirement R2, in the particular Jurisdiction in which the new standard is becoming effective.



Inactive MOD-014-0 Development of Steady-State System Models To establish consistent data requirements, reporting procedures, and system models to be used in the analysis of the reliability of the interconnected transmission systems. 2/8/2005
6/30/2016 Implementation Plan
MOD-014-0 retires midnight of the day immediately prior to the Effective Date of MOD-032-1, Requirement R2, in the particular Jurisdiction in which the new standard is becoming effective.



Inactive MOD-015-0 Development of Dynamics System Models To establish consistent data requirements, reporting procedures, and system models to be used in the analysis of the reliability of the interconnected transmission systems. 2/8/2005
6/30/2016 Implementation Plan
This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Inactive MOD-015-0.1 Development of Dynamics System Models To establish consistent data requirements, reporting procedures, and system models to be used in the analysis of the reliability of the interconnected transmission systems. 10/29/2008
6/30/2016 Implementation Plan
This standard was not approved by FERC in Order 693. MOD-015-0.1 retires midnight of the day immediately prior to the Effective Date of MOD-032-1, Requirement R2, in the particular Jurisdiction in which the new standard is becoming effective.



Inactive MOD-016-1.1 Documentation of Data Reporting Requirements for Actual and Forecast Demands, Net Energy for Load, and Controllable Demand-Side Management Ensure that accurate, actual Demand data is available to support assessments and validation of past events and databases. Forecast Demand data is needed to perform future system assessments to identify the need for system reinforcements for continued reliability. In addition, to assist in proper real-time operating, Load information related to controllable Demand-Side Management (DSM) programs is needed. 10/29/2008 5/13/2009 6/30/2016 Implementation Plan

5/13/2009 RSAW

Inactive MOD-017-0.1 Aggregated Actual and Forecast Demands and Net Energy for Load To ensure that assessments and validation of past events and databases can be performed, reporting of actual Demand data is needed. Forecast demand data is needed to perform future system assessment to identify the need for system reinforcement for continued reliability. In addition to assist in proper real-time operating, load information related to controllable Demand-Side Management programs is needed. 10/29/2008 5/13/2009 6/30/2016 Implementation Plan

5/13/2009 RSAW

Inactive MOD-018-0 Treatment of Nonmember Demand Data and How Uncertainties are Addressed in the Forecasts of Demand and Net Energy for Load To ensure that Assessments and validation of past events and databases can be performed, reporting of actual demand data is needed. Forecast demand data is needed to perform future system assessments to identify the need for system reinforcement for continued reliability. In addition, to assist in proper real-time operating, load information related to controllable Demand-Side Management programs is needed. 2/8/2005 6/18/2007 6/30/2016 Implementation Plan

3/16/2007 RSAW

Inactive MOD-019-0.1 Reporting of Interruptible Demands and Direct Control Load Management To ensure that assessments and validation of past events and databases can be performed, reporting of actual demand data is needed. Forecast demand data is needed to perform future system assessments to identify the need for system reinforcement for continued reliability. In addition, to assist in proper real-time operating, load information related to controllable Demand-Side Management programs is needed. 10/29/2008 5/13/2009 6/30/2016 Implementation Plan

5/13/2009 RSAW

Inactive MOD-020-0 Providing Interruptible Demands and Direct Control Load Management Data to System Operators and Reliability Coordinators To ensure that assessments and validation of past events and databases can be performed, reporting of actual demand data is needed. Forecast demand data is needed to perform future system assessments to identify the need for system reinforcement for continued reliability. In addition to assist in proper real-time operating, load information related to controllable Demand-Side Management programs is needed. 2/8/2005 6/18/2007 12/14/2020 Implementation Plan

3/16/2007 RSAW

Inactive MOD-021-1 Documentation of the Accounting Methodology for the Effects of Demand-Side Management in Demand and Energy Forecasts. To ensure that assessments and validation of past events and databases can be performed, reporting of actual Demand data is needed. Forecast demand data is needed to perform future system assessments to identify the need for system reinforcement for continued reliability. In addition, to assist in proper real-time operating, load information related to Demand-Side Management (DSM) programs is needed. 8/5/2010 4/1/2011 6/30/2016 Implementation Plan

1/10/2011 RSAW

Inactive MOD-024-1 Verification of Generator Gross and Net Real Power Capability To ensure accurate information on generator gross and net Real Power capability is available for steady-state models used to assess Bulk Electric System reliability. 2/7/2006
6/30/2016 Implementation Plan
This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Inactive MOD-025-1 Verification of Generator Gross and Net Reactive Power Capability To ensure accurate information on generator gross and net Reactive Power capability is available for steady-state models used to assess Bulk Electric System reliability. 2/7/2006
6/30/2016 Implementation Plan
This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Mandatory Subject to Enforcement MOD-025-2 Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability To ensure that accurate information on generator gross and net Real and Reactive Power capability and synchronous condenser Reactive Power capability is available for planning models used to assess Bulk Electric System (BES) reliability. 2/7/2013 7/1/2016
Implementation Plan
Please see the Implementation Plan for specific compliance dates and timeframes. 3/20/2014 RSAW
11/12/2020: Compliance Guidance Updates
Mandatory Subject to Enforcement MOD-026-1 Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions To verify that the generator excitation control system or plant volt/var control function model (including the power system stabilizer model and the impedance compensator model) and the model parameters used in dynamic simulations accurately represent the generator excitation control system or plant volt/var control function behavior when assessing Bulk Electric System (BES) reliability. 2/7/2013 7/1/2014
Implementation Plan
Please see the Implementation Plan for specific compliance dates and timeframes. 3/20/2014 RSAW

Mandatory Subject to Enforcement MOD-027-1 Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions To verify that the turbine/governor and load control or active power/frequency control model and the model parameters, used in dynamic simulations that assess Bulk Electric System (BES) reliability, accurately represent generator unit real power response to system frequency variations. 2/7/2013 7/1/2014
Implementation Plan

3/20/2014 RSAW

Mandatory Subject to Enforcement MOD-028-2 Area Interchange Methodology To increase consistency and reliability in the development and documentation of Transfer Capability calculations for short-term use performed by entities using the Area Interchange Methodology to support analysis and system operations. 2/9/2012 10/1/2013
Implementation Plan

7/18/2013 RSAW

Inactive MOD-029-1a Rated System Path Methodology To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term use performed by entities using the Rated System Path Methodology to support analysis and system operations. 11/5/2009 4/1/2011 3/31/2017 Implementation Plan

9/16/2010 RSAW

Mandatory Subject to Enforcement MOD-029-2a Rated System Path Methodology To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term use performed by entities using the Rated System Path Methodology to support analysis and system operations. 11/13/2014 4/1/2017
Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW

Inactive MOD-030-2 Flowgate Methodology To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term use performed by entities using the Flowgate Methodology to support analysis and system operations. 2/10/2009 4/1/2011 3/31/2017 Implementation Plan

11/24/2009 RSAW

Mandatory Subject to Enforcement MOD-030-3 Flowgate Methodology To increase consistency and reliability in the development and documentation of transfer capability calculations for short-term use performed by entities using the Flowgate Methodology to support analysis and system operations. 11/13/2014 4/1/2017
Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW

Inactive MOD-031-1 Demand and Energy Data To provide authority for applicable entities to collect Demand, energy and related data to support reliability studies and assessments and to enumerate the responsibilities and obligations of requestors and respondents of that data. 5/7/2014 7/1/2016 9/30/2016 Implementation Plan

2/19/2015 RSAW

Inactive MOD-031-2 Demand and Energy Data To provide authority for applicable entities to collect Demand, energy and related data to support reliability studies and assessments and to enumerate the responsibilities and obligations of requestors and respondents of that data. 11/5/2015 10/1/2016 3/31/2021 Implementation Plan

2/18/2016 RSAW

Mandatory Subject to Enforcement MOD-031-3 Demand and Energy Data To provide authority for applicable entities to collect Demand, energy and related data to support reliability studies and assessments and to enumerate the responsibilities and obligations of requestors and respondents of that data. 2/6/2020 4/1/2021
Implementation Plan

10/30/2020 RSAW

Mandatory Subject to Enforcement MOD-032-1 Data for Power System Modeling and Analysis To establish consistent modeling data requirements and reporting procedures for development of planning horizon cases necessary to support analysis of the reliability of the interconnected transmission system. 2/6/2014 7/1/2015
Implementation Plan
Please see the implementation plan for specific compliance dates and timeframes. 5/1/2014 RSAW

Inactive MOD-033-1 Steady-State and Dynamic System Model Validation To establish consistent validation requirements to facilitate the collection of accurate data and building of planning models to analyze the reliability of the interconnected transmission system. 2/6/2014 7/1/2017 3/31/2021 Implementation Plan

5/1/2014 RSAW
8/7/2017
Mandatory Subject to Enforcement MOD-033-2 Steady-State and Dynamic System Model Validation To establish consistent validation requirements to facilitate the collection of accurate data and building of planning models to analyze the reliability of the interconnected transmission system. 2/6/2020 4/1/2021
Implementation Plan

10/30/2020 RSAW

Inactive NUC-001-3 Nuclear Plant Interface Coordination This standard requires coordination between Nuclear Plant Generator Operators and Transmission Entities for the purpose of ensuring nuclear plant safe operation and shutdown. 8/14/2014 1/1/2016 3/31/2021 Implementation Plan

11/4/2014 RSAW

Mandatory Subject to Enforcement NUC-001-4 Nuclear Plant Interface Coordination This standard requires coordination between Nuclear Plant Generator Operators and Transmission Entities for the purpose of ensuring nuclear plant safe operation and shutdown. 2/6/2020 4/1/2021
Implementation Plan

10/30/2020 RSAW

Inactive PER-001-0.2 Operating Personnel Responsibility and Authority Transmission Operator and Balancing Authority operating personnel must have the responsibility and authority to implement real-time actions to ensure the stable and reliable operation of the Bulk Electric System. 3/8/2012 9/13/2012 3/31/2017 Implementation Plan

9/13/2012 RSAW

Inactive PER-003-1 Operating Personnel Credentials To ensure that System Operators performing the reliability-related tasks of the Reliability Coordinator, Balancing Authority and Transmission Operator are certified through the NERC System Operator Certification Program when filling a Real-time operating position responsible for control of the Bulk Electric System. 2/17/2011 10/1/2012 6/30/2019 Implementation Plan

9/15/2011 RSAW

Mandatory Subject to Enforcement PER-003-2 Operating Personnel Credentials To ensure that System Operators performing the reliability-related tasks of the Reliability Coordinator, Balancing Authority and Transmission Operator are certified through the NERC System Operator Certification Program when filling a Real-time operating position responsible for control of the Bulk Electric System. 5/10/2018 7/1/2019
Implementation Plan

11/21/2018 RSAW

Inactive PER-004-2 Reliability Coordination — Staffing Reliability Coordinators must have sufficient, competent staff to perform the Reliability Coordinator functions. 2/10/2009 4/1/2011 6/30/2019 Implementation Plan
Please note: The effective date in the standard refers to the retirements in PER-004-1. 11/18/2010 RSAW

Inactive PER-005-1 System Personnel Training To ensure that System Operators performing real-time, reliability-related tasks on the North American Bulk Electric System (BES) are competent to perform those reliability-related tasks. The competency of System Operators is critical to the reliability of the North American Bulk Electric System. 2/10/2009 4/1/2013 6/30/2016 Implementation Plan

11/18/2010 RSAW

Mandatory Subject to Enforcement PER-005-2 Operations Personnel Training To ensure that personnel performing or supporting Real-time operations
on the Bulk Electric System are trained using a systematic approach.
2/6/2014 7/1/2016
Implementation Plan

6/19/2014 RSAW

Mandatory Subject to Enforcement PER-006-1 Specific Training for Personnel To ensure that personnel are trained on specific topics essential to reliability to perform or support Real-time operations of the Bulk Electric System. 8/11/2016 4/1/2021
Implementation Plan
Effective dates delayed to April 1, 2021 due to COVID-19 per FERC Order (https://www.nerc.com/FilingsOrders/us/FERCOrdersRules/order granting motion to defer the implementation dates.pdf). 6/7/2018 RSAW

Inactive PRC-001-1.1(ii) System Protection Coordination To ensure system protection is coordinated among operating entities. 2/12/2015 5/29/2015 3/31/2021 Implementation Plan
Requirements 2, 5 and 6 are inactive as of 3/31/2017 due to TOP/IRO standards. Replaced by TOP/IRO standards, PER-006-1 and 5/29/2015 RSAW

Inactive PRC-001-2 System Protection Coordination To ensure system protection is coordinated among operating entities. 5/29/2012
1/26/2016

FERC approved withdrawal of standard



Inactive PRC-002-1 Define Regional Disturbance Monitoring and Reporting Requirements Ensure that Regional Reliability Organizations establish requirements for installation of Disturbance Monitoring Equipment (DME) and reporting of Disturbance data to facilitate analyses of events and verify system models. 8/2/2006
6/30/2016 Implementation Plan
This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Mandatory Subject to Enforcement PRC-002-2 Disturbance Monitoring and Reporting Requirements To have adequate data available to facilitate analysis of Bulk Electric
System (BES) Disturbances.
11/13/2014 7/1/2016
Implementation Plan
Due to Covid-19, Entities will be required to establish 50% compliance with Requirements R2-R4 and R6-R11 by January 1, 2021. See Implementation Plan for additional effective date information. 9/17/2015 RSAW
11/12/2020
Filed and Pending Regulatory Approval PRC-002-3 Disturbance Monitoring and Reporting Requirements To have adequate data available to facilitate analysis of Bulk Electric System (BES) Disturbances. 5/13/2021

Implementation Plan

6/28/2021


Inactive PRC-002-NPCC-01 Disturbance Monitoring Ensure that adequate disturbance data is available to facilitate Bulk Electric System event analyses. All references to equipment and facilities herein unless otherwise noted will be to Bulk Electric System (BES) elements. 11/4/2010 10/20/2013 7/1/2016 Implementation Plan
This standard has a phased implementation. Please see the Implementation Plan for further compliance date information. This standard was approved by FERC on 10/20/2011. 10/20/2011 N/A

Inactive PRC-003-1 Regional Procedure for Analysis of Misoperations of Transmission and Generation Protection Systems To ensure all transmission and generation Protection System Misoperations affecting the reliability of the Bulk Electric System (BES) are analyzed and mitigated. 2/7/2006
6/30/2016 Implementation Plan
This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Inactive PRC-004-2 Analysis and Mitigation of Transmission and Generation Protection System Misoperations Ensure all transmission and generation Protection System Misoperations affecting the reliability of the Bulk Electric System (BES) are analyzed and mitigated. 8/5/2010
9/25/2011 Implementation Plan

1/10/2011


Inactive PRC-004-2.1(i)a Analysis and Mitigation of Transmission and Generation Protection System Misoperations Ensure all transmission and generation Protection System Misoperations affecting the reliability of the Bulk Electric System (BES) are analyzed and mitigated. 11/13/2014 5/29/2015 6/30/2016 Implementation Plan

5/29/2015 RSAW

Inactive PRC-004-2.1a Analysis and Mitigation of Transmission and Generation Protection System Misoperations Ensure all transmission and generation Protection System Misoperations affecting the reliability of the Bulk Electric System (BES) are analyzed and mitigated. 2/9/2012 11/25/2013 5/28/2015 Implementation Plan

9/19/2013


Inactive PRC-004-2a Analysis and Mitigation of Transmission and Generation Protection System Misoperations Ensure all transmission and generation Protection System Misoperations affecting the reliability of the Bulk Electric System (BES) are analyzed and mitigated. 2/17/2011 4/1/2012 11/24/2013 Implementation Plan

9/26/2011


Inactive PRC-004-3 Protection System Misoperation Identification and Correction Identify and correct the causes of Misoperations of Protection Systems for Bulk Electric System (BES) Elements. 8/14/2014
6/30/2016 Implementation Plan
The Implementation Plan for PRC-004-4 provides that PRC-004-4 becomes enforcable on the effective date for PRC-004-3. Because of this, PRC-004-3 will never become enforceable. 5/13/2015


Inactive PRC-004-4 Project 2014-01 Standards Applicability for Dispersed Generation Resources Identify and correct the causes of Misoperations of Protection Shystems for Bulk Electric System (BES) Elements. 11/13/2014
6/30/2016 Implementation Plan
PRC-004-4 was superseded by PRC-004-4(i) and will never be enforceable. 5/29/2015


Inactive PRC-004-4(i) Protection System Misoperation Identification and Correction Identify and correct the causes of Misoperations of Protection Systems for Bulk Electric System (BES) Elements. 6/22/2015 7/1/2016 4/1/2017 Implementation Plan


RSAW

Inactive PRC-004-5(i) Protection System Misoperation Identification and Correction Identify and correct the causes of Misoperations of Protection Systems for Bulk Electric System (BES) Elements. 6/22/2015 4/2/2017 3/31/2021 Implementation Plan


RSAW

Mandatory Subject to Enforcement PRC-004-6 Protection System Misoperation Identification and Correction Identify and correct the causes of Misoperations of Protection Systems for Bulk Electric System (BES) Elements. 5/9/2019 4/1/2021
Implementation Plan

9/17/2020 RSAW

Inactive PRC-004-WECC-1 Protection System and Remedial Action Scheme Misoperation Regional Reliability Standard to ensure all transmission and generation Protection System and Remedial Action Scheme (RAS) Misoperations on Transmission Paths and RAS defined in section 4 are analyzed and/or mitigated. 10/29/2008 10/1/2011 3/31/2017


4/21/2011 N/A

Inactive PRC-004-WECC-2 Protection System and Remedial Action Scheme Misoperation Regional Reliability Standard to ensure all transmission and generation Protection System and Remedial Action Scheme (RAS) Misoperations on Transmission Paths and RAS defined in section 4 are analyzed and/or mitigated. 11/13/2014 4/1/2017 1/1/2021 Implementation Plan
NERC filed a joint petition March 9, 2018 for approval of retirement of PRC-004-WECC-2.

Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition.

11/19/2015 N/A

Mandatory Subject to Enforcement PRC-005-1.1b Transmission and Generation Protection System Maintenance and Testing To ensure all transmission and generation Protection Systems affecting the reliability of the Bulk Electric System (BES) are maintained and tested. 5/9/2012 11/25/2013 3/31/2027 Implementation Plan
Replaced with PRC-005-1.1b 9/19/2013 RSAW

Inactive PRC-005-2 Protection System Maintenance To document and implement programs for the maintenance of all Protection Systems affecting the reliability of the Bulk Electric System (BES) so that these Protection Systems are kept in working order. 11/7/2012 4/1/2015 5/28/2015 Implementation Plan
The enforcement date for PRC-005-2 has been corrected from the date first posted. The enforcement date for PRC-005-2 will be April 1, 2015, which is the first date entities must be compliant with part of the standard. The implementation plan for PRC-005-2 includes specific compliance dates and timeframes for each of the Requirements. The regulatory approval date in the U.S. is February 24, 2014. Entities should use this date as a starting point for calculating the compliance dates for each of the Requirements as detailed in the implementation plan. 12/19/2013


Inactive PRC-005-2(i) Protection System Maintenance To document and implement programs for the maintenance of all Protection Systems affecting the reliability of the Bulk Electric System (BES) so that these Protection Systems are kept in working order. 11/13/2014 5/29/2015 12/31/2016 Implementation Plan
To be retired 12/31/2016 by PRC-005-6 Implementation Plan. 5/29/2015 RSAW

Inactive PRC-005-2(ii) Protection System Maintenance To document and implement programs for the maintenance of all Protection Systems affecting the reliability of the Bulk Electric System (BES) so that these Protection Systems are kept in working order. 11/13/2014
12/31/2015 Implementation Plan
Retired by PRC-005-6; PRC-005-2(ii) was never enforceable 11/19/2015


Inactive PRC-005-3 Protection System and Automatic Reclosing Maintenance To document and implement programs for the maintenance of all Protection Systems and Automatic Reclosing affecting the reliability of the Bulk Electric System (BES) so that they are kept in working order. 11/7/2013
12/31/2015 Implementation Plan
Retired by PRC-005-6; PRC-005-3 was never enforceable.



Inactive PRC-005-3(i) Protection System and Automatic Reclosing Maintenance To document and implement programs for the maintenance of all Protection Systems and Automatic Reclosing affecting the reliability of the Bulk Electric System (BES) so that they are kept in working order. 11/13/2014
12/31/2015 Implementation Plan
Retired by PRC-005-6; PRC-005-3(i) was never enforceable.



Inactive PRC-005-3(ii) Protection System and Automatic Reclosing Maintenance To document and implement programs for the maintenance of all Protection Systems and Automatic Reclosing affecting the reliability of the Bulk Electric System (BES) so that they are kept in working order. 11/13/2014 4/1/2017 12/31/2015 Implementation Plan
Retired by PRC-005-6; PRC-005-3(ii) was never enforceable. 11/19/2015


Inactive PRC-005-4 Protection System, Automatic Reclosing, and Sudden Pressure Relaying To document and implement programs for the maintenance of all Protection Systems, Automatic Reclosing, and Sudden Pressure Relaying affecting the reliability of the Bulk Electric System (BES) so that they are kept in working order. 11/13/2014
12/31/2015 Implementation Plan
Retired by PRC-005-6; PRC-005-4 was never enforceable.



Inactive PRC-005-5 Protection System, Automatic Reclosing, and Sudden Pressure Relaying To document and implement programs for the maintenance of all Protection Systems, Automatic Reclosing, and Sudden Pressure Relaying affecting the reliability of the Bulk Electric System (BES) so that they are kept in working order. 5/7/2015
12/31/2015 Implementation Plan
Approved by Board of Trustees; replaced and retired by PRC-005-6; PRC-005-5 was never enforceable. 12/18/2015


Mandatory Subject to Enforcement PRC-005-6 Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance To document and implement programs for the maintenance of all Protection Systems, Automatic Reclosing, and Sudden Pressure Relaying affecting the reliability of the Bulk Electric System (BES) so that they are kept in working order. 11/5/2015 1/1/2016
Implementation Plan Supplemental Reference and FAQ Please see the implementation plan for guidance on phased-in enforcement dates. 12/18/2015 RSAW
5/21/2018
Inactive PRC-006-2 Automatic Underfrequency Load Shedding To establish design and documentation requirements for automatic underfrequency load shedding (UFLS) programs to arrest declining frequency, assist recovery of frequency following underfrequency events and provide last resort system preservation measures. 11/13/2014 10/1/2015 9/30/2017 Implementation Plan

3/04/2015 RSAW

Inactive PRC-006-3 Automatic Underfrequency Load Shedding To establish design and documentation requirements for automatic underfrequency load shedding (UFLS) programs to arrest declining frequency, assist recovery of frequency following underfrequency events and provide last resort system preservation measures. 8/10/2017 10/1/2017 3/31/2021

Reliability Standard PRC-006-3 revises the regional Variance for the Québec Interconnection as necessary to account for the physical characteristics and operational practices of that Interconnection. No changes have been made to any of the continent-wide Requirements of Reliability Standard PRC-006-21 nor the regional Variance for the Western Electricity Coordinating Council Interconnection.
RSAW

Inactive PRC-006-4 Automatic Underfrequency Load Shedding To establish design and documentation requirements for automatic underfrequency load shedding (UFLS) programs to arrest declining frequency, assist recovery of frequency following underfrequency events and provide last resort system preservation measures. 2/6/2020
3/31/2021 Implementation Plan

10/30/2020


Mandatory Subject to Enforcement PRC-006-5 Automatic Underfrequency Load Shedding To establish design and documentation requirements for automatic underfrequency load shedding (UFLS) programs to arrest declining frequency, assist recovery of frequency following underfrequency events and provide last resort system preservation measures. 8/20/2020 4/1/2021
Implementation Plan

12/23/2020 RSAW

Inactive PRC-006-NPCC-1 Automatic Underfrequency Load Shedding To provide a regional reliability standard that ensures the development of an effective automatic underfrequency load shedding (UFLS) program in order to preserve the security and integrity of the bulk power system during declining system frequency events in coordination with the NERC UFLS reliability standard characteristics. 2/9/2012 7/1/2015 3/31/2020 Implementation Plan

2/21/2013 N/A

Mandatory Subject to Enforcement PRC-006-NPCC-2 Automatic Underfrequency Load Shedding The NPCC Automatic Underfrequency Load Shedding (UFLS) regional Reliability Standard establishes more stringent and specific NPCC UFLS program requirements than the NERC continent-wide PRC-006 standard. The program is designed such that declining frequency is arrested and recovered in accordance with established NPCC performance requirements stipulated in this document. 11/5/2019 4/1/2020
Implementation Plan

12/23/2019


Inactive PRC-006-SERC-01 Automatic Underfrequency Load Shedding Requirements To establish consistent and coordinated requirements for the design, implementation, and analysis of automatic underfrequency load shedding (UFLS) programs among all SERC applicable entities. 11/3/2011 4/1/2014 12/31/2017 Implementation Plan
See the implementation plan for guidance on phased-in enforcement dates 4/29/2013 N/A

Mandatory Subject to Enforcement PRC-006-SERC-02 Automatic Underfrequency Load Shedding Requirements To establish consistent and coordinated requirements for the design,
implementation, and analysis of automatic underfrequency load shedding (UFLS)
programs among all SERC applicable entities.
8/10/2017 1/1/2018







Pending Regulatory Filing PRC-006-SERC-03 Automatic Underfrequency Load Shedding Requirement To establish consistent and coordinated requirements for the design, implementation, and analysis of automatic underfrequency load shedding (UFLS) programs among all SERC applicable entities. 6/24/2021

Implementation Plan





Mandatory Subject to Enforcement PRC-008-0 Implementation and Documentation of Underfrequency Load Shedding Equipment Maintenance Program Provide last resort system preservation measures by implementing an Under Frequency Load Shedding (UFLS) program. 2/8/2005 6/18/2007 3/31/2027 Implementation Plan

3/16/2007 RSAW

Inactive PRC-010-0 Technical Assessment of the Design and Effectiveness of Undervoltage Load Shedding Program. Provide System preservation measures in an attempt to prevent system voltage collapse or voltage instability by implementing an Undervoltage Load Shedding (UVLS) program. 2/8/2005 6/18/2007 3/31/2017 Implementation Plan

3/16/2007 RSAW

Inactive PRC‐010‐1 Undervoltage Load Shedding To establish an integrated and coordinated approach to the design, evaluation, and reliable operation of Undervoltage Load Shedding Programs (UVLS Programs). 11/13/2014 4/1/2017 4/1/2017 Implementation Plan

11/19/2015


Mandatory Subject to Enforcement PRC-010-2 Undervoltage Load Shedding To establish an integrated and coordinated approach to the design, evaluation, and reliable operation of Undervoltage Load Shedding Programs (UVLS Programs). 5/7/2015 4/2/2017
Implementation Plan

11/19/2015 RSAW

Mandatory Subject to Enforcement PRC-011-0 Undervoltage Load Shedding System Maintenance and Testing Provide system preservation measures in an attempt to prevent system voltage collapse or voltage instability by implementing an Undervoltage Load Shedding (UVLS) program. 2/8/2005 6/18/2007 3/31/2027 Implementation Plan

3/16/2007 RSAW

Inactive PRC-012-0 Special Protection System Review Procedure To ensure that all Special Protection Systems (SPS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 2/8/2005
3/31/2017 Implementation Plan
This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Inactive PRC-012-1 Remedial Action Scheme Review Procedure To ensure that all Remedial Action Schemes (RAS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 11/13/2014
12/31/2020 Implementation Plan
Because Reliability Standards PRC-012-0, PRC-013-0, and PRC-014-0 were never approved or remanded, Reliability Standards PRC-012-1, PRC-013-1, and PRC-014-1 were only developed for ‘completeness’ and are not enforceable.



Mandatory Subject to Enforcement PRC-012-2 Remedial Action Schemes To ensure that Remedial Action Schemes (RAS) do not introduce unintentional or unacceptable reliability risks to the Bulk Electric System (BES). 5/5/2016 1/1/2021
Implementation Plan

9/20/2017 RSAWs

Inactive PRC-013-0 Special Protection System Database To ensure that all Special Protection Systems (SPSs) are properly designed, meet performance requirements, and are coordinated with other protection systems. 2/8/2005
3/31/2017 Implementation Plan
This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Inactive PRC-013-1 Remedial Action Scheme Database To ensure that all Remedial Action Schemes (RAS) are properly designed, meet performance requirements, and are coordinated with other protection systems. 11/13/2014
12/31/2020 Implementation Plan
Because Reliability Standards PRC-012-0, PRC-013-0, and PRC-014-0 were never approved or remanded, Reliability Standards PRC-012-1, PRC-013-1, and PRC-014-1 were only developed for ‘completeness’ and are not enforceable.



Inactive PRC-014-0 Special Protection System Assessment To ensure that all Special Protection Systems (SPS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 2/8/2005
3/31/2017 Implementation Plan
This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Inactive PRC-014-1 Remedial Action Scheme Assessment To ensure that all Remedial Action Schemes (RAS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 11/13/2014
12/31/2020 Implementation Plan
Because Reliability Standards PRC-012-0, PRC-013-0, and PRC-014-0 were never approved or remanded, Reliability Standards PRC-012-1, PRC-013-1, and PRC-014-1 were only developed for ‘completeness’ and are not enforceable.



Inactive PRC-015-0 Special Protection System Data and Documentation To ensure that all Special Protection Systems (SPS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 2/8/2005 6/18/2007 3/31/2017 Implementation Plan

3/16/2007 RSAW

Inactive PRC-015-1 Remedial Action Scheme Data and Documentation To ensure that all Remedial Action Schemes (RAS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 11/13/2014 4/1/2017 12/31/2020 Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW

Inactive PRC-016-0.1 Special Protection System Misoperations To ensure that all Special Protection Systems (SPS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 10/29/2008 5/13/2009 3/31/2017 Implementation Plan

5/13/2009 RSAW

Inactive PRC-016-1 Remedial Action Scheme Misoperations To ensure that all Remedial Action Schemes (RAS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 11/13/2014 4/1/2017 12/31/2020 Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW

Inactive PRC-017-0 Special Protection System Maintenance and Testing To ensure that all Special Protection Systems (SPS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 2/8/2005 6/18/2007 3/31/2017 Implementation Plan

3/16/2007 RSAW

Mandatory Subject to Enforcement PRC-017-1 Remedial Action Scheme Maintenance and Testing To ensure that all Remedial Action Schemes (RAS) are properly designed, meet performance requirements, and are coordinated with other protection systems. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. 11/13/2014 4/1/2017 3/31/2027 Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW

Mandatory Subject to Enforcement PRC-018-1 Disturbance Monitoring Equipment Installation and Data Reporting Ensure that Disturbance Monitoring Equipment (DME) is installed and that Disturbance data is reported in accordance with regional requirements to facilitate analyses of events. 8/2/2006 6/18/2007 6/30/2022 Implementation Plan

3/16/2007 RSAW

Inactive PRC-019-1 Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection To verify coordination of generating unit Facility or synchronous condenser voltage regulating controls, limit functions, equipment capabilities and Protection System settings. 2/7/2013 7/1/2016 6/30/2016 Implementation Plan
Please see the Implementation Plan for specific compliance dates and timeframes. The standard become inactive 6/30/16. 3/20/2014


Mandatory Subject to Enforcement PRC-019-2 Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection To verify coordination of generating unit Facility or synchronous condenser voltage regulating controls, limit functions, equipment capabilities and Protection System settings. 2/12/2015 7/1/2016
Implementation Plan
Please see the Implementation Plan for Version 1 for specific compliance dates and timeframes. 5/29/2015 RSAW
12/15/2020
Inactive PRC-020-1 Under-Voltage Load Shedding Program Database Ensure that a regional database is maintained for Under-Voltage Load Shedding (UVLS) programs implemented by entities within the Region to mitigate the risk of voltage collapse or voltage instability in the Bulk Electric System (BES). Ensure the UVLS database is available for Regional studies and for dynamic studies and simulations of the BES. 2/7/2006
3/31/2017

This Standard was not approved by FERC in Order 693. See Standards Under Development page or Reliability Standards Development Plan for more information.



Inactive PRC-021-1 Under-Voltage Load Shedding Program Data Ensure data is provided to support the Regional database maintained for Under-Voltage Load Shedding (UVLS) programs that were implemented to mitigate the risk of voltage collapse or voltage instability in the Bulk Electric System (BES). 2/7/2006 6/18/2007 3/31/2017


3/16/2007 RSAW

Inactive PRC-022-1 Under-Voltage Load Shedding Program Performance Ensure that Under Voltage Load Shedding (UVLS) programs perform as intended to mitigate the risk of voltage collapse or voltage instability in the Bulk Electric System (BES). 2/7/2006 6/18/2007 3/31/2017


3/16/2007 RSAW

Inactive PRC-023-3 Transmission Relay Loadability Protective relay settings shall not limit transmission loadability; not interfere with system operators’ ability to take remedial action to protect system reliability and; be set to reliably detect all fault conditions and protect the electrical network from these faults. 11/7/2013 10/1/2014 3/31/2017 Implementation Plan

07/17/2014 RSAW

Mandatory Subject to Enforcement PRC-023-4 Transmission Relay Loadability Protective relay settings shall not limit transmission loadability; not interfere with system operators’ ability to take remedial action to protect system reliability and; be set to reliably detect all fault conditions and protect the electrical network from these faults. 11/13/2014 4/1/2017
Implementation Plan
Entities with newly classified “Remedial Action Scheme” (RAS) resulting from the application of the revised definition must be fully compliant with all Reliability Standards applicable RAS twenty-four (24) months from the Effective Date of the revised definition of RAS. This additional time applies only to existing schemes that must transition to RAS due to the revised definition. 11/19/2015 RSAW
5/21/2018
Filed and Pending Regulatory Approval PRC-023-5 Transmission Relay Loadability Protective relay settings shall not limit transmission loadability; not interfere with system operators’ ability to take remedial action to protect system reliability and; be set to reliably detect all fault conditions and protect the electrical network from these faults. 5/13/2021

Implementation Plan

6/28/2021


Inactive PRC-024-1 Generator Frequency and Voltage Protective Relay Settings Ensure Generator Owners set their generator protective relays such that generating units remain connected during defined frequency and voltage excursions. 5/9/2013 7/1/2016 6/30/2016 Implementation Plan
Please see the Implementation Plan for specific compliance dates and timeframes. The standard become inactive 6/30/16. 3/20/2014


Mandatory Subject to Enforcement PRC-024-2 Generator Frequency and Voltage Protective Relay Settings Ensure Generator Owners set their generator protective relays such that generating units remain connected during defined frequency and voltage excursions. 2/12/2015 7/1/2016 9/30/2022 Implementation Plan
Please see the Implementation Plan for Version 1 for specific compliance dates and timeframes. 5/29/2015 RSAW
1/3/2019
Subject to Future Enforcement PRC-024-3 Frequency and Voltage Protection Settings for Generating Resources To set protection such that generating resource(s) remain connected during defined frequency and voltage excursions in support of the Bulk Electric System (BES). 2/6/2020 10/1/2022
Implementation Plan





Inactive PRC-025-1 Generator Relay Loadability To set load-responsive protective relays associated with generation Facilities at a level to prevent unnecessary tripping of generators during a system disturbance for conditions that do not pose a risk of damage to the associated equipment. 8/15/2013 10/1/2014 6/30/2018 Implementation Plan
See Implementation Plan. For applicable relays where the entity has determined replacement or removal is not necessary, the entity shall be compliant by 10/1/2019. For applicable relays where the entity has determined replacement or removal is necessary, the entity shall be compliant by 10/1/2021. 7/17/2014 RSAW

Mandatory Subject to Enforcement PRC-025-2 Generator Relay Loadability To set load-responsive protective relays associated with generation Facilities at a level to prevent unnecessary tripping of generators during a system disturbance for conditions that do not pose a risk of damage to the associated equipment. 2/8/2018 7/1/2018
Implementation Plan
Due to Covid-19, entities will be required to establish compliance with Requirement R1 Attachment 1: Relay Settings, Table 1 Options 5b, 14b, 15b, and 16b by January 1, 2021, where the entity has determined that replacement or removal of the applicable relay is not needed. Refer to the Implementation Plan for Phased-in Compliance details. 5/2/2018 RSAW

Mandatory Subject to Enforcement PRC-026-1 Relay Performance During Stable Power Swings To ensure that load-responsive protective relays are expected to not trip in response to stable power swings during non-Fault conditions. 12/17/2014 1/1/2018
Implementation Plan
Requirement R1 is effective 1/1/2018.  Requirements R2, R3 and R4 are effective 1/1/2020. 3/17/2016 RSAW

Filed and Pending Regulatory Approval PRC-026-2 Relay Performance During Stable Power Swings To ensure that load-responsive protective relays are expected to not trip in response to stable power swings during non-Fault conditions. 5/13/2021

Implementation Plan

6/28/2021


Mandatory Subject to Enforcement PRC-027-1 Coordination of Protection Systems for Performance During Faults To maintain the coordination of Protection Systems installed to detect and isolate Faults on Bulk Electric System (BES) Elements, such that those Protection Systems operate in the intended sequence during Faults. 11/5/2015 4/1/2021
Implementation Plan
Effective dates delayed to April 1, 2021 due to COVID-19 per FERC Order (https://www.nerc.com/FilingsOrders/us/FERCOrdersRules/order granting motion to defer the implementation dates.pdf). 6/7/2018 RSAW

Inactive TOP-001-1a Reliability Responsibilities and Authorities To ensure reliability entities have clear decision-making authority and capabilities to take appropriate actions or direct the actions of others to return the transmission system to normal conditions during an emergency. 5/12/2010 11/21/2011 3/31/2017 Implementation Plan

9/15/2011 RSAW

Inactive TOP-001-2 Transmission Operations To prevent instability, uncontrolled separation, or cascading outages that adversely impact the reliability of the Interconnection by ensuring prompt action to prevent or mitigate such occurrences. 5/9/2012
1/26/2016 Implementation Plan
FERC approved withdrawal of standard



Inactive TOP-001-3 Transmission Operations To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection by ensuring prompt action to prevent or mitigate such occurrences. 2/12/2015 4/1/2017 6/30/2018 Implementation Plan

11/19/2015 RSAW
5/21/2018
Inactive TOP-001-4 Transmission Operations To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection by ensuring prompt action to prevent or mitigate such occurrences. 2/9/2017 7/1/2018 3/31/2021 Implementation Plan

4/17/2017 RSAW
1/8/2021
Mandatory Subject to Enforcement TOP-001-5 Transmission Operations To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection by ensuring prompt action to prevent or mitigate such occurrences. 5/9/2019 4/1/2021
Implementation Plan

9/17/2020 RSAW

Filed and Pending Regulatory Approval TOP-001-6 Transmission Operations To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection by ensuring prompt action to prevent or mitigate such occurrences. 5/13/2021

Implementation Plan

6/28/2021


Inactive TOP-002-2.1b Normal Operations Planning Current operations plans and procedures are essential to being prepared for reliable operations, including response for unplanned events. 4/11/2012 9/13/2012 3/31/2017


9/13/2012 RSAW

Inactive TOP-002-3 Operations Planning To ensure that Transmission Operators have plans for operating within specified limits 5/9/2012
1/26/2016 Implementation Plan
FERC approved withdrawal of standard



Mandatory Subject to Enforcement TOP-002-4 Operations Planning To ensure that Transmission Operators and Balancing Authorities have plans for operating within specified limits. 11/13/2014 4/1/2017
Implementation Plan

11/19/2015 RSAW

Inactive TOP-003-1 Planned Outage Coordination Scheduled generator and transmission outages that may affect the reliability of interconnected operations must be planned and coordinated among Balancing Authorities, Transmission Operators, and Reliability Coordinators. 10/17/2008 10/1/2011 3/31/2017 Implementation Plan

3/17/2011 RSAW

Inactive TOP-003-2 Operational Reliability Data To ensure that the Transmission Operator and Balancing Authority have the data needed to fulfill their operational planning and Real-time monitoring responsibilities. 5/9/2012
1/26/2016 Implementation Plan
FERC approved withdrawal of standard



Inactive TOP-003-3 Operational Reliability Data To ensure that the Transmission Operator and Balancing Authority have data needed to fulfill their operational and planning responsibilities. 11/13/2014 1/1/2017 3/31/2021 Implementation Plan
For the Requirement R3 and R4 VSLs only, the intent of the SDT is to start with the Severe VSL first and then to work your way to the left until you find the situation that fits. In this manner, the VSL will not be discriminatory by size of entity. If a small entity has just one affected reliability entity to inform, the intent is that that situation would be a Severe violation. 11/19/2015 RSAW

Mandatory Subject to Enforcement TOP-003-4 Operational Reliability Data To ensure that the Transmission Operator and Balancing Authority have data needed to fulfill their operational and planning responsibilities. 2/6/2020 4/1/2021 3/31/2023 Implementation Plan

10/30/2020 RSAW

Manadatory Subject to Future Enforcement TOP-003-5 Operational Reliability Data To ensure that the Transmission Operator and Balancing Authority have data needed to fulfill their operational and planning responsibilities. 6/11/2021 4/1/2023
Implementation Plan

8/24/2021


Inactive TOP-004-2 Transmission Operations To ensure that the transmission system is operated so that instability, uncontrolled separation, or cascading outages will not occur as a result of the most severe single Contingency and specified multiple Contingencies. 11/1/2006 1/22/2009 3/31/2017


1/22/2009 RSAW

Inactive TOP-005-2a Operational Reliability Information To ensure reliability entities have the operating data needed to monitor system conditions within their areas. 10/17/2008 10/1/2011 3/31/2017 Implementation Plan

3/17/2011 RSAW

Inactive TOP-006-2 Monitoring System Conditions To ensure critical reliability parameters are monitored in real-time. 10/17/2008 10/1/2011 3/31/2017 Implementation Plan

3/17/2011 RSAW

Inactive TOP-006-3 Monitoring System Conditions To ensure critical reliability parameters are monitored in real-time. 11/7/2012
3/18/2015 Implementation Plan





Inactive TOP-007-0 Reporting System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL) Violations This standard ensures SOL and IROL violations are being reported to the Reliability Coordinator so that the Reliability Coordinator may evaluate actions being taken and direct additional corrective actions as needed. 2/8/2005 6/18/2007 3/31/2017 Implementation Plan

3/16/2007 RSAW

Inactive TOP-007-WECC-1a System Operating Limits When actual flows on Major WECC Transfer Paths exceed System Operating Limits (SOL), their associated schedules and actual flows are not exceeded for longer than a specified time. 2/6/2014 6/18/2014 3/10/2017


6/18/2014 N/A

Inactive TOP-008-1 Response to Transmission Limit Violations To ensure Transmission Operators take actions to mitigate SOL and IROL violations. 11/1/2006 6/18/2007 3/31/2017 Implementation Plan

6/16/2007 RSAW

Inactive TOP-010-1 Real-time Reliability Monitoring and Analysis Capabilities Establish requirements for Real-time monitoring and analysis capabilities to support reliable System operations. 5/5/2016
3/31/2018 Implementation Plan
TOP-010-1(i) became enforceable 4/1/2018, therefore TOP-010-1 will never be enforceable. 9/22/2016 RSAW

Mandatory Subject to Enforcement TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities Establish requirements for Real-time monitoring and analysis capabilities to support reliable System operations. 11/2/2016 4/1/2018
Implementation Plan
VRF designations for Requirement R1 of IRO-018-1 and Requirements R1 and R2 of TOP-010-1 changed to high.
RSAW
3/12/2020
Mandatory Subject to Enforcement TPL-001-4 Transmission System Planning Performance Requirements Establish Transmission system planning performance requirements within the planning horizon to develop a Bulk Electric System (BES) that will operate reliably over a broad spectrum of System conditions and following a wide range of probable Contingencies. 2/7/2013 1/1/2015 6/30/2023 Implementation Plan
TPL-001-4 was adopted by the Board of Trustees as TPL-001-3, but a discrepancy in numbering was identified and corrected prior to filing with the regulatory agencies. 10/17/2013 RSAW
3/24/2017
Inactive TPL-001-5 Transmission System Planning Performance Requirements Establish Transmission system planning performance requirements within the planning horizon to develop a Bulk Electric System (BES) that will operate reliably over a broad spectrum of System conditions and following a wide range of probable Contingencies. 11/7/2018 7/1/2023 6/10/2020 Implementation Plan
Replaced by TPL-001-5.1 (Errata approved by SC on April 22, 2020) 1/23/2020


Subject to Future Enforcement TPL-001-5.1 Transmission System Planning Performance Requirements Establish Transmission system planning performance requirements within the planning horizon to develop a Bulk Electric System (BES) that will operate reliably over a broad spectrum of System conditions and following a wide range of probable Contingencies. 11/7/2018 7/1/2023
Implementation Plan
Phased-in Compliance Dates for Requirement R2, Part 2.7 for the revised Category P5 Planning Event:

July 1, 2025
Entities shall not be required to comply with Requirement R2, Part 2.7 for the Table 1 Category P5 planning event for the non-redundant components of a Protection System identified in footnote 13 items a, b, c, and d until 24 months after the effective date of Reliability Standard TPL-001-5.

July 1, 2029
For CAPs developed to address failures to meet Table 1 performance requirements for the P5 planning event for the non-redundant components of a Protection System identified in footnote 13 items a, b, c, and d, entities shall not be required to comply until 72 months after the effective date of Reliability Standard TPL-001-5 with the bolded part of Requirement R2, Part 2.7 that states:
“Revisions to the Corrective Action Plan(s) are allowed in subsequent Planning Assessments but the planned System shall continue to meet the performance requirements in Table 1.”
6/10/2020


Inactive TPL-007-1 Transmission System Planned Performance for Geomagnetic Disturbance Events Establish requirements for Transmission system planned performance during geomagnetic disturbance (GMD) events. 12/17/2014 7/1/2017 6/30/2019 Implementation Plan
See Implementation Plan for phased-in compliance dates. 9/22/2016 RSAW
10/28/16: Compliance Guidance Updates
Inactive TPL-007-2 Transmission System Planned Performance for Geomagnetic Disturbance Events Establish requirements for Transmission system planned performance during geomagnetic disturbance (GMD) events. 11/9/2017 7/1/2019 6/30/2019 Implementation Plan
TPL-007-3 will supersede TPL-007-2 in the U.S. All phased-in compliance dates are carried forward unchanged. See Implementation Plan for phased-in compliance dates. 11/25/2018


Inactive TPL-007-3 Transmission System Planned Performance for Geomagnetic Disturbance Events Establish requirements for Transmission system planned performance during geomagnetic disturbance (GMD) events. 2/7/2019 7/1/2019 9/30/2020 Implementation Plan
TPL-007-3 adds a Variance for Canadian entities. Under the terms of the TPL-007-3 Implementation Plan, TPL-007-3 will supersede TPL-007-2 in the U.S. All phased-in compliance dates are carried forward unchanged. See Implementation Plan for phased-in compliance dates.
RSAW

Mandatory Subject to Enforcement TPL-007-4 Transmission System Planned Performance for Geomagnetic Disturbance Events Establish requirements for Transmission system planned performance during geomagnetic disturbance (GMD) events. 2/6/2020 10/1/2020
Implementation Plan

3/19/2020 RSAWs
11/12/2020: Compliance Guidance Updates
Inactive VAR-001-4.1 Voltage and Reactive Control To ensure that voltage levels, reactive flows, and reactive resources are monitored, controlled, and maintained within limits in Real-time to protect equipment and the reliable operation of the Interconnection. 2/6/2014 11/13/2015 9/25/2017 Implementation Plan

11/13/2015 RSAW

Inactive VAR-001-4.2 Voltage and Reactive Control To ensure that voltage levels, reactive flows, and reactive resources are monitored,
controlled, and maintained within limits in Real-time to protect equipment and the reliable
operation of the Interconnection.
8/10/2017 9/26/2017 12/31/2018 Implementation Plan


RSAW

Mandatory Subject to Enforcement VAR-001-5 Voltage and Reactive Control To ensure that voltage levels, reactive flows, and reactive resources are monitored, controlled, and maintained within limits in Real-time to protect equipment and the reliable operation of the Interconnection. 8/16/2018 1/1/2019
Implementation Plan

10/15/2018 RSAW

Inactive VAR-001-6 Voltage and Reactive Control To ensure that voltage levels, reactive flows, and reactive resources are monitored, controlled, and maintained within limits in Real-time to protect equipment and the reliable operation of the Interconnection. 5/9/2019
5/14/2020 Implementation Plan
Withdrawn as of 5/14/2020



Inactive VAR-002-4 Generator Operation for Maintaining Network Voltage Schedules To ensure generators provide reactive support and voltage control, within generating Facility capabilities, in order to protect equipment and maintain reliable operation of the Interconnection. 11/13/2014 5/29/2015 9/25/2017 Implementation Plan

5/29/2015 RSAW

Mandatory Subject to Enforcement VAR-002-4.1 Generator Operation for Maintaining Network Voltage Schedules To ensure generators provide reactive support and voltage control, within generating
Facility capabilities, in order to protect equipment and maintain reliable operation of the
Interconnection.
8/10/2017 9/26/2017
Implementation Plan


RSAW

Inactive VAR-002-WECC-2 Automatic Voltage Regulators (AVR) To ensure that Automatic Voltage Regulators on synchronous generators and condensers shall be kept in service and controlling voltage. 11/13/2014 4/1/2015 9/5/2018 Implementation Plan
NERC filed a joint petition March 7, 2018 for approval of retirement of VAR-002-WECC-2. 3/03/2015 N/A

Inactive VAR-501-WECC-2 Power System Stabilizer (PSS) To ensure that Power System Stabilizers (PSS) on synchronous generators shall be kept in service. 11/13/2014 4/1/2015 6/30/2017 Implementation Plan

3/03/2015 N/A

Inactive VAR-501-WECC-3 Power System Stabilizer (PSS) Establish Transmission system planning performance requirements within the planning horizon to develop a Bulk Electric System (BES) that will operate reliably over a broad spectrum of System conditions and following a wide range of probable Contingencies. 2/9/2017 7/1/2017 9/25/2017 Implementation Plan
Requirement R3 has an effective date of July 1, 2017 for units placed in first-time service after regulatory approval. R3 has an effective date of July 1, 2022 for units placed in service prior to final regulatory approval.



Mandatory Subject to Enforcement VAR-501-WECC-3.1 Power System Stabilizer (PSS) To ensure the Western Interconnection is operated in a coordinated manner under normal and abnormal conditions by establishing the performance criteria for WECC power system stabilizers. 8/10/2017 9/26/2017


Requirement R3 has an effective date of July 1, 2017 for units placed in first-time service after regulatory approval. R3 has an effective date of July 1, 2022 for units placed in service prior to final regulatory approval.




Sheet 2: Version History
This is a living document that is updated based on standard(s) status changes and current
RSAWs once they are posted to the Compliance and Enforcement web page.
Version Date Owner Change Tracking
1.0 10/01/2015 Standards Information

Email sarcomm@nerc.net with questions
New
1.1 10/9/2015 Standards Information

PRC-023-2 corrected Enforcement date to 7/1/2012
1.2 10/13/2015 Standards Information (bkn) PRC-006-1 removed duplicate
PRC-006-1 updated status to inactive effective 9/30/2015
PRC-006-2 updated status to mandatory subject to enforcement effective 10/1/2015
CIP-014-1 updated status to inactive effective 10/1/2015
CIP-014-2 updated status to mandatory subject to enforcement effective 10/2/2015
BAL-001-TRE-1 added
COM-001-2 updated status to mandatory subject to enforcement effective 10/1/2015
PRC-006-NPCC-1 updated status to mandatory subject to enforcement effective 7/01/2015
PRC-006-SERC-01 updated status to mandatory subject to enforcement effective 4/01/2014
1.3 10/22/2015 Standards Information (mb) NUC-001-2.1 Added inactive date 12/31/2015
PRC-005-3 Corrected the inactive date to 12/31/2015
1.4 11/16/2015 Standards Information (mb) PRC-005-5 Updated to Filed and Pending
PRC-027-1 Added
BAL-002-2 Added
MOD-031-2 Added
PRC-005-6 Added
1.5 12/1/2015 Standards Information (mb) Added Enforcement Dates:
PRC-010-1, PRC-010-2, EOP-011-1, PRC-004-5, BAL-003-1.1, COM-001-2.1, VAR-001-4.1
Added Inactive Dates:
EOP-001-2.1b, EOP-002-3.1, EOP-003-2, PRC-004-4, PRC-010-0, PRC-020-1, PRC-021-1, PRC-022-1, PRC-010-1, BAL-003-1, COM-001-2, VAR-001-4
1.6. 12/7/2015 Standards Information (mb) Added Enforcement Dates:
TOP-001-3, TOP-002-4, TOP-003-3, IRO-001-4, IRO-002-4, IRO-008-2, IRO-010-2, IRO-014-3, IRO-017-1
Added Inactive Dates:
IRO-001-1.1, IRO-002-2, IRO-003-2, IRO-004-2, IRO-005-3.1a, IRO-008-1, IRO-010-1a, IRO-14-1, IRO-015-1
IRO-016-1, PER-001-0.2, TOP-001-1a, TOP-002-2.1b, TOP-003-1, TOP-004-2, TOP-005-2a, TOP-006-2, TOP-007-0, TOP-008-1
Updated:
PRC-004-3(i), PRC-004-4(i), PRC-004-5, PRC-004-5(i)
1.7 12/8/2015 Standards Information (mb) Updated Enforcement and Inactive dates for: IRO-006-EAST-2, IRO-006-EAST-1, IRO-009-1, IRO-009-2
2 12/11/2015 Standards Information (mb) Updated spreadsheet to include additional columns: Implementation Plans, RSAWs, Notes, FERC Order Date.

Changed spreadsheet name from US | Standards | Purpose | Status to: US Standard One-Stop-Shop
2.1 12/18/2015 Standards Information (mb) Added inactive dates for the following standards:
PRC-005-2(i), PRC-005-1b, PRC-005-2(ii), PRC-005-3, PRC-005-3(i), PRC-005-3(ii), PRC-005-4, PRC-005-5

Added enforcement date for PRC-005-6
2.2 12/29/2015 Standards Information (mb) PRC-005-2(i) Changed the inactive date to 12/31/2016
Changed the status of the following standards to inactive: PRC-004-3, PRC-004-3(i), PRC-004-4 and PRC-004-5.
2.3 12/31/2015 Standards Information (NS) Corrected PRC-002-2 status to "Subject to Future Enforcement"
2.4 1/1/2016 Standards Information (mb) Changed the status to inactive for:
TPL-001-0.1, TPL-002-0b, TPL-003-0b, TPL-004-0a, PRC-005-2(ii), PRC-005-3, PRC-005-3(i), PRC-005-3(ii), PRC-005-4, PRC-005-5, IRO-009-1, NUC-001-2.1, FAC-002-1, FAC-001-1
Changed the status to Mandatory Subject to Enforcement:
FAC-001-2, FAC-002-2, IRO-009-2, NUC-001-3, PRC-005-6
2.5 1/6/2016 Standards Information (NS) Updated PRC-005-2(i) Implementation Plan (Errata May 2015)
2.6 1/19/2016 Standards Information (mb) Updated MOD-026-1 to remove inactive date
Changed status of PRC-004-5(i) to Subject to Future Enforcement
2.7 1/20/2016 Standards Information (NS) Updated implementation plans for PRC-004-4(i) and PRC-004-5(i)
2.8 1/21/2016 Standards Information (NS) Added project age for PRC-00404(i) and PRC-004-5(i). Updated RSAWS for EOP-005-2 and IRO-009-2.
2.9 1/27/2016 Standards Information (mb) Added Lessons Learned column and link to CIP Version 5 Transition Program for V5 and V6 CIP standards
Updated status and enforcement dates for: CIP-003-6, CIP-004-6, CIP-006-6, CIP-007-6, CIP-009-6, CIP-010-2, CIP-011-2
Added Inactive dates for: CIP-003-5, CIP-004-5.1, CIP-006-5, CIP-007-5, CIP-009-5, CIP-010-1, CIP-011-1

2.1 2/3/2016 Standards Information (NS) Updated status BAL-002-2 - "Filed and pending regulatory approva"
2.11 2/4/2016 Standards Information (NS) Updated status PRC-023-2 to "Inactive"
2.12 2/5/2016 Standards Information (NS) Updated status, FERC Order link, enforcement date and public notes for: EOP-004-3, PRC-023-4, FAC-010-3, FAC-011-3, MOD-030-3, MOD-029-2a, PRC-015-1, PRC-004-WECC-2, PRC-016-1. Added inactive dates for
2.13 2/8/2016 Standards Information (NS) Added implementation plan for TPL-001-4, TPL-002-0(i)b, TPL-003-0(i)b, TPL-004-0(i)b. Added FERC Order date/link and enforcement date for TPL-001-0.1(i), TPL-02(i)b, TPL-003-0(i)b, TPL-004-0(i)a, PRC-017-1. Updated inactive dates for PRC-017-0 and PRC-017-1.
2.14 2/16/2016 Standards Information (mb) Inactive standards: TPL-001-0.1(i), TPL-002-0(i)b, TPL-003-0(i)b, TPL-004-0(i)a,
2.15 2/17/2016 Standards Information (mb) Added BAL-005-1
2.16 2/18/2019 Standards Information (NS) Added FAC-001-3 and FAC-003-4
2.17 2/26/2016 Standards Information (mb) Updated MOD-031-2 enforcement date and MOD-031-1 inactive date
Updated CIP V5 enforcement and inactive dates
2.18 3/2/2016 Standards Information (mb) CIP-002-3, CIP-003-3, CIP-004-3a, CIP-005-3a, CIP-006-3c, CIP-007-3a, CIP-008-3, CIP-009-3 updated inactive date based on 2/25/16 FERC Order.
2.18 3/2/2016 Standards Information (mb) Update inactive dates for PRC-008-0 and PRC-011-0.
Added PRC-005 inactive standards for added clarity.
2.19 3/14/2016 Standards Information (mb) Added a link to Glossary of Terms on Resource tab
2.2 3/15/2016 Standards Information (mb) Changed status of FAC-003-4 to Filed and Pending Reg Approval
2.21 3/15/2016 Standards Information (mb) Added a Related Documents column for supporting material associated with the standard
2.22 3/29/2016 Standards Information (mb) Updated status of PRC-026-1
2.23 3/30/2016 Standards Information (mb) Added withdrawn status to: TOP-001-2, TOP-002-3, TOP-003-2, IRO-001-3, IRO-002-3, IRO-005-4, IRO-014-2, PRC-001-2
2.24 4/1/2016 Standards Information (mb) Changed status of IRO-006-EAST-1 and IRO-006-EAST-2
Updated/Add RSAW links for: COM-002-4, PER-005-2, PRC-002-2, IRO-006-EAST-2, PRC-004-4(i), PRC-019-2, NUC-001-3
2.25 4/11/2016 Standards Information (mb) PRC-012-1, PRC-013-1 and PRC-014-1: changed status to Filed and Pending Regulatory Approval and added a public note.
2.26 4/14/2016 Standards Information (mb) Corrected inactive date of PRC-004-4(i) to 4/1/2017
2.27 4/22/2016 Standards Information (mb) Changed status of BAL-005-1 and FAC-001-3
2.28 4/27/2016 Standards Information (mb) Changed status of FAC-003-4. Added dates for FAC-003-3 and FAC-003-4
2.29 5/10/2016 Standards Information (mb) Added IRO-018-1, TOP-010-1, PRC-012-2
2.3 5/17/2016 Standards Information (mb) Added RSAWS: BAL-001-2, MOD-031-1, PRC-024-2
Added Revised RSAW: PRC-005-6
2.31 5/26/2016 Standards Information (mb) Updated status of IRO-018-1 and TOP-010-1
2.32 6/3/2016 Standards Information (mb) Added link to CIP V5 Effective Dates for associated standards
3 6/9/2016 Standards Information (mb) Added new column: Compliance Guidance
Added link to CIP V5 standards referencing 5/20/2016 updates
3.1 6/24/2016 Standards Information (mb) Replaced BAL-001-TRE-1
3.2 7/1/2016 Standards Information (mb) Subject to enforcement: BAL-001-2, COM-002-4, CIP-002-5.1, CIP-003-6, CIP-004-6, CIP-005-5, CIP-006-6, CIP-007-6, CIP-008-5, CIP-009-6, CIP-010-2, CIP-011-2, MOD-025-2, MOD-031-1, PER-005-2, PRC-002-2, PRC-004-4(i), PRC-019-2, PRC-024-2
3.2 7/1/2016 Standards Information (mb) Inactive: BAL-001-1, CIP-002-3, CIP-002-3b, CIP-003-3, CIP-003-3a, CIP-003-5, CIP-004-3a, CIP-004-5.1, CIP-005-3a, CIP-006-3C, CIP-006-5, CIP-007-3a, CIP-007-3b, CIP-007-5, CIP-008-3, CIP-009-3, CIP-009-5, CIP-010-1, CIP-011-1, COM-001-1.1 R4, COM-002-2, COM-002-2A, COM-002-3, MOD-010-0, MOD-011-0, MOD-012-0, MOD-013-1, MOD-014-0, MOD-015-0, MOD-015-0.1, MOD-016-1.1, MOD-017-0.1, MOD-018-0, MOD-021-1, MOD-024-1, MOD-025-1, PER-005-1, PRC-002-1, PRC-003-1, PRC-004-2.1(i)a, PRC-004-3, PRC-004-3(i), PRC-004-4, PRC-019-1, PRC-024-1
3.3 7/11/2016 Standards Information (mb) Added RSAWS: FAC-003-4 and MOD-031-2
3.4 7/19/2016 Standards Information (mb) Updated MOD-019-0.1 to show as inactive
3.5 7/25/2016 Standards Information (mb) Added updated RSAWs for FAC-003-4 and PER-005-2 (Errata Changes)
3.6 7/28/2016 Standards Information (mb) changed status of INT-011-1.1 to inactive
3.7 8/8/2016 Standards Information (jmb) changed status of PRC-012-2 to Filed and Pending
3.8 8/15/2016 Standards Information (mb) Added COM-001-3. Filed and Pending
3.9 8/16/2016 Standards Information (mb) Added PER-006-1 Pending Regulatory Approval
3.1 8/17/2016 Standards Information (mb) PRC-002-NPCC-01 Inactive
3.11 8/26/2016 Standards Information (mb) PRC-027-1 Implementation Plans added
3.12 9/8/2016 Standards Information (mb) PRC-027-1 and PER-006-1 Filed and Pending Regulatory Approval
3.13 9/29/2016 Standards Information (mb) IRO-018-1, TOP-010-1 and TPL-007-1 Subject to Future Enforcement Dates status change
3.14 10/3/2016 Standards Information (mb) changed status: FAC-003-3, FAC-003-4, MOD-031-1, MOD-031-2
3.15 10/5/2016 Standards Information (mb) IRO-018-1, TOP-010-1 and TPL-007-1 Enforcement Dates entered and Updated Implementation Plan linked
3.16 10/14/2016 Standards Information (mb) Added RSAWs IRO-010-2 and TOP-003-3
3.17 11/4/2016 Standards Information (mb) changed status COM-001-3; added inactive date for COM-001-2.1; added CIP-002-5.1a
3.18 11/7/2016 Standards Information (mb) Added IRO-018-1(i), TOP-010-1(i) and BAL-002-WECC-2a
3.19 11/7/2016 Standards Information (mb) changed the status of IRO-018-1(i) and TOP-010-1(i) to Filed and Pending Regulatory approval
3.2 11/9/2016 Standards Information (mb) Added RSAWs IRO-001-4, IRO-002-4, IRO-008-2, MOD-029-2a, MOD-030-3, PRC-015-1, PRC-016-1, PRC-017-1, PRC-023-4 which become effective on April 1, 2017. PRC-004-5(i) becomes effective on April 2, 2017.
3.2 11/9/2016 Standards Information (mb) changed status of BAL-002-WECC-2a to Filed and Pending Regulatory approval
3.21 11/28/2016 Standards Information (mb) changed status of CIP-002-5.1a to Filed and Pending Regulatory approval
3.22 11/29/2016 Standards Information (mb) Added a Compliance Guidance link to the following standards: CIP-014-1, FAC-003-3, and TPL-007-1
3.23 1/4/2017 Standards Information (mb) changed status of TOP-003-3 to Mandatory Subject to Enforcement
3.24 1/5/2017 Standards Information (mb) Changed status of TOP-010-1(i), TOP-010-1, IRO-018-1(i) and IRO-018-1 and added Enforcement Dates.
Changed the status and dates of CIP-002-5.1 and CIP-002-5.1a
3.25 1/20/2017 Standards Information (mb) updated the status of BAL-002-2
3.26 1/23/2017 Standards Information (mb) Added RSAWs for TOP-002-4 and FAC-011-3. Changed the status of BAL-004-0 to Pending Inactive. Changed the Board Adopted Date of CIP-006-6 to 11/13/2014.
3.27 1/25/2017 Standards Information (mb) Changed status of BAL-002-WECC-2 to inactive; changed status of BAL-002-WECC-2a to Subject to Mandatory Enforcement
3.28 2/6/2017 Standards Information (mb) Updated BAL-002-2 with effective date. Added Inactive date for BAL-002-1
3.29 2/16/2017 Standards Information (mb) Added EOP-004-4, EOP-005-3, EOP-006-3, and EOP-008-2 as Pending Regulatory Filing
3.3 3/2/2017 Standards Information (mb) Added CIP-003-7, IRO-002-5, TOP-001-4, VAR-501-WECC-3
3.31 3/3/2017 Standards Information (mb) Changed status of CIP-003-7 to Filed and Pending Regulatory Approval
3.32 3/8/2017 Standards Information (mb) Changed status of IRO-002-5 and TOP-001-4 to Filed and Pending Regulatory Approval
3.33 3/8/2017 Standards Information (mb) Added RSAWs for TOP-001-3, FAC-010-3, EOP-011-1, and EOP-004-3
3.34 3/10/2017 Standards Information (mb) Added RSAWS for IRO-014-3, IRO-017-1, and PRC-010-2.
Changed the status of BAL-002-1a to Pending Inactive
3.35 3/15/2017 Standards Information (mb) Changed status: VAR-501-WECC-3 to Filed and Pending Regulatory Approval;
Changed status to Pending Inactive: PRC-020-0, PRC-012-0, PRC-012-1, PRC-13-0, PRC-013-1, PRC-014-0, PRC-014-1, RIO-018-1, TOP-010-1
New Pending Inactive Status: A standard becomes Pending Inactive once determined that it will not become enforceable and has been superseded by another standard. The status will change to inactive at midnight on the day immediately prior to the effective date of the superseding standard.
4 3/15/2017 Standards Information (mb) Changed header column from Enforcement Date to 'Effective Date of Standard'
4.1 3/17/2017 Standards Information (mb) Changed BAL-004-0 to inactive
4.2 3/28/2017 Standards Information (mb) Changed the status of EOP-004-4, EOP-005-3, EOP-006-3, and EOP-008-2 to Filed and Pending Regulatory Approval
4.2 3/28/2017 Standards Information (mb) Changed the status of VAR-501-WECC-3 to Filed and Pending Regulatory Approval
4.2 3/28/2017 Standards Information (mb) Changed the status of TOP-007-WECC-1a to Inactive
4.3 4/3/2017 Standards Information (mb) Changed to Mandatory Enforceable: EOP-004-3, EOP-011-1, FAC-010-3, FAC-011-3, IRO-001-4, IRO-002-4, IRO-008-2, IRO-014-3, IRO-017-1, MOD-029-2a, MOD-030-3, PRC-004-5(i), PRC-004-WECC-2, PRC-010-2, PRC-015-1, PRC-016-1, PRC-017-1, PRC-023-4, TOP-001-3, TOP-002-4
4.3 4/3/2017 Standards Information (mb) Changed to Inactive: EOP-001-2.1b, EOP-002-3.1, EOP-003-2, EOP-004-2, FAC-010-2.1, FAC-011-2, IRO-001-1.1, IRO-002-2, IRO-003-2, IRO-005-3.1a, IRO-008-1, IRO-010-1a, IRO-014-1, IRO-015-1, IRO-016-1, MOD-029-1a, MOD-030-2, PER-001-0.2, PRC-004-4(i), PRC-004-5, PRC-004-WECC-1, PRC-010-0, PRC-010-1, PRC-015-0, PRC-016-0.1, PRC-017-0, PRC-022-1, PRC-023-3, TOP-001-1a, TOP-002-2.1b, TOP-003-1, TOP-004-2, TOP-005-2a, TOP-006-2, TOP-007-0, TOP-008-1
4.4 4/10/2017 Standards Information (mb) Added RSAW for MOD-033-1
4.5 4/24/2017 Standards Information (mb) Changed status of IRO-002-5 and TOP-001-4 to Subject to Future Enforcement and added Effective Dates. Added Inactive dates for IRO-002-4 and TOP-001-3.
4.6 5/2/2017 Standards Information (mb) Changed the status of VAR-501-WECC-3 to Subject to Future Enforcement and added Inactive date for VAR-501-WECC-2
4.7 5/22/2017 Standards Information (mb) Changed the status of BAL-002-1a to inactive. Changed the status of BAL-004-0 to Subject to Enforcement. (See Public Note column.)
4.8 5/25/2017 Standards Information (mb) Replaced updated RSAWS for COM-001-2.1, TOP-001-3, TPL-007-1, VAR-001-4.1 and MOD-025-2
4.9 6/12/2017 Standards Information (mb) Added RSAW for COM-001-3
4.1 6/21/2017 Standards Information (mb) CIP-014-1 changed to inactive status; IRO-010-2 to mandatory enforcement
4.11 7/3/2017 Standards Information (mb) MOD-033-1, TPL-007-1 and VAR-501-WECC-3 changed to subject to enforcement. VAR-501-WECC-2 changed to inactive status.
Added public note for PRC-025-1.
4.12 7/14/2017 Standards Information (mb) Updated project page link for PRC-014-1 to project 2010-05.3 phase 3
4.13 8/28/2017 Standards Information (mb) Updated the following standards: BAL-002-2(i), CIP-005-6, CIP-010-3, CIP-013-1, PRC-006-SERC-02, VAR-001-4.2, VAR-002-4.1. Added RSAW IRO-002-5.
4.14 9/6/2017 Standards Information (mb) Added VAR-501-WECC-3.1, BAL-502-RF-03, and PRC-006-3
4.15 9/7/2017 Standards Information (mb) Changed the status of BAL-502-RF-03 to Filed and Pending Regulatory Approval
4.16 9/12/2017 Standards Information (mb) Changed the status of PRC-006-SERC-02 to Filed and Pending Regulatory Approval
4.17 9/21/2017 Standards Information (mb) Added effective date for PRC-006-3 and inactive date for PRC-006-2.
4.18 9/27/2017 Standards Information (mb) Changed the status of CIP-005-6, CIP-010-3 and CIP-013-1 to Filed and Pending Regulatory Approval.
BAL-005-1, FAC-001-3, PRC-012-2 FERC approved - Effective Dates to be entered soon.
VAR-001-4.2, VAR-002-4.1, VAR-501-WECC-3.1 - FERC approved - Effective Dates to be entered soon.
4.19 10/2/2017 Standards Information (mb) Changed the status of: COM-001-3, COM-001-2.1; IRO-002-5, IRO-002-4; PRC-006-3, PRC-006-2
4.2 10/4/2017 Standards Information (mb) Added Effective Date for PRC-012-2. Added Inactive Dates for: PRC-012-1, PRC-013-1, PRC-014-1, PRC-015-1, PRC-016-1. Added a public note for PRC-006-3 for clarification.
4.21 10/5/2017 Standards Information (mb) Added Effective Dates for BAL-005-1, FAC-001-3, VAR-001-4.2, VAR-002-4.1, VAR-501-WECC-3.1. Added Inactive Dates for: VAR-001-4.1, VAR-002-4, VAR-501-WECC-3, BAL-005-0.2b, BAL-006-2, FAC-001-2
4.22 10/11/2017 Standards Information (mb) Adjusted the effective date of VAR-002-4.1 and inactive date of VAR-002-4
4.23 10/12/2017 Standards Information (mb) Added RSAWS: BAL-002-2, IRO-018-1(i), TOP-010-1(i), PRC-026-1
4.24 10/12/2017 Standards Information (mb) VAR-001-4.2 and VAR-501-WECC-3.1 were updated to reflect a 9/26/17 effective date. VAR-001-4.1 and VAR-501-WECC-3 inactive dates were updated to reflect 9/25/2017.
4.25 10/25/2017 Standards Information (mb) Added effective dates for PRC-006-SERC-02, BAL-502-RF-03 . Added inactive dates for PRC-006-SERC-01, BAL-502-RF-02
4.26 11/12/2017 Standards Information (mb) Added TPL-007-2
4.27 11/15/2017 Standards Information (mb) Updated TOP-006-3 status to inactive
4.28 12/5/2017 Standards Information (mb) Updated RSAWS: PRC-006-3, VAR-001-4.2, and VAR-002-4.1
4.29 1/2/2018 Standards Information (mb) Changed the status of the following to subject to enforcement: BAL-002-2; BAL-502-RF-03; PRC-006-SERC-02; PRC-026-1.
Changed the status of the following to inactive: BAL-002-1; BAL-502-RFC-02; PRC-006-SERC-01
4.3 1/18/2018 Standards Information (mb) Replace with an errata Implementation Plan for TPL-007-2. Non-substantive changes were made to ensure that, in the event of prompt regulatory approval, entities would not have to comply with TPL-007 requirements under the TPL-007-2 Implementation Plan before the dates originally set forth in the TPL-007-1 Implementation Plan.
4.31 1/22/2018 Standards Information (mb) Changed status to Subject to Future Enforcement: EOP-004-4, EOP-005-3, EOP-006-3, EOP-008-2
4.32 1/24/2018 Standards Information (mb) Changed status of TPL-007-2 to Filed and Pending Regulatory Approval
4.33 2/5/2018 Standards Information (NS) Updated inactive date for BAL-002-2 and added effective date for BAL-002-2(i).
4.34 2/16/2018 Standards Information (NS) Added PRC-025-2, FAC-501-WECC-2 and BAL-004-WECC-3 as Pending Regulatory Filing.
4.35 3/8/2018 Standards Information (NS) Added public notes for VAR-002-WECC-2
4.36 3/12/2018 Standards Information (NS) Updated status of BAL-004-WECC-3 to Filed and Pending Regulatory Approval. Added public note.
4.37 3/26/2018 Standards Information (NS) Added effective date to EOP-004-4, EOP-005-3, EOP-006-3, EOP-008-2. Added RSAWs for BAL-003-1.1 and INT-004-3.1 to reflect correct standards' names. Updated status of PRC-025-2and FAC-501-WECC-2 to Filed and Pending.
4.38 3/29/2018 Standards Information (NS) Added Inactive date to BAL-004-0 and updated status to Inactive.
4.39 4/23/2018 Standards Information (NS) Added effective date and updated IRO-018-1(i), TOP-010-1(i) and BAL-002-2(i) status to Subject to Enforcement. Added Inactive dates to IRO-018-1, TOP-010-1 and updated status to Inactive. Added inactive date to EOP-004-3, EOP-005-2, EOP-006-2 and EOP-008-1. Updated status of EOP-004-4, EOP-005-3, EOP-006-3 and EOP-008-2 to Subject to Future Enforcement.
4.4 4/30/2018 Standards Information (NS) Updated status of CIP-003-7 to "Subject to Future Enforcement" and added effective date; Added Inactive Date for CIP-003-6. Added FERC Order.
4.41 5/14/2018 Standards Information (NS) Updated status of PRC-025-2 to "Subject to Future Enforcement"; added effective date. Added FERC Order link and date. Added inactive date to PRC-025-1.
4.42 5/25/2018 Standards Information (NS) Updated public note for CIP-003-6. Added PER-003-2 as Filed and Pending Regulatory Approval.
4.43 6/6/2018 Standards Information (NS) Updated public note for CIP-003-6. Updated status of BAL-004-WECC-3 and FAC-501-WECC-2. Added inactive dates to BAL-004-WECC-2 and FAC-501-WECC-1.
4.44 6/15/2018 Standards Information (NS) Updated link to the CIP-003-7 Implementation Plan.
4.45 6/26/2018 Standards Information (NS) Updated status of PER-006-1 and PRC-027-1 to Subject to Future Enforcement; added effective date. Added inactive dates to PRC-001-1.1(ii).
4.46 7/2/2018 Standards Information (NS) Updated status of FAC-501-WECC-1, PRC-025-1 and TOP-001-3 to Inactive. Updated status of FAC-501-WECC-2, PRC-025-2 and TOP-001-4 to Mandatory Subject to Enforcement. Added FERC Order date and link for TOP-001-4.
4.47 7/30/2018 Standards Information (NS) Updated status of PER-003-2 to Filed and Pending Regulatory Approval.
4.48 8/24/2018 Standards Information (NS) Added BAL-002-3 as Filed and Pending Regulatory Approval. Added FERC order links and RSAWs for BAL-002-2(i), BAL-005-1, FAC-001-3, and PRC-025-2. Added CIP-012-1 and VAR-001-5 as NERC Board Adopted; included links to the associated implementation plans.
4.49 9/18/2018 Standards Information (NS) Updated status of VAR-002-WECC-2 to Inactive. Updated status of VAR-001-5 to Filed and Pending Regulatory Approval and added Implementation Plan. Updated CIP-012-1 to Filed and Pending Regulatory Approval.
4.5 10/1/2018 Standards Information (NS) Updated status of BAL-004-WECC-3 to Mandatory Subject to Enforcement and BAL-004-WECC-02 to Inactive.
4.51 10/3/2018 Standards Information (NS) Updated Status of BAL-002-3 to Subject to Future Enforcement; added effective date and FERC Order date/link. Added Inactive date to BAL-002-2(i)
4.52 10/23/2018 Standards Information (NS) Updated RSAW link for MOD-026-1
4.53 10/30/2018 Standards Information (NS) Updated status of CIP-005-6, CIP-010-3 and CIP-013-1 to "Subject to Future Enforcement". Added Effective Date and FERC Order date/link. Added "Inactive" date for CIP-005-5 and CIP-010-2.
4.54 11/8/2018 Standards Information (NS) Added TPL-001-5 as "Pending Regulatory Filing"; Updated status of VAR-001-5 to "Subject to Future Enforcement"; added link to the FERC Order. Added RSAW links for EOP-005-3 and EOP-008-2.
4.55 11/14/2018 Standards Information (NS) Added effective date to VAR-001-5 and inactive date to VAR-001-4.2.
4.56 12/4/2018 Standards Information (NS) Added link to FERC order and updated status of TPL-007-2 to "Subject to Future Enforcement"; added Inactive date to TPL-007-1.
4.57 12/31/2018 Standards Information (NS) Updated status to "Mandatory Subject to Enforcement" for BAL-005-1, FAC-001-3 and VAR-001-5. Updated status to "Inactive" for BAL-005-0.2b, FAC-001-2 and VAR-001-4.2.
4.58 2/1/2019 Standards Information (NS) Added RSAWs for BAL-002-3, VAR-001-5, EOP-004-4, EOP-006-3, CIP-002-5.1a, and TOP-010-1. Added Compliance Guidance for PRC-024-2, TOP-001-3, PRC-023-4, PRC-005-6, CIP-010-3, FAC-008-3, CIP-004-6, MOD-033-1, CIP-013-1, TPL-001-4, TPL-007-1.
4.59 2/14/2019 Standards Information (NS) Updated status of PER-003-2 to Subject to Future Enforcement; added Effective Date and FERC Order.
4.60 2/21/2019 Standards Information (NS) Added TPL-007-3 as Filed and Pending; added CIP-008-6 and IRO-006-WECC-3 as Pending Regulatory Filing.
4.61 3/1/2019 Standards Information (NS) Added effective dates for TPL-007-3. TPL-007-3 adds a Variance for Canadian entities. Under the terms of the TPL-007-3 implementation plan, TPL-007-3 will supersede TPL-007-2 in the U.S. All phased-in compliance dates are carried forward unchanged.
4.62 3/8/2019 Standards Information (NS) Updated status of CIP-008-6 and IRO-006-WECC-3 to Filed and Pending Regulatory Approval. Added Inactive date to IRO-006-TRE-1. Added CR Form 1 to BAL-002-3.
4.63 3/28/2019 Standards Information (NS) Added Inactive date to PRC-004-WECC-2.
4.64 4/8/2019 Standards Information (NS) Updated status of BAL-002-2(i), EOP-004-3, EOP-005-2, EOP-006-2 and EOP-008-1 to Inactive. Updated status of BAL-002-3, EOP-004-4, EOP-005-3, EOP-006-3 and EOP-008-2 to Mandatory Subject ot Enforcement.
4.65 5/3/2019 Standards Information (NS) Added RSAW for PER-003-2 and TPL-007-3.
4.66 5/10/2019 Standards Information (NS) Added Inactive date to IRO-006-WECC-2. Updated status of IRO-006-WECC-3 to Subject to Future Enforcement and added effective date.
4.67 5/14/2019 Standards Information (NS) Added IRO-002-6 and IRO-002-7 as Pending Regulatory Filing.
4.68 5/21/2019 Standards Information (NS) Added CIP-003-8 as Filed and Pending.
4.69 6/5/2019 Standards Information (NS) Added FAC-008-4, INT-006-5, INT-009-3, PRC-004-6, TOP-001-5, VAR-001-6 as Pending Regulatory Filing.
4.70 6/6/2019 Standards Information (NS) Added RSAW for CIP-003-7.
4.71 7/11/2019 Standards Information (NS) Added Inactive date to CIP-008-5. Added Effective date and updated status of CIP-008-6 to Subject to Future Enforcement. Added Inactive date to IRO-002-5; added Effective date to IRO-002-6.
4.72 8/22/2019 Standards Information (NS) Updated status of TPL-007-1, TPL-007-2 to Inactive and TPL-007-3 to Mandatory Subject to Enforcement.
4.73 8/23/2019 Standards Information (NS) Updated status of CIP-003-8 to Subject to Future Enforcement; added Implementation Plan and FERC Order. Added Inactive date to CIP-003-7.
4.74 9/5/2019 Standards Information (NS) Added BAL-002-WECC-3 as Pending Regulatory Filing; added Implementation Plan. Updated status of PER-003-1 and PER-004-2 to Inactive.
4.75 9/6/2019 Standards Information (NS) Updated status of BAL-002-WECC-3 to Filed and Pending Regulatory Approval.
4.76 10/2/2019 Standards Information (NS) Updated status of IRO-006-WECC-3 and PER-003-2 to Mandatory Subject to Enforcement. Updated status of IRO-006-WECC-2 and PER-003-1 to Inactive.
4.77 10/3/2019 Standards Information (NS) Updated Status of FAC-008-4, INT-006-5, INT-009-3, PRC-004-6, TOP-001-5, VAR-001-6 to Filed and Pending Regulatory Approval. Updated status of MOD-001-2 to Pending Inactive.
4.78 11/5/2019 Standards Information (NS) Added BAL-003-2 and PRC-006-NPCC-2 as Pending Regulatory Filing.
4.79 12/4/2019 Standards Information (NS) Added Implementation Plan for IRO-002-6.
4.80 12/19/2019 Standards Information (NS) Updated status to "Filed and Pending Regulatory Approval" for BAL-003-2. Added RSAW for IRO-002-6.
4.81 12/23/2019 Standards Information (NS) Updated status to "filed and Pending Regulatory Approval" for PRC-006-NPCC-2.
4.82 1/2/2020 Standards Information (NS) Updated status to "Inactive" for CIP-003-6 and IRO-002-5. Updated status to "Mandatory Subject to Enforcement" for CIP-003-7 and IRO-002-6.
4.83 2/6/2020 Standards Information (NS) Added FERC Order date and link for MOD-031-2.
4.84 2/19/2020 Standards Information (NS) Added effective date to CIP-012-1 and TPL-001-5; updated status to "Subject to Future Enforcement" and added inactive date to TPL-001-4.
4.85 2/20/2020 Standards Information (NS) Added TPL-007-4 as Filed and Pending Regulatory Approval. Added FAC-002-3, IRO-010-3, MOD-031-3, MOD-033-2, NUC-001-4, PRC-006-4, TOP-003-4, PRC-024-3, BAL-001-TRE-2 as Pending Regulatory Filing.
4.86 2/25/2019 Standards Information (NS) Updated FAC-002-3, IRO-010-3, MOD-031-3, MOD-033-2, NUC-001-4, PRC-006-4, TOP-003-4 to Filed and Pending Regulattory Approval.
4.87 3/4/2020 Standards Information (NS) Added effective date to PRC-006-NPCC-2 and inactive date to PRC-006-NPCC-1.
4.88 3/31/2020 Standards Information (NS) Updated status of PRC-024-3 to Filed and Pending Regulatory Approval and TPL-007-4 to Subject to Future Enforcement. Added inactive date for TPL-007-3 and effective date for TPL-007-4.
4.89 4/2/2020 Standards Information (NS) Added FERC Orders for PRC-002-2 and PRC-012-2. Also added RSAWs for CIP-005-6, CIP-010-3 and CIP-013-1.
4.90 5/15/2020 Standards Information (NS) Updated the following due to COVID-19 related FERC Order:
1) inactive dates for CIP-005-5, CIP-010-2, PRC-001-1(
2) effective dates for CIP-005-6, CIP-010-3, CIP-013-1, PER-006-1, PRC-027-1 and
3) phased in effective dates for PRC-002-2 amd PRC-025-2.
4.91 6/23/2020 Standards Information (NS) Removed links to the CIP-003-6 and CIP-003-7 as they have retired and are archived.
4.92 6/25/2020 Standards Information (NS) Updated inactive date BAL-001-TRE-1 and effective date of BAL-001-TRE-2.
4.93 7/1/2020 Standards Information (NS) Updated status of BAL-001-TRE-1 to Inactive and BAL-001-TRE-2 to Mandatory Subject to Enforcement
4.94 7/24/2020 Standards Information (NS) Updated status of BAL-003-2 and PRC-024-3; added effective dates. Added inactive dates to BAL-003-1.1 and PRC-024-2.
4.95 7/27/2020 Standards Information (NS) Added CIP-002-6
4.96 7/29/2020 Standards Information (NS) Added TPL-001-5.1 as Subject to Future Enforcement
4.97 8/28/2020 Standards Information (KH) Added PRC-006-5 as Pending Regulatory Filing.
4.98 8/31/2020 Standards Information (KH) Updated links for TPL-001-5 and TPL-001-5.1
4.99 9/8/2020 Standards Information (KH) Updated status to inactive for TPL-001-5
5.0 9/16/2020 Standards Information (KH) Updated status of CIP-003-7 to Inactive and CIP-003-8 to Mandatory Subject to Enforcement
5.1 9/28/2020 Standards Information (KH) Added RSAW links for BAL-003-2 and TPL-007-4 to Mandatory Subject to Enforcement
5.2 9/28/2020 Standards Information (KH) Updated Status of TPL-007-3 to Inactive as 9/30/2020
5.3 10/5/2020 Standards Information (KH) Updated Status of CIP-005-5 to Inactive and CIP-005-6 to Mandatory Subject to Enforcement
5.4 10/5/2020 Standards Information (KH) Updated Status of CIP-010-2 to Inactive and CIP-010-3 to Mandatory Subject to Enforcement
5.5 10/5/2020 Standards Information (KH) Updated CIP-013-1 to Mandatory Subject to Enforcement
5.6 10/5/2020 Standards Information (KH) Updated Status of PRC-027-1 to Mandatory Subject to Enforcement
5.7 10/5/2020 Standards Information (KH) Updated Status of PRC-001-1.1(ii) to Inactive as of 9/30/2020
5.8 10/7/2020 Standards Information (KH) Updated Status of PRC-026-1 to Subject to Future Enforcement
5.9 10/23/2020 Standards Information (KH) Updated Status of PRC-012-2 with RSAW
5.10 10/27/2020 Standards Information (KH) Updated status of INT-006-4 ,INT-009-2.1, PRC-004-5(i), IRO-002-5/-6, TOP-001-4 Added Inactive Date
5.11 10/27/2021 Standards Information (KH) Updated status of FAC-013-2, INT-004-3.1 , INT-010-2.1, MOD-020-0 to Added Inactive Dates
5.12 10/27/2020 Standards Information (KH) Updated Status of PRC-027-1 and PRC-001-1.1 (ii) to Subject to Future Enforcement
5.13 11/5/2020 Standards Information (KH) Updated Status of CIP-008-6 with RSAW
5.14 11/12/2020 Standards Information (KH) Updated status of INT-006-5 ,INT-009-3,PRC-004-6 ,IRO-002-7 and TOP-001-5 to Added Subject to Future Enforcement
5.15 11/17/2020 Standards Information (KH) Added CIP-005-7,CIP-010-4,CIP-013-2 Pending Regulatory Filing.
5.16 11/30/2020 Standards Information (KH) Updated staus of FAC-002-3,IRO-010-3,MOD-031-3,MOD-033-2,NUC-001-4,PRC-006-4,TOP-003-4 to Mandatory Subject to Enforcement
5.17 11/30/2020 Standards Information (KH) Updated status of INT-006-4,INT-009-2.1,IRO-002-6,PRC-004-5(i) to Inactive Date 3/1/2021
5.18 11/30/2020 Standards Information (KH) Updated status of VAR-001-6 to Withdrawn as of 5/14/2020
5.19 12/8/2020 Standards Information (KH) Updated status of BAL-003-1.1 to Inactive and BAL-003-2 to Mandatory Subject to Enforcement
5.20 12/14/2020 Standards Information (KH) Updated status of FAC-013-2,INT-004-3.1, INT-010-2.1, MOD-020-0 to Inactive
5.21 1/4/2021 Standards Information (KH) Updated status of CIP-008-5,PRC-012-1,PRC-013-1,PRC-014-1,PRC-015-1,PRC-016-1,PRC-004-WECC-2 to Inactive
5.22 1/4/2021 Standards Information (KH) Updated status of PRC-012-2,CIP-008-6 to Mandatory Subject to Enforcement
5.23 1/11/2021 Standards Information (KH) Updated status of FAC-002-2 to Inactive 3/31/2021
5.24 1/13/2021 Standards Information (KH) Updated status of IRO-010-2,MOD-031-2,TOP-003-3 to Inactive 3/31/2021
5.25 1/22/2021 Standards Information (KH) Updated status of MOD-033-1,NUC-001-3,PER-005-2,PRC-006-3 to Inactive 3/31/2021
5.26 1/22/2021 Standards Information (KH) Updated status of VAR-001-6 to to Filed and Pending Regulatory Approval
5.27 1/25/2021 Standards Information (KH) Updated status of VAR-001-6 ,MOD-001-02,IRO-014-2,PRC-020-1,PRC-012-0,PRC-013-0,PRC-014-0 to Inactive
5.28 1/26/2021 Standards Information (KH) Updated status of FAC-002-3,IRO-010-3,MOD-031-3,MOD-33-2,PRC-004-6,PRC-006-4,TOP-003-4 to Mandatory Subject to Future Enforcement
5.29 2/2/2021 Standards Information (KH) Updated status of PRC-006-5 to Subject to Future Enforcement
5.30 2/2/2021 Standards Information (KH) Updated status of PRC-006- to Inactive 6/30/2021
5.31 2/2/2021 Standards Information (KH) Updated status of TOP-001-4 to Inactive 3/31/2021
5.32 3/1/2021 Standards Information (KH) Updated status of PRC-006-4 to Pending Inactive 3/31/2021
5.33 3/15/2021 Standards Information (KH) Updated status of CIP-002-6 to Withdrawn 2/4/2021
5.34 3/18/2021 Standards Information (KH) Added RSAW for FAC-002-3, IRO-010-3, MOD-031-3, MOD-033-2, NUC-001-4, PRC-006-5, TOP-003-4, INT-006-5,INT-009-3, PRC-004-6,TOP-001-5
5.35 3/29/2021 Standards Information (KH) Added RSAW for IRO-002-7
5.36 4/5/2021 Standards Information (KH) Updated status of CIP-005-7,CIP-010-4,CIP-013-2 Subject to Future Enforcement
5.37 4/12/2021 Standards Information (KH) Added FAC-008-5 Subject to Future Enforcement
5.38 4/12/2021 Standards Information (KH) Updated Status of FAC-008-3 to Inactive 9/30/2021
5.39 4/12/2021 Standards Information (KH) Updated Status of FAC-008-4 to Withdrawn
5.40 5/4/2021 Standards Information (KH) Updated Status of PRC-006-5 to Subject to Mandatory Enforcement
5.41 5/4/2021 Standards Information (KH) Updated Status of BAL-002-WECC-3 to Subject to Future Enforcement
5.42 5/10/2021 Standards Information (KH) Updated Status of PRC-002-2 FERC Order link
5.43 5/20/2021 Standards Information (KH) Updated FAC-008-5 Mandatory Subject to Enforcement
5.44 6/23/2021 Standards Information (KH) Updated EOP-011-2,IRO-010-4,TOP-003-5 to Pending Regulatory Approval
5.45 7/7/2021 Standards Information (KH) Updated FAC-003-5,FAC-011-4,FAC-014-3,IRO-008-3,PRC-002-3,PRC-023-5 PRC-026-2,TOP-001-6 to Pending Regulatory Approval
5.46 7/14/2021 Standards Information (KH) Updated RSAW for PRC-024-2
5.47 8/11/2021 Standards Information (KH) Updated PRC-006-SERC-03 to Pending Regulatory Approval
5.48 8/13/2021 Standards Information (KH) Updated CIP-004-7 and CIP-011-3 to Filed and Pending Regulatory Approval
5.49 9/20/2021 Standards Information (KH) Updated FAC-008-5 with RSAW
5.50 9/30/2021 Standards Information (KH) Updated Status of FAC-008-03 to Inactive 9/30/2021
5.51 9/30/2021 Standards Information (KH) Updated Status of FAC-008-05 to Mandatory Subject to Enforcement 10/1/2021

The words contained in this file might help you see if this file matches what you are looking for:

...Sheet us standard onestopshop status version title with link to project page purpose board adopted date effective of inactive standards is in the process adding remaining implemenation plans implementation plan related documents public notes ferc orders issued rsaws enforceable only lessons learned compliance guidance bal real power balancing control performance maintain interconnection steadystate frequency within defined limits by demand and supply realtime rsaw mandatory subject enforcement replaced baltre primary response ercot region please see for specific dates timeframes disturbance dcs ensure authority able utilize its contingency reserve balance resources return following a reportable because generator failures are far more common than significant losses load activation does not typically apply loss application limited bala was never approved or amended notice withdrawal filed approval ndash recovery from event sharing group balances returns s area error values applicable i r...

no reviews yet
Please Login to review.