ucf planning design construction owner s substantial completion final completion and closeout checklist project manager required for this type of document additional information project photo s photos should represent the ...

icon picture XLSX Filetype Excel XLSX | Posted on 14 Aug 2022 | 3 years ago
Partial file snippet.
                                                                 UCF Planning, Design & Construction
               Owner's Substantial Completion & Final Completion and Close-out Checklist
            Project Manager: 
            Required 
            for this   Type of Document Additional Information
            Project?
                       Photo(s)                Photos should represent the 
                       Representative of       completed project and be free of 
                       Completed Project       construction debris or people.
                       Certificate of          Received from Building Code 
                       Completion              Office
                       Certificate of          Received from Building Code 
                       Occupancy               Office
                                               History of inspection results 
                       Proof of Passed         showing passed final inspections 
                       Building Inspections    from BCO's Citizenserve site or 
                                               both sides of signed off permit 
                                               card.
                       Proof of Passed State 
                       Fire Marshal            Received from State Fire Marshal
                       Inspection
                                               Punch List should denote all 
                                               work not conforming to contract 
                       Punch List              specifications that the 
                                               contractor must complete prior 
                                               to final payment. 
                       Final Completed         Provided puchlist should indicate 
                       Punch List              all punch list items are 
                                               complete.
                       Architect Record of     AIA Document G704, fully 
                       Certificate of          executed by A/E, Owner 
                       Substantial             (Director of FPC) and Contractor.
                       Completion
                                               Signed and sealed letter from all 
                                               project Architects and Engineers 
                                               of Record attesting that all 
                       CD Changes              required changes to 
                       Submitted to BCO for  Construction Documents due to 
                       Review                  ASIs and CCDs have been 
                                               incorporated into submitted 
                                               revisions reviewed and 
                                               approved by the Building Code 
                                               Office
                                               Signed and sealed letter from 
                       EOR Confirms Arc        the EOR or CXA that Arc Flash 
                       Flash Studies           calculations and coordination 
                                               studies have been completed 
                                               and labels have been installed
                       Arc Flash               Arc Flash Coordination Studies
                       Coordination Studies
                       Lightning Protection    Lightning Protection Certificate
                       Certificate
                       Agenda from Close-      Close-out Agenda_UCF-583
                       out Meeting
                     Close-out Meeting 
                     Minutes
                     Close-out Meeting 
                     Attendance Sheet
                     Final Test and Balance EOR Approval Affixed to the 
                     with EOR Approval    Final T & B Report
                                          A zip file that contains the 
                                          Preliminary Commissioning 
                                          Issues Log, and a letter from the 
                                          Engineer of Record, the Cx 
                     Preliminary          Agent and UES indicating that 
                     Commissioning zip    the systems to be commissioned 
                     file                 have been tested and the 
                                          commissioning report has been 
                                          submitted with issues, issue 
                                          status, and contractual 
                                          completions dates.
                     Commissioning Issues 
                     Log 
                                           Letter from the Engineer of 
                                          Record, the Cx Agent and UES 
                     Letters from EOR,    indicating that the systems to 
                     CXA and UES that CX  be commissioned have been 
                     Systems are          tested and the commissioning 
                     operating as noted.  report has been submitted with 
                                          issues, issue status, and 
                                          contractual completions dates.
                                          Letter from the Commissioning 
                                          Agent attesting that 
                                          commissioning testing is 100% 
                                          complete for the laboratory-type 
                                          spaces and that commissioning 
                     Letter from Cx Agent  is non-laboratory type spaces is 
                     indicating           substantially complete and that 
                     Commissioning        the preliminary commissioning 
                     testing is complete  report has been approved by the 
                                          Engineer of Record. A schedule, 
                                          including all remaining 
                                          commissioning activities, is 
                                          submitted, and completion is 
                                          tied to Contract Final Completion 
                                          date
                                           Building envelope report with 
                                          affixed letter from Building 
                     Building Envelope    Envelope Consultant stating that 
                     Report and Letter    the roof and building envelope 
                                          are complete as installed and in 
                                          compliance with Contract 
                                          Documents
                                            Every sheet of the complete As-
                                            Built Drawing package must be 
                                            stamped “As-Built” and dated in 
                                            the lower right-hand corner, 
                                            whether or not there are 
                                            changes in that plan sheet. The 
                                            set of As-Built Drawings must be 
                      Contractor's As-Built  a complete package, not just a 
                      zip File              collection of the pages 
                                            containing changes. MEPF 
                                            discipline as-built sets may be 
                                            submitted as individual files that 
                                            are zipped into the primary 
                                            project As-built file. The As-Built 
                                            Drawing Package should NOT 
                                            include extemporaneous 
                                            documents.
                                            Contractor warranties must 
                                            reflect a start date of the 
                                            Certificate of Completion or 
                                            Occupancy date (unless an 
                      Prime Contractor      executed Certificate of 
                      Warranty              Substantial completion indicates 
                                            other start date), specify the 
                                            project, and be signed by an 
                                            authorized representative of the 
                                            company providing the warranty.
                                            Subcontractor warranties must 
                                            reflect a start date of the 
                                            Certificate of Completion or 
                                            Occupancy date (unless an 
                                            executed Certificate of 
                                            Substantial completion indicates 
                      Trade Subcontractor  other start date), specify the 
                      Warranty              project, and be signed by an 
                                            authorized representative of the 
                                            company providing the warranty. 
                                            If more than one trade 
                                            subcontractor warranty, all 
                                            should be named individually, 
                                            be bound together in a zip file 
                                            named as above.
                                            Zip file with a collection of all 
                                            subcontractor warranties. The 
                      Subcontractor         files contained within should be 
                      Warranty Zip File     named per the Trade 
                                            Subcontractor Warranty naming 
                                            standard: WTY_Trade_Contractor 
                                            Name_UCF Project Number
                       Project Asset Table     Project Asset Table should be used to record asset related information which is information that provides operation, maintenance and warranty information for components and equipment added to University property as a result of repair replacement or new construction project and requires care from the Facilities and Safety departments throughout the component or equipment lifecycle. Examples of assets may be see on the first page of the Project Asset Table. Ensure that the format provided is easily legible.
                       Paint Schedule
                                               The Room Paint Matrix or as-built paint schedule should be used to record paint information for projects that alter the paint of University property
                                               All of the individual files for 
                                               manufacturer’s O&Ms and 
                       Manufacturer            warranties for the project should 
                       Warranties and O&M  be compressed into a zip file. 
                       Compressed Zip File     The files within the zip file 
                                               should be named as indicated 
                                               below
                                               Each piece of equipment or 
                                               material should have its own 
                                               warranty and O&M file or one 
                                               combined file if this is how they 
                       Manufacturer O & M  are provided from the 
                       Files                   manufacturer. All of the 
                                               individual files for 
                                               manufacturer’s O&Ms and 
                                               warranties for the project should 
                                               bound together in a zip file.
                                               Each piece of equipment or 
                                               material should have its own 
                                               warranty and O&M file or one 
                                               combined file if this is how they 
                       Manufacturer            are provided from the 
                       Warranty Files          manufacturer. All of the 
                                               individual files for 
                                               manufacturer’s O&Ms and 
                                               warranties for the project should 
                                               bound together in a zip file.
                                               In the case that the 
                                               manufacturer’s warranty and 
                       Combined                O&M is combined in one 
                       Manufacturer O&M        document, the naming 
                       and Warranty Files      convention should reflect this 
                                               and in this case the document 
                                               only needs to be submitted 
                                               once.
The words contained in this file might help you see if this file matches what you are looking for:

...Ucf planning design construction owner s substantial completion final and closeout checklist project manager required for this type of document additional information photo photos should represent the representative completed be free debris or people certificate received from building code office occupancy history inspection results proof passed showing inspections bco citizenserve site both sides signed off permit card state fire marshal punch list denote all work not conforming to contract specifications that contractor must complete prior payment provided puchlist indicate items are architect record aia g fully executed by ae director fpc sealed letter architects engineers attesting cd changes submitted documents due review asis ccds have been incorporated into revisions reviewed approved eor confirms arc cxa flash studies calculations coordination labels installed lightning protection agenda close out meeting minutes attendance sheet test balance approval affixed with t b report a ...