                                      1
                                                    Reportable
                        IN THE SUPREME COURT OF INDIA
                         CIVIL APPELLATE JURISDICTION
                        CIVIL APPEAL NOS.8442-8443 OF 2016  
                (Arising out of SLP (C) Nos.9924-9925 of 2013)
            M/S SHANTI CONDUCTORS(P) LTD. ANR.     ………APPELLANTS
                                    Vs.
            ASSAM STATE ELECTRICITY BOARD & ORS.   ……RESPONDENTS
                                    WITH
                        CIVIL APPEAL NO.8445 OF 2016  
                   (Arising out of SLP (C) No.15274 of 2013)
                        CIVIL APPEAL NO.8448 OF 2016  
                   (Arising out of SLP (C) No. 9898 of 2014)
                                      AND
                        CIVIL APPEAL NO.8450 OF 2016  
                   (Arising out of SLP (C) No. 538 of 2016)
                              J U D G M E N T
              V. GOPALA GOWDA, J. 
                   Leave granted in all the Special Leave
              Petitions. 
              2. The present appeals were listed together as a
              common question of law arises in all of them for
                                                          Page 1
                                       2
              consideration before this Court. 
              3. For the sake of convenience, reference is made
              to the facts of the appeals arising out of SLP
              (C) Nos. 9924-9925 of 2013, which have been
              directed against the impugned final judgment and
              orders dated 20.11.2012 and 20.12.2012 passed in
              RFA No. 66 of 2000 and MC No. 3472 of 2012
              respectively,   by   the   Gauhati   High   Court   at
              Guwahati. 
                    The facts of the case which are required to
              appreciate the rival legal contentions advanced
              on behalf of the parties are stated in brief as
              under: 
                     On 31.03.1992, the respondent-Assam State
              Electricity Board (hereinafter referred to as the
              “Electricity Board”) placed an order for supply
              of   Aluminium   Electrical   Conductors   from   the
              appellants-M/s Shanti Conductors Pvt. Ltd. for a
              total   consideration   of   Rs.   1.22   crores.   The
              supplies   were   to   be   made   between   June   and
              December, 1992. On 13.05.1992, another order was
                                                          Page 2
                                                                                        3
                                placed by the Electricity Board to M/s Shanti
                                Conductors for the supply of various types of
                                conductors for a total consideration of Rs. 32.49
                                lacs. The supplies of the aforesaid goods were to
                                be made between January and February, 1993. 
                                4.            On   23.09.1992,   the   President   of   India
                                     promulgated an ordinance, namely, the Interest
                                     on Delayed Payment to Small Scale Ancillary
                                     Industrial   Undertakings   Ordinance,   1992.
                                     Subsequently, on 02.04.1993, the Interest on
                                     Delayed Payment to Small Scale and Ancillary
                                     Industrial Undertakings Act, 1993 (in short the
                                     “Act”) was enacted and it was deemed to have
                                     come into force with effect from 23.09.1992.
                                 
                                5.     Meanwhile, the supply of equipments under the
                                     aforesaid purchase orders was completed by M/s
                                     Shanti Conductors on 04.10.1993. On 05.03.1994,
                                     the entire payment of Rs. 2.15 crores against
                                     the aforesaid supply orders was received by M/s
                                     Shanti Conductors.    
                                                                                                                                    Page 3
                                                                                        4
                                6.           Subsequently,   on   10.01.1997,   M/s   Shanti
                                     Conductors   filed   a   suit   for   recovery   of
                                     Rs.53.68 lacs on account of interest on delayed
                                     payments and future interest at the rate of 27%
                                     per   annum   on   the   decreetal   amount.     The
                                     Electricity Board filed the written statement
                                     on 16.09.1998, inter-alia, raising the plea of
                                     limitation and contending that the Act is not
                                     applicable to the case of the appellant- M/s
                                     Shanti Conductors as the contract was concluded
                                     prior to the enactment of the Act. The Trial
                                     Court   decreed   the   suit   on   02.02.2000   for
                                     recovery of the amount of Rs. 51,60,507.42 with
                                     compound interest at the rate of 23.75% p.a.
                                     with monthly rests from the date of the suit
                                     till realization.
                                7.     Aggrieved of the impugned judgment and order,
                                     the   Electricity   Board   filed   Regular   First
                                     Appeal No. 66 of 2000 before the High Court of
                                     Gauhati.   Vide   order   dated   18.10.2001,   the
                                     Division Bench of the High Court referred the
                                                                                                                                    Page 4
The words contained in this file might help you see if this file matches what you are looking for:

...Reportable in the supreme court of india civil appellate jurisdiction appeal nos arising out slp c m s shanti conductors p ltd anr appellants vs assam state electricity board ors respondents with no and j u d g e n t v gopala gowda leave granted all special petitions present appeals were listed together as a common question law arises them for page consideration before this sake convenience reference is made to facts which have been directed against impugned final judgment orders dated passed rfa mc respectively by gauhati high at guwahati case are required appreciate rival legal contentions advanced on behalf parties stated brief under respondent hereinafter referred placed an order supply aluminium electrical from pvt total rs crores supplies be between june december another was various types lacs aforesaid goods january february president promulgated ordinance namely interest delayed payment small scale ancillary industrial undertakings subsequently act short enacted it deemed come ...

no reviews yet
Please Login to review.