     SESSION OVERVIEW
     •  Status of Consultation Process
     •  Local Limit and Wind Speed Changes
     •  Extreme Wind Cut-out / Other Cut-out
     •  “Possible Power” / “Estimated Power” Proposal
     •  Next Steps
                                                                SLIDE 2
     CURRENT STATUS OF CONSULTATION 
     PROCESS
         Stage                           Date
         Issues Paper                    18 March 2016
         First stage submissions         27 May 2016
         Draft Report                    2 August 2016
         Second stage submissions        25 August 2016
         Final report due (currently)    7 October 2016
     •  Draft Report stated
        o Local Limit and Wind Speed minor amendments
        o “Possible Power” excluded
        o Extreme-wind cut-out SCADA proposed
    Strong participant feedback in second stage raised 
      
    question whether AEMO should extend consultation to 
    include new functionality – discussed in following slides SLIDE 3
     LOCAL LIMIT AND WIND SPEED
     •  Local Limit SCADA signal resolved
        o Small amendments following second stage consultation
        o AEMO working on distribution network limit constraint 
           equations
     •  Wind Speed SCADA signal definition resolved
                                                                 SLIDE 4
     TURBINE CUT-OUT
     •  Draft report proposed new “Extreme wind cut-out” SCADA
        o To improve accuracy of AWEFS dispatch forecast when wind 
            farm constrained during extreme wind events
     •  Feedback in submissions:
        o May be expensive or difficult for some farms
        o Many causes for cut-out or reduced production
     •  Ideas for a signal to allow AWEFS to model more of this 
        behaviour more accurately in dispatch?
        o Turbines ready-to-run in next 5 minutes?
        o Share of capacity ready-to-run in next 5 minutes?
     •  AEMO needs some signal to represent what’s happening in 
        times of cut-out
                                                                       SLIDE 5
     “ESTIMATED POWER” PROPOSAL
     •   Substantial participant feedback in second stage
     •   “Estimated Power” name to avoid confusion with existing 
         “Possible Power” in control systems
     •   Participants keen to provide a signal to incorporate all factors 
         affecting wind farm operation, including:
         o Wind speed / direction at each turbine
         o Effects of high wind speed,  extreme wind direction change, site 
            temperature, wind sector management
         o Dynamic effects of turbine pausing and feathering
                                                                        SLIDE 6
The words contained in this file might help you see if this file matches what you are looking for:

...Session overview status of consultation process local limit and wind speed changes extreme cut out other possible power estimated proposal next steps slide current stage date issues paper march first submissions may draft report august second final due currently october stated o minor amendments excluded scada proposed strong participant feedback in raised question whether aemo should extend to include new functionality discussed following slides signal resolved small working on distribution network constraint equations definition turbine improve accuracy awefs dispatch forecast when farm constrained during events be expensive or difficult for some farms many causes reduced production ideas a allow model more this behaviour accurately turbines ready run minutes share capacity needs represent what s happening times substantial name avoid confusion with existing control systems participants keen provide incorporate all factors affecting operation including direction at each effects high ...

no reviews yet
Please Login to review.