KEMENTERIAN KETENAGAKERJAAN R.I | ||||||
DIREKTORAT JENDERAL PEMBINAAN PELATIHAN DAN PRODUKTIVITAS | ||||||
BALAI BESAR PENGEMBANGAN LATIHAN KERJA | ||||||
Jalan Guntur Raya Nomor. 1 Bekasi Telepon 021-8841147, Faksimile 021-8841146 | ||||||
HARGA PERKIRAAN SENDIRI | ||||||
PENGADAAN PEKERJAAN PEMBUATAN MEDIA PROMOSI PELATIHAN | ||||||
BERUPA PEMBUATAN PANEL SPANDUK, PIGURA SERTA MAKET MASTERPLAN | ||||||
PADA BALAI BESAR PENGEMBANGAN LATIHAN KERJA BEKASI | ||||||
TAHUN ANGGARAN 2018 | ||||||
Volume | Satuan | |||||
No | Uraian Pekerjaan | Hari | Jumlah Harga | |||
1 | Pekerjaan X-Banner Ilustrasi Sign Bangunan pada BBPLK Bekasi Tahun 2018 | 2 | Unit | 659,200 | 1,318,400 | |
Spesifikasi | ||||||
- Ukuran 0.6 x 1.6 m | ||||||
- Finish Laminating Glossy | ||||||
2 | Pekerjaan Pigura Master Plan pada BBPLK Bekasi Tahun 2018 | 1 | Unit | 2,900,000 | 2,900,000 | |
Spesifikasi | ||||||
- Ukuran 128 x 88 cm | ||||||
- Finish Laminating Glossy | ||||||
3 | Pekerjaan Pigura Ruang Inovation Center pada BBPLK Bekasi Tahun 2018 | 1 | Unit | 2,900,000 | 2,900,000 | |
Spesifikasi | ||||||
- Ukuran 125 x 85 cm | ||||||
- Finish Laminating Glossy | ||||||
4 | Pekerjaan Makket Master Plan pada BBPLK Bekasi Tahun 2018 | 1 | Unit | 35,000,000 | 35,000,000 | |
Spesifikasi | ||||||
- Ukuran 125 x 122 cm | ||||||
5 | Pekerjaan Pembuatan Panel Spanduk pada BBPLK Bekasi Tahun 2018 | 1 | Unit | |||
a. Pekerjaan Persiapan | ||||||
Pemasangan Bowplank/Pengukuran | 1 | Ls | 150,000 | 150,000 | ||
P3K dan Keamanan | 1 | Ls | 150,000 | 150,000 | ||
b. Pekerjaan pondasi | ||||||
Pekerjaan pondasi | 14 | Titik | 275,811 | 3,861,360 | ||
c. Pekerjaan pembesian | ||||||
Pekerjaan pembesian rangka baja ringan C75 ( Double Truss ) | 66 | M² | 297,341 | 19,624,506 | ||
d. Pekerjaan Spanduk | ||||||
Pekerjaan finishing spanduk | 132 | M² | 50,000 | 6,600,000 | ||
TOTAL | 72,504,266 | |||||
PPN 10 % | 7,250,427 | |||||
JUMLAH TOTAL | 79,754,693 | |||||
DIBULATKAN | 79,754,693 | |||||
Pejabat Pembuat Komitmen | ||||||
Fadilah Hakim, ST | ||||||
NIP. 19760129 200712 1 001 |
Analisa Harga Taksir | ||||||
Taksir | Roll up Banner per Pcs | |||||
No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
A | TENAGA | |||||
Desainer | OH | 1.000 | 250,000.00 | 250,000.00 | ||
Jumlah Tenaga Kerja | 250,000.00 | |||||
B | BAHAN | |||||
Albetros | Unit | 0.960 | 270,000.00 | 259,200.00 | ||
Rangka Roll up banner | Unit | 1.000 | 150,000.00 | 150,000.00 | ||
Jumlah Harga Bahan | 409,200.00 | |||||
D | Jumlah (A + B + C) | 659,200.00 | ||||
E | Overhead & Profit (10%) | |||||
F | Harga Satuan Pekerjaan (D+E) | 659,200.00 | ||||
Taksir | Pekerjaan Vigura | |||||
No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
A | TENAGA | |||||
Desainer | OH | 1.000 | 300,000.00 | 300,000.00 | ||
Jumlah Tenaga Kerja | 300,000.00 | |||||
B | BAHAN | |||||
Albetros | M2 | 3.000 | 300,000.00 | 900,000.00 | ||
Frame Vigura Plus kaca | Unit | 1.000 | 1,700,000.00 | 1,700,000.00 | ||
Jumlah Harga Bahan | 2,600,000.00 | |||||
D | Jumlah (A + B + C) | 2,900,000.00 | ||||
E | Overhead & Profit (10%) | |||||
F | Harga Satuan Pekerjaan (D+E) | 2,900,000.00 | ||||
Taksir | Pekerjaan Sticker Papan Nama | |||||
No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
A | TENAGA | |||||
Desainer | OH | 1.000 | 250,000.00 | 250,000.00 | ||
Tukang | OH | 4.000 | 75,000.00 | 300,000.00 | ||
Jumlah Tenaga Kerja | 550,000.00 | |||||
B | BAHAN | |||||
Sticker finishing Laminating Glosy | M | 0.660 | 301,500.00 | 198,990.00 | ||
Jumlah Harga Bahan | 198,990.00 | |||||
D | Jumlah (A + B + C) | 748,990.00 | ||||
E | Overhead & Profit (10%) | |||||
F | Harga Satuan Pekerjaan (D+E) | 748,990.00 | ||||
Taksir | Sticker Penunjuk Arah | |||||
No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
A | TENAGA | |||||
Desainer | OH | 2.000 | 250,000.00 | 500,000.00 | ||
Tukang | OH | 0.080 | 75,000.00 | 6,000.00 | ||
Jumlah Tenaga Kerja | 506,000.00 | |||||
B | BAHAN | |||||
Sticker finishing Laminating Glosy | M | 0.090 | 301,500.00 | 27,135.00 | ||
Jumlah Harga Bahan | 27,135.00 | |||||
D | Jumlah (A + B + C) | 533,135.00 | ||||
E | Overhead & Profit (10%) | |||||
F | Harga Satuan Pekerjaan (D+E) | 533,135.00 | ||||
` | Renovasi Makket | |||||
No. | Uraian | Kode | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
A | TENAGA | |||||
Pembuatan maket | OH | 1.000 | 250,000.00 | 250,000.00 | ||
Jumlah Tenaga Kerja | 250,000.00 | |||||
B | BAHAN | |||||
Vinyl Laminating | M | 0.090 | 500,000.00 | 45,000.00 | ||
Jumlah Harga Bahan | 45,000.00 | |||||
D | Jumlah (A + B + C) | 295,000.00 | ||||
E | Overhead & Profit (10%) | |||||
F | Harga Satuan Pekerjaan (D+E) | 295,000.00 |
PENAWARAN HARGA | |||||||
PENGADAAN PEKERJAAN PEMBUATAN MEDIA PROMOSI PELATIHAN | |||||||
BERUPA PEMBUATAN PANEL SPANDUK, PIGURA SERTA MAKET MASTERPLAN | |||||||
PADA BALAI BESAR PENGEMBANGAN LATIHAN KERJA BEKASI | |||||||
TAHUN ANGGARAN 2018 | |||||||
Volume | Satuan | ||||||
No | Uraian Pekerjaan | Harga Satuan | Jumlah Harga | ||||
1 | Pekerjaan X-Banner Ilustrasi Sign Bangunan pada BBPLK Bekasi Tahun 2018 | 2 | Unit | 659,200 | 1,318,400 | ||
Spesifikasi | |||||||
- Ukuran 0.6 x 1.6 m | |||||||
- Finish Laminating Glossy | |||||||
2 | Pekerjaan Pigura Master Plan pada BBPLK Bekasi Tahun 2018 | 1 | Unit | 2,900,000 | 2,900,000 | ||
Spesifikasi | |||||||
- Ukuran 128 x 88 cm | |||||||
- Finish Laminating Glossy | |||||||
3 | Pekerjaan Pigura Ruang Inovation Center pada BBPLK Bekasi Tahun 2018 | 1 | Unit | 2,900,000 | 2,900,000 | ||
Spesifikasi | |||||||
- Ukuran 125 x 85 cm | |||||||
- Finish Laminating Glossy | |||||||
4 | Pekerjaan Makket Master Plan pada BBPLK Bekasi Tahun 2018 | 1 | Unit | 35,000,000 | 35,000,000 | ||
Spesifikasi | |||||||
- Ukuran 125 x 122 cm | |||||||
5 | Pekerjaan Pembuatan Panel Spanduk pada BBPLK Bekasi Tahun 2018 | 1 | Unit | ||||
a. Pekerjaan Persiapan | |||||||
Pemasangan Bowplank/Pengukuran | 1 | Ls | 150,000 | 150,000 | |||
P3K dan Keamanan | 1 | Ls | 150,000 | 150,000 | |||
b. Pekerjaan pondasi | |||||||
Pekerjaan pondasi | 14 | Titik | 275,811 | 3,861,360 | |||
c. Pekerjaan pembesian | |||||||
Pekerjaan pembesian rangka baja ringan C75 ( Double Truss ) | 66 | M² | 297,341 | 19,624,506 | |||
d. Pekerjaan Spanduk | |||||||
Pekerjaan finishing spanduk | 132 | M² | 50,000 | 6,600,000 | |||
TOTAL | 72,504,266 | ||||||
PPN 10 % | 7,250,427 | ||||||
JUMLAH TOTAL | 79,754,693 | ||||||