jagomart
digital resources
picture1_Area Ppt 78901 | Requirements For Wind Farms Wfs Grid


 146x       Filetype PPTX       File size 0.74 MB       Source: www.entsoe.eu


File: Area Ppt 78901 | Requirements For Wind Farms Wfs Grid
requirements for wind farms wfs grid connection frequency and voltage operation boundaries all wtgs should stay connected within the boundary 47 0 51 5 hz all wtgs should disconnect with ...

icon picture PPTX Filetype Power Point PPTX | Posted on 06 Sep 2022 | 3 years ago
Partial capture of text on file.
           Requirements for Wind Farms (WFs) Grid connection
                   Frequency and Voltage Operation Boundaries
       •   All WTGs should stay connected within the boundary 47.0 - 51.5 Hz 
       •   All WTGs should disconnect with no delay for system frequency < 47Hz 
       •   The disconnection of WTGs for system frequency > 51.5Hz takes place in 4 steps, with a 0.5sec 
           delay between each step
       •   In each step, 25% of the operating WTGs is disconnected 
       •   Applicable to all WFs
                                                                                                                         2
           Requirements for Wind Farms (WFs) Grid connection
                              Active/Reactive Power Boundaries
         Upper diagram : Q-V curve
         •   Within the no-striped area (PF> 0.95) the WF 
             should operate at it’s nominal capacity
         •   Within the striped area (0.835  10 
             MW
      Requirements for Wind Farms (WFs) Grid connection
                 Voltage/Reactive Power Control
    • Upon TSO’s request, the WF should operate in 
      voltage, reactive power or PF control mode
      – Voltage regulation is applied at system connection point 
       (HV/150kV), reactive power and power factor regulation is 
       applied at the MV (20kV) side of WF step up transformer
    • The WF should be equipped with 
      voltage/reactive power regulator according a HV 
      Q–V characteristic 
      – The slope and the reference value Vset (zero reactive power 
       injection at the MV (20kV) side of WF step up transformer are 
       defined by the TSO
    • The desired value of the controlled quantity 
      should be implemented within 30sec after signal 
      receiving
    • speed of regulation response : 
      – in a voltage step change at the connection point (or a 
       step change of reactive power or power factor 
       reference value) the reactive power of the WF should 
       reach 90% of the steady state value in less than 1s
    • Applicable to WFs with installed capacity  > 10 
      MW
      Requirements for Wind Farms (WFs) Grid connection
                   Load-Frequency control
    • At TSO’s command, the WF should 
     change the active power ramp up/down 
     rate (±MW/min)
      – Min and max limits of ramp up/down rates are set 
       by the TSO
      – Active power measurement applies at the MV 
       (20kV) side of WF step up (150/20) transformer 
    • The WF should be equipped with a load-
     frequency controller (characteristic f-P) 
      – Frequency measurement precision ±10mHz 
      – Points Β and Γ define a dead zone within the WF 
       should operate with a constant percentage (% 
       P/Pmax) of the available active power
      – Table values are defined by the TSO
    • TSO’s command for reduction of the 
     production should be implemented 
     within 60s after signal receiving
    • Applicable to WFs with installed capacity  
     > 10 MW
           Requirements for Wind Farms (WFs) Grid connection
                          Low Voltage Ride Through capability
        •  Applicable to all WTGs, voltage is measured at the 
           HV connection point
        •  Disconnection is allowed in area 1 
             –  Reconnection after fault clearance, within 2sec, with a rate 
                10-20% Pmax/sec
        •  Disconnection is allowed in area 2 
             –  Disconnection in 4 steps, with 0.3sec delay between each 
                step, shed 25% of WFs WTGS at each step
             –  Reconnection when the voltage at the connection point (HV) 
                is greater than 142,5kV or 380 kV
        •  After fault clearance, WTGs not disconnected 
           should increase their production with a rate of 10-
           20% Pmax/sec  
        •  Reactive current control 
             –  WTG nominal values Ηare the reference values
             –  For a ±10% Vnom voltage change, the control is activated 
                within 20msec after fault detection
             –  Provision of reactive current ± 2% Ιnom for each ±1% ΔVnom
             –  For voltage sags 50% Vnom , provision of reactive current 
                +100 % Ιnom within 70 msec after fault detection 
             –  Provision of reactive current applies for 500 msec  after 
                voltage recovery within ±10% Vnom band
The words contained in this file might help you see if this file matches what you are looking for:

...Requirements for wind farms wfs grid connection frequency and voltage operation boundaries all wtgs should stay connected within the boundary hz disconnect with no delay system disconnection of takes place in steps a sec between each step operating is disconnected applicable to active reactive power upper diagram q v curve striped area pf wf operate at it s nominal capacity mw low ride through capability measured hv point allowed reconnection after fault clearance rate pmax shed when greater than kv or not increase their production current control wtg values are reference vnom change activated msec detection provision nom sags applies recovery band...

no reviews yet
Please Login to review.