agenda time topic 1 00 1 10 safety meeting objectives timeline objectives meeting approach 1 10 2 45 timeline presentation 1 10 1 25 submit application land review 1 25 ...

icon picture PPTX Filetype Power Point PPTX | Posted on 09 Aug 2022 | 3 years ago
Partial capture of text on file.
                                    Agenda
      Time           Topic
      1:00 – 1:10    Safety, Meeting objectives, Timeline objectives, & Meeting 
                     approach 
      1:10 – 2:45    Timeline presentation
           1:10 – 1:25   Submit Application & Land Review
           1:25 – 1:35   Interconnection Agreement Administered
           1:35 – 2:05   Engineering Review Issued
           2:05 – 2:20   Design
           2:20 – 2:35   Utilities Construction
           2:35 – 2:45   Commissioning
      2:45 – 3:00    Recap & next steps
      2
           Safety – Emergency, Earthquake 
           & Evacuation
In the event of an emergency in the room:
1) Who will dial 3-3622?
2) Who is CPR/AED certified?
In the event of an earthquake: 
If you hear an alarm wait for announcement and instructions
Should we need to evacuate
     1)Exit the room through doors and turn right to 
       the 245 Market main lobby. 
     2)Evacuation location:
        a)Primary meeting location is across the 
           street in Bechtel Plaza
        b)Backup meeting location is Justin Hermann 
In the event of an active shooter:
           Plaza             Get Out, Hide Out, Take Out
               3
              Meeting Objectives
    • Understand the steps from Interconnection 
       application to PTO for Rule 21 projects from 
       both the utility and developer perspectives
    • Identify steps and practices that create the 
       biggest challenges for project interconnection 
       related to timelines
    • Identify inconsistencies across utilities and 
       reasons
    • Agree on next steps to address identified issues
    4
            Timeline objectives
    • Shorten timeline in each step as much as 
      possible
    • Understand the context timelines are 
      provided and what specific things can 
      affect them
    • Discuss how utilities can better set 
      expectations for timing
    5
   Interconnection
   Timelines
    SARAH Cummings       EDUYNG Castano
    JKB Energy           SCE
    ROBERT Chan          JAMES Spurgeon
    PG&E                 SDG&E
The words contained in this file might help you see if this file matches what you are looking for:

...Agenda time topic safety meeting objectives timeline approach presentation submit application land review interconnection agreement administered engineering issued design utilities construction commissioning recap next steps emergency earthquake evacuation in the event of an room who will dial is cpr aed certified if you hear alarm wait for announcement and instructions should we need to evacuate exit through doors turn right market main lobby location a primary across street bechtel plaza b backup justin hermann active shooter get out hide take understand from pto rule projects both utility developer perspectives identify practices that create biggest challenges project related timelines inconsistencies reasons agree on address identified issues shorten each step as much possible context are provided what specific things can affect them discuss how better set expectations timing sarah cummings eduyng castano jkb energy sce robert chan james spurgeon pg e sdg...

no reviews yet
Please Login to review.