Sheet 1: Summary







TRAIL DEVELOPMENT COST GUIDE FOR OREGON PARKS AND RECREATION DEPARTMENTS SCORP PROJECT





1st Edition (Q4 - 2018)
ESTIMATE OF PROBABLE COST





Cost provided by DCW Cost Management
NOTE: This tool is being provided as a resource and is based on construction cost averages in 2018. It does not take recent cost increases into account. Grant applicants or anyone else using this tool should consult with local contractors, vendors, and other industry professionals to develop an accurate project budget reflective of current market rates. (JB 7/19/2022)
Item
Length Width Direct Construction Cost Construction Cost incl. Mark ups Total w. Design, Permitting, Etc. Notes





40.0% 34.6%
Trail Network - New Construction
Length (Mile) Width (LF)



1 Asphalt trail (mile) 1.00 5 145,884.44 204,238.22 $274,904.65
2 Concrete trail (mile) 1.00 5 277,884.44 389,038.22 $523,645.45
3 Gravel trail (mile) 1.00 5 74,311.11 104,035.56 $140,031.86
4 Native surface trail (mile) 1.00 5 34,320.00 48,048.00 $64,672.61













Subtotal Trail system $1,003,254.56








Boardwalk - New Construction
Length (LF) Width (LF)



1 Concrete structure 1 5 444.98 622.97 $838.52
1 Metal structure 1 5 444.98 622.97 $838.52
2 Timber structure 1 5 239.98 335.97 $452.22
3 Synthetic structure 1 5 209.98 293.97 $395.69













Subtotal Boardwalk $1,686








Trail Bridge - New Construction
Length (LF) Width (LF)



1 Concrete structure 1 12 2,573.96 3,603.54 $4,850.36
1 Metal structure 1 12 2,433.96 3,407.54 $4,586.55
2 Timber structure 1 12 1,931.96 2,704.74 $3,640.58
3 Fiberglass structure 1 12 1,789.96 2,505.94 $3,372.99













Subtotal Trail Bridge $11,600








Culvert - New Construction
Length (LF)




1 Culvert - 18" dia. or less 1
56.94 79.72 $107.31
2 Culvert - 24" dia. or less 1
70.49 98.68 $132.83
3 Culvert - 36" dia. or less 1
109.52 153.33 $206.38
4 Culvert - 48" dia. or less 1
151.15 211.61 $284.82













Subtotal Culvert $107








Parking Lot - New Construction
Length (LF) Width (LF)



1 Asphalt 9 18 1,640.04 2,296.06 $3,090.49

or # of stalls (9'x18') 1
1,640.04 2,296.06 $3,090.49
2 Concrete 9 18 2,992.74 4,189.84 $5,639.52

or # of stalls (9'x18') 1
2,992.74 4,189.84 $5,639.52
3 Gravel 9 18 674.70 944.58 $1,271.40

or # of stalls (9'x18') 1
674.70 944.58 $1,271.40













Subtotal Parking Lot $18,731








Trail Head Access Roads - New Construction
Length (Mile)




1 Asphalt 1.00
76,083.56 106,516.98 $143,371.85
2 Concrete 1.00
99,051.56 138,672.18 $186,652.75
3 Gravel 1.00
44,990.22 62,986.31 $84,779.57













Subtotal Trail Head $414,804








Restroom - New Construction
# of stalls




1 Vault






Vault - one stall 1
37,610.00 52,654.00 $70,872.28

Vault - two stall 1
33,849.00 47,388.60 $63,785.06
2 Flush






Flush - one stall 1
55,360.00 77,504.00 $104,320.38

Flush - two stall 2
99,648.00 139,507.20 $187,776.69

Flush - three to five stall 4
159,440.00 223,216.00 $300,448.74

FLush - six + 6
227,202.00 318,082.80 $428,139.45













Subtotal Restroom $1,155,343








Item
Length Width Direct Construction Cost Construction Cost incl. Mark ups Total w. Design, Permitting, Etc. Notes





0.0% 0.0%
Trail Network (Maintenance)
Length (Mile) Width (LF)



1 Asphalt trail






Major rehab 1.00 5 105,600.00 147,840.00 $198,992.64

Routine maintenance 1.00 5 50,160.00 70,224.00 $94,521.50
2 Concrete trail






Major rehab 1.00 5 258,720.00 362,208.00 $487,531.97

Routine maintenance 1.00 5 112,200.00 157,080.00 $211,429.68
3 Gravel trail






Major rehab 1.00 5 45,906.67 64,269.33 $86,506.52

Routine maintenance 1.00 5 32,193.33 45,070.67 $60,665.12
3 Native surface trail






Major rehab 1.00 5 31,680.00 44,352.00 $59,697.79

Routine maintenance 1.00 5 18,480.00 25,872.00 $34,823.71













Subtotal Trail system $1,234,168.94








Boardwalk (Maintenance)
Length (LF) Width (LF)



1 Metal structure






Major rehab 1 5 110.75 155.05 $208.70

Routine maintenance 1 5 59.13 82.78 $111.42
2 Timber structure






Major rehab 1 5 89.50 125.30 $168.65

Routine maintenance 1 5 48.50 67.90 $91.39
3 Synthetic structure






Major rehab 1 5 74.50 104.30 $140.39

Routine maintenance 1 5 41.00 57.40 $77.26













Subtotal Boardwalk $798








Trail Bridge (Maintenance)
Length (LF) Length (LF)



1 Metal structure






Major rehab 1 5 366.58 513.22 $690.79

Routine maintenance 1 5 184.29 258.01 $347.28
2 Timber structure






Major rehab 1 5 158.88 222.43 $299.38

Routine maintenance 1 5 80.44 112.61 $151.58
3 Synthetic structure






Major rehab 1 5 103.51 144.91 $195.06

Routine maintenance 1 5 52.76 73.86 $99.41













Subtotal Trail Bridge $1,783








Culvert (Maintenance)
Length (LF)




1 Culvert






Culvert - 18" dia. (routine maint.) 1
5.80 8.12 $10.93

Culvert - 18" dia. (major rehab) 1
51.25 71.75 $96.58

Culvert - 24" dia. (routine maint.) 1
7.00 9.80 $13.19

Culvert - 24" dia. (major rehab) 1
61.60 86.24 $116.08

Culvert - 36" dia. (routine maint.) 1
10.40 14.56 $19.60

Culvert - 36" dia. (major rehab) 1
92.30 129.22 $173.93

Culvert - 48" dia. (routine maint.) 1
13.80 19.32 $26.00

Culvert - 48" dia. (major rehab) 1
123.00 172.20 $231.78













Subtotal Culvert $688








Parking Lot (Maintenance)
Length (LF) Width (LF)



1 Asphalt






Major rehab 9 18 659.34 923.08 $1,242.46

or # of stalls (9'x18') 1
659.34 923.08 $1,242.46

Routine maintenance 9 18 319.14 446.80 $601.39

or # of stalls (9'x18') 1
319.14 446.80 $601.39
2 Concrete






Major rehab 9 18 2,141.64 2,998.30 $4,035.71

or # of stalls (9'x18') 1
2,141.64 2,998.30 $4,035.71

Routine maintenance 9 18 942.84 1,319.98 $1,776.69

or # of stalls (9'x18') 1
942.84 1,319.98 $1,776.69
3 Gravel






Major rehab 9 18 281.70 394.38 $530.84

or # of stalls (9'x18') 1
281.70 394.38 $530.84

Routine maintenance 9 18 197.64 276.70 $372.43

or # of stalls (9'x18') 1
197.64 276.70 $372.43













Subtotal Parking Lot $17,119








Trail Access Road
Length (Mile) Width (LF)



1 Asphalt






Major rehab 1.00 5 119,350.00 167,090.00 $224,903.14

Routine maintenance 1.00 5 63,010.00 88,214.00 $118,736.04
2 Concrete






Major rehab 1.00 5 321,310.00 449,834.00 $605,476.56

Routine maintenance 1.00 5 125,050.00 175,070.00 $235,644.22
3 Gravel






Major rehab 1.00 5 60,976.67 85,367.33 $114,904.43

Routine maintenance 1.00 5 47,698.00 66,777.20 $89,882.11













Subtotal Trail Head $1,389,547








Restroom (Maintenance)
# of stalls




1 Vault






Major rehab 1
9,850.00 13,790.00 $18,561.34

Routine maintenance 1
7,465.00 10,451.00 $14,067.05
2 Flush






Major rehab 1
9,850.00 13,790.00 $18,561.34

Routine maintenance 1
7,465.00 10,451.00 $14,067.05













Subtotal Restroom $65,257

Sheet 2: Detail

Construction Components QTY U/M Unit Rate










Trail System














Trail - Asphalt






Asphalt - 4" thk.
1 SF $3.75


Aggregate base - 6" thk.
1 SF $0.93


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$29,176.89


Trail - Concrete






Concrete - 4" thk.
1 SF $8.75


Aggregate base - 6" thk.
1 SF $0.93


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$55,576.89










Trail - Gravel






Gravel - 4" thk.
1 SF $1.04


Aggregate base - 6" thk.
1 SF $0.93


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$14,862.22










Trail - Native Surface






Trail compaction
1 SF $0.45


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$6,864.00










Boardwalk System














Boardwalk - concrete






Concrete deck, incl. frame
1 SF $65.00


Support structure/footing
1 SF $22.00


Grading - fine
1 SF $0.30


Excavation
1 SF $1.30


Site clearing/demolition
1 SF $0.40






$89.00


Boardwalk - metal






Metal grid panel
1 SF $18.50


Metal frame
1 SF $14.00


Support structure/footing
1 SF $22.00


Grading - fine
1 SF $0.30


Excavation
1 SF $1.30


Site clearing/demolition
1 SF $0.40






$56.50


Boardwalk - timber






Timber plank
1 SF $12.00


Timber frame
1 SF $12.00


Support structure/footing
1 SF $22.00


Grading - fine
1 SF $0.30


Excavation
1 SF $1.30


Site clearing/demolition
1 SF $0.40






$48.00


Boardwalk - fiberglass






Fiberglass plank
1 SF $7.50


Fiberglass frame
1 SF $10.50


Support structure/footing
1 SF $22.00


Grading - fine
1 SF $0.30


Excavation
1 SF $1.30


Site clearing/demolition
1 SF $0.40






$42.00










Bridge System














Bridge - concrete






Concrete deck, incl. frame
1 SF $65.00


Railing - concrete
1 SF $37.50


Support structure/footing
1 SF $110.00


Grading - fine
1 SF $0.30


Excavation
1 SF $1.30


Site clearing/demolition
1 SF $0.40






$214.50


Bridge - steel






Metal grid panel
1 SF $30.00


Metal frame
1 SF $27.50


Railing - metal
1 SF $33.33


Support structure/footing
1 SF $110.00


Grading - fine
1 SF $0.30


Excavation
1 SF $1.30


Site clearing/demolition
1 SF $0.40






$202.83


Bridge - timber






Timber plank
1 SF $12.00


Timber frame
1 SF $12.00


Railing - timber
1 SF $25.00


Support structure/footing
1 SF $110.00


Grading - fine
1 SF $0.30


Excavation
1 SF $1.30


Site clearing/demolition
1 SF $0.40






$161.00


Bridge - fiberglass






fiberglass plank
1 SF $7.50


fiberglass frame
1 SF $10.50


Railing - synthetic
1 SF $19.17


Support structure/footing
1 SF $110.00


Grading - fine
1 SF $0.30


Excavation
1 SF $1.30


Site clearing/demolition
1 SF $0.40






$149.16










Culvert














Culvert - 18" dia.






Culvert
1 LF $50.00


Aggregate base - 6" thk.
1 LF $2.78


Excavation
1 LF $2.92


Grading - fine
1 LF $0.45


Site clearing/demolition
1 LF $0.80






$56.94


Culvert - 24" dia.






Culvert
1 SF $60.00


Aggregate base - 6" thk.
1 SF $3.70


Excavation
1 SF $5.19


Grading - fine
1 SF $0.60


Site clearing/demolition
1 SF $1.00






$70.49


Culvert - 36" dia.






Culvert
1 SF $90.00


Aggregate base - 6" thk.
1 SF $5.56


Excavation
1 SF $11.67


Grading - fine
1 SF $0.90


Site clearing/demolition
1 SF $1.40






$109.52










Culvert - 48" dia.






Culvert
1 SF $120.00


Aggregate base - 6" thk.
1 SF $7.41


Excavation
1 SF $20.74


Grading - fine
1 SF $1.20


Site clearing/demolition
1 SF $1.80






$151.15










Parking Lot














Parking lot - asphalt






Asphalt - vehicular
1 SF $6.15


Striping
1 SF $0.07


Aggregate base - 6" thk.
1 SF $1.20


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Demolition - existing surface
1 SF $2.25






$10.12


Parking lot - concrete






Concrete - vehicular
1 SF $14.50


Striping
1 SF $0.07


Aggregate base - 6" thk.
1 SF $1.20


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Demolition - existing surface
1 SF $2.25






$18.47


Parking lot - gravel






Gravel - 4" thk.
1 SF $1.04


Aggregate base - 6" thk.
1 SF $0.93


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Demolition - existing surface
1 SF $1.75






$4.16










Trailhead Access Road














Trailhead - asphalt surface






Asphalt - vehicular
1 SF $6.15


Aggregate base - 6" thk.
1 SF $1.20


Entry sign - allow
1 LS $15,000.00


Planting - allow
1 LS $3,000.00


Gate/bollard - allow
1 LS $5,000.00


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Demolition - existing surface
1 SF $2.25






$76,083.56


Trailhead - concrete surface






Concrete - vehicular
1 SF $10.50


Aggregate base - 6" thk.
1 SF $1.20


Entry sign - allow
1 LS $15,000.00


Planting - allow
1 LS $3,000.00


Gate/bollard - allow
1 LS $5,000.00


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Demolition - existing surface
1 SF $2.25






$99,051.56


Trailhead - gravel surface






Gravel - 4" thk.
1 SF $1.04


Aggregate base - 6" thk.
1 SF $0.93


Entry sign - allow
1 LS $15,000.00


Planting - allow
1 LS $3,000.00


Gate/bollard - allow
1 LS $5,000.00


Grading - rough
1 SF $0.15


Grading - fine
1 SF $0.30


Demolition - existing surface
1 SF $1.75






$44,990.22










Restroom














Restroom building
48 SF



Concrete continuous footing, 16" x 18"
28 LF $2,290.00


4" slab-on grade
48 SF $504.00


Exterior wall - 8" CMU
280 SF $7,840.00


Steel roof deck assembly, incl waterproofing and insul.
60 SF $1,710.00


Ceiling and soffit panels
48 SF $504.00


Roof flashing and gutter
28 LF $560.00


Join sealant - allow
1 LS $1,000.00


Exterior door - hollow metal
1 EA $1,250.00


Exterior door hardware
1 EA $1,200.00


Floor finish - etched concrete
48 SF $480.00


Wall finish - paint
280 SF $490.00


Ceiling finish - open to structure
48 SF $84.00


Toilet room accessories
1 EA $1,450.00


Plumbing fixtures and piping - per bathroom
1 EA $4,500.00


Connection and piping to existing sewer system
1 ALW $17,500.00


Water heater
1 EA $1,250.00


Floor drain
1 EA $1,500.00


Power distribution and connection
1 LS $10,000.00


Lighting and controls - allow
48 SF $960.00


Demolition - existing surface
72 SF $288.00






$55,360.00










Flush - one stall


$55,360.00 $55,360.00


Flush - two stall


$49,824.00 $24,912.00


Flush - three to five stall


$39,860.00 $13,286.67


FLush - six +


$37,867.00










Restroom building
48 SF



Concrete continuous footing, 16" x 18"
28 LF $2,290.00


4" slab-on grade
48 SF $504.00


Exterior wall - 8" CMU
280 SF $7,840.00


Steel roof deck assembly, incl waterproofing and insul.
60 SF $1,710.00


Ceiling and soffit panels
48 SF $504.00


Roof flashing and gutter
28 LF $560.00


Join sealant - allow
1 EA $1,000.00


Exterior door - hollow metal
1 EA $1,250.00


Exterior door hardware
1 EA $1,200.00


Floor finish - etched concrete
48 SF $480.00


Wall finish - paint
280 SF $490.00


Ceiling finish - open to structure
48 SF $84.00


Toilet room accessories
1 EA $1,450.00


Plumbing fixtures and piping - per bathroom
1 EA $2,000.00


Vault system - allow
1 ALW $5,000.00


Power distribution and connection
1 LS $10,000.00


Lighting and controls - allow
48 SF $960.00


Demolition - existing surface
72 SF $288.00






$37,610.00










Vault - one stall


$37,610.00 $37,610.00


Vault - two stall


$33,849.00 $16,924.50










Trail System Maintenance














Trail - Asphalt (major rehab)






Asphalt overlay
1 SF $2.85


Base compaction
1 SF $0.40


Site clearing/demolition
1 SF $0.75






$21,120.00


Trail - Asphalt (routine maintenance)






Asphalt - patch and repair
1 SF $1.15


Site clearing/demolition
1 SF $0.75






$10,032.00


Trail - Concrete (major rehab)






Concrete - 4" thk.
1 SF $8.75


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.75






$51,744.00


Trail - Concrete (routine maintenance)






Concrete - patch and repair
1 SF $3.50


Site clearing/demolition
1 SF $0.75






$22,440.00


Trail - Gravel (major rehab)






Gravel - 4" thk.
1 SF $1.04


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$9,181.33


Trail - Gravel (routine maintenance)






Gravel - touch up 2" thk.
1 SF $0.52


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$6,438.67


Trail - Native Surface (major rehab)






Infill - replace loose material
1 SF $0.50


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$6,336.00


Trail - Native Surface (routine maintenance)






Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$3,696.00










Boardwalk System Maintenance














Boardwalk - metal (major rehab)






Metal grid panel - replace as required
1 SF $9.25


Metal frame - replace as required
1 SF $7.00


Support structure/footing - repair as required
1 SF $5.50


Site clearing/demolition
1 SF $0.40






$22.15


Boardwalk - metal (routine maintenance)






Metal grid panel - clean and repair
1 SF $4.63


Metal frame - clean and repair
1 SF $3.50


Support structure/footing - clean and repair
1 SF $3.30


Site clearing/demolition
1 SF $0.40






$11.83










Boardwalk - timber (major rehab)






Timber plank - replace as required
1 SF $6.00


Timber frame - replace as required
1 SF $6.00


Support structure/footing - repair as required
1 SF $5.50


Site clearing/demolition
1 SF $0.40






$17.90










Boardwalk - timber (routine maintenance)






Timber plank - clean and repair
1 SF $3.00


Timber frame - clean and repair
1 SF $3.00


Support structure/footing - clean and repair
1 SF $3.30


Site clearing/demolition
1 SF $0.40






$9.70










Boardwalk - synthetic (major rehab)






Synthetic plank - replace as required
1 SF $3.75


Synthetic frame - replace as required
1 SF $5.25


Support structure/footing - repair as required
1 SF $5.50


Site clearing/demolition
1 SF $0.40






$14.90










Boardwalk - synthetic (routine maintenance)






Synthetic plank - clean and repair
1 SF $1.88


Synthetic frame - clean and repair
1 SF $2.63


Support structure/footing - clean and repair
1 SF $3.30


Site clearing/demolition
1 SF $0.40






$8.20










Bridge System Maintenance














Bridge - metal (major rehab)






Metal grid panel - replace as required
1 SF $15.00


Metal frame - replace as required
1 SF $13.75


Railing - metal - replace as required
1 SF $16.67


Support structure/footing - repair as required
1 SF $27.50


Site clearing/demolition
1 SF $0.40






$73.32










Bridge - metal (routine maintenance)






Metal grid panel - clean and repair
1 SF $7.50


Metal frame - clean and repair
1 SF $6.88


Railing - metal - clean and repair
1 SF $8.33


Support structure/footing - clean and repair
1 SF $13.75


Site clearing/demolition
1 SF $0.40






$36.86


Bridge - timber (major rehab)






Timber plank
1 SF $6.00


Timber frame
1 SF $6.00


Railing - timber
1 SF $12.50


Support structure/footing
1 SF $6.88


Site clearing/demolition
1 SF $0.40






$31.78










Bridge - timber (routine maintenance)






Timber plank
1 SF $3.00


Timber frame
1 SF $3.00


Railing - timber
1 SF $6.25


Support structure/footing
1 SF $3.44


Site clearing/demolition
1 SF $0.40






$16.09










Bridge - synthetic (major rehab)






Synthetic plank
1 SF $3.75


Synthetic frame
1 SF $5.25


Railing - synthetic
1 SF $9.58


Support structure/footing
1 SF $1.72


Site clearing/demolition
1 SF $0.40






$20.70


Bridge - synthetic (routine maintenance)






Synthetic plank
1 SF $1.88


Synthetic frame
1 SF $2.63


Railing - synthetic
1 SF $4.79


Support structure/footing
1 SF $0.86


Site clearing/demolition
1 SF $0.40






$10.55










Culvert Maintenance














Culvert - 18" dia. (routine maint.)






Culvert - repair and replace as required
1 LF $5.00


Site clearing/demolition
1 LF $0.80






$5.80


Culvert - 18" dia. (major rehab)






Culvert
1 LF $50.00


Grading - fine
1 LF $0.45


Site clearing/demolition
1 LF $0.80






$51.25


Culvert - 24" dia. (routine maint.)






Culvert - repair and replace as required
1 SF $6.00


Site clearing/demolition
1 SF $1.00






$7.00


Culvert - 24" dia. (major rehab)






Culvert
1 SF $60.00


Grading - fine
1 SF $0.60


Site clearing/demolition
1 SF $1.00






$61.60


Culvert - 36" dia. (routine maint.)






Culvert
1 SF $9.00


Site clearing/demolition
1 SF $1.40






$10.40


Culvert - 36" dia. (major rehab)






Culvert
1 SF $90.00


Grading - fine
1 SF $0.90


Site clearing/demolition
1 SF $1.40






$92.30


Culvert - 48" dia. (routine maint.)






Culvert
1 SF $12.00


Site clearing/demolition
1 SF $1.80






$13.80


Culvert - 48" dia. (major rehab)






Culvert
1 SF $120.00


Grading - fine
1 SF $1.20


Site clearing/demolition
1 SF $1.80






$123.00


Parking Lot Maintenance














Parking lot - asphalt (major rehab)






Asphalt overlay
1 SF $2.85


Striping
1 SF $0.07


Base compaction
1 SF $0.40


Site clearing/demolition
1 SF $0.75






$4.07










Parking lot - asphalt (routine maintenance)






Asphalt - patch and repair
1 SF $1.15


Striping
1 SF $0.07


Site clearing/demolition
1 SF $0.75






$1.97










Parking lot - concrete (major rehab)






Concrete - vehicular
1 SF $10.50


Striping
1 SF $0.07


Base compaction
1 SF $0.40


Site clearing/demolition
1 SF $2.25






$13.22










Parking lot - concrete (routine maintenance)






Concrete - patch and repair
1 SF $3.50


Striping
1 SF $0.07


Site clearing/demolition
1 SF $2.25






$5.82










Parking lot - gravel (major rehab)






Gravel - 4" thk.
1 SF $1.04


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$1.74










Parking lot - gravel (routine maintenance)






Gravel - touch up 2" thk.
1 SF $0.52


Grading - fine
1 SF $0.30


Site clearing/demolition
1 SF $0.40






$1.22










Trailhead Access Road Maintenance














Trailhead - asphalt surface (major rehab)






Asphalt overlay
1 SF $2.85


Base compaction
1 SF $0.40


Entry sign - clean and repair
1 LS $1,500.00


Gate/bollard - repair as required
1 LS $1,250.00


Site clearing/demolition
1 SF $0.75






$23,870.00










Trailhead - asphalt surface (routine maintenance)






Asphalt - patch and repair
1 SF $1.15


Base compaction
1 SF $0.25


Entry sign - clean and repair
1 LS $500.00


Gate/bollard - repair as required
1 LS $750.00


Site clearing/demolition
1 SF $0.75






$12,602.00










Trailhead - concrete surface (major rehab)






Concrete - vehicular
1 SF $10.50


Base compaction
1 SF $0.40


Entry sign - clean and repair
1 LS $1,500.00


Gate/bollard - repair as required
1 LS $1,250.00


Site clearing/demolition
1 SF $0.75






$64,262.00










Trailhead - concrete surface (routine maintenance)






Concrete - patch and repair
1 SF $3.50


Base compaction
1 SF $0.25


Entry sign - clean and repair
1 LS $500.00


Gate/bollard - repair as required
1 LS $750.00


Site clearing/demolition
1 SF $0.75






$25,010.00


Trailhead - gravel surface (major rehab)






Gravel - 4" thk.
1 SF $1.04


Entry sign - clean and repair
1 LS $1,500.00


Gate/bollard - repair as required
1 LS $1,250.00


Site clearing/demolition
1 SF $0.75






$12,195.33










Trailhead - gravel surface (routine maintenance)






Gravel - touch up 2" thk.
1 SF $0.52


Grading - fine
1 SF $0.30


Entry sign - clean and repair
1 LS $500.00


Gate/bollard - repair as required
1 LS $750.00


Site clearing/demolition
1 SF $0.75






$9,539.60










Restroom Maintenance














Restroom building (major rehab)
48 SF



Exterior cleaning and repair
280 SF $1,260.00


Interior - clean and repair
280 SF $1,680.00


Signage - replace
1 LS $750.00


Toilet room accessories - replace
1 EA $1,450.00


Plumbing fixtures - replace as required
1 EA $2,250.00


Connection and piping to existing sewer system
1 ALW $750.00


Floor drain - repair as required
1 EA $750.00


Lighting and controls - replace
48 SF $960.00






$9,850.00










Restroom building (routine maintenance)
48 SF



Exterior - clean and repair
280 SF $700.00


Interior - clean and repair
280 SF $980.00


Signage - replace
1 LS $750.00


Toilet room accessories - replace
1 EA $1,450.00


Plumbing fixtures - repair as required
1 EA $1,125.00


Connection and piping to existing sewer system
1 ALW $750.00


Floor drain - repair as required
1 EA $750.00


Lighting and controls - replace
48 SF $960.00






$7,465.00

Sheet 3: Markup
CONTRACTOR'S MARK-UPS


Markup Description %

General Conditions 10.00%

Overhead &Profit 8.00%

Bonds and Insurance 2.00%




Design Contingency 20.00%


40.00%
TOTAL CONSTRUCTION COSTS




PRE-CONSTRUCTION PLANNING


Description %

Investigation/Remediation 2%

Project planning & scheduling 2%



TOTAL PRE-CONSTRUCTION COST




TOTAL CONSTRUCTION BURDEN










TOTAL CONSTRUCTION COSTS -SOFT COST CALCULATOR




FEE SCHEDULE


Description %

A/E Design Team 12.50%

Geotechnical 0.00%

Survey 2.00%




Permitting and review fees 0.30%

Special Inspections 0.20%

Land Use Approvals 0.00%

Other








15.00%
TOTAL SOFT COSTS







TOTAL CONTRACT BURDEN







OWNER'S PROJECT MANAGEMENT


Description %

A/E Management 15.00%

Pre-Construction Management 15.00%

Construction and Close out Management 3.00%

Community Engagement 1.00%

Administration/ Marketing 0.50%

Consumables 0.10%








34.60%
TOTAL SOFT COSTS




OWNER MANAGED CONTIGENCIES


Description %

Construction Contingency 10.00%

Soft Cost Contingency 3.00%

Construction and Close out Management Contingency 3.00%

Other









TOTAL PROJECT BURDEN


The words contained in this file might help you see if this file matches what you are looking for:

...Sheet summary trail development cost guide for oregon parks and recreation departments scorp project st edition q estimate of probable provided by dcw management note this tool is being as a resource based on construction averages in it does not take recent increases into account grant applicants or anyone else using should consult with local contractors vendors other industry professionals to develop an accurate budget reflective current market rates jb item length width direct incl mark ups total w design permitting etc notes network new mile lf asphalt concrete gravel native surface subtotal system boardwalk structure metal timber synthetic bridge fiberglass culvert quot dia less parking lot stalls x head access roads restroom vault one stall two flush three five six maintenance major rehab routine maint...

no reviews yet
Please Login to review.